Berg v. Kucharo Construction Co.

21 N.W.2d 561, 237 Iowa 478, 1946 Iowa Sup. LEXIS 272
CourtSupreme Court of Iowa
DecidedFebruary 5, 1946
DocketNo. 46805.
StatusPublished
Cited by13 cases

This text of 21 N.W.2d 561 (Berg v. Kucharo Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berg v. Kucharo Construction Co., 21 N.W.2d 561, 237 Iowa 478, 1946 Iowa Sup. LEXIS 272 (iowa 1946).

Opinion

Oliver, J.

Plaintiff is a building contractor. Defendants are construction companies which had a contract for the construction of War Housing Project, Texas 41224, consisting of one hundred twenty-five apartment buildings, referred to as Liberator Village, and another contract for the construction of one hundred thirty-seven houses for Federal Housing Administration at Fort Worth, Texas, referred to as Defense Housing. Plaintiff was first employed by defendants as a carpenter fore *480 man on Liberator Village. Later =he entered into two subcontracts with defendants to do certain parts of the carpenter work upon the Liberator Village project and. the Defense Housing project. Defendants also rented seven electric power saws from plaintiff. • ' "•

This action is in four counts: . ..

Count 1 is for damage to'the-power saws; count 2 is'for the balance of 'the Liberator Village subcontract £>rice; count 3 is for extra work performed on the Liberator Village job; and count 4 is for damages for breach of the Defense Housing subcontract. ' " ." •

On count 1 the jury allowed $375; oh count 2 plaintiff demanded $12,890.84 and was allowed $11,509.73; on ,count 3 he' was allowed $3,340.46; on count 4 he demanded $6,286.75 and was allowed $2,886.93. [These.,allowances, resulted in judgment for plaintiff for $18,112.12, from which defendants have appealed. : ; ..... -

Federal Housing projects are built on a production basis similar to an ass.embly-line plan. One group of • carpenters performs a specific part of the work, such'as setting the floor joists, and moves to the next building to again perform the identical work. Each' following group of workmen,¡does .some, other specific part of the work on each .building.. Thus each carpenter or mechanic does specialized work with .which he becomes, very familiar. Plaintiff testified this method of organization substantially reduces labor costs and that contracts for such projects are figured upon, this -.basis.- . -. .,

Liberator Village subcontract was for the erection of all interior millwork, cabinets and wood trim, application of hardware, fitting and hanging of windows, doors, screens ánd' screen-doors in one hundred twenty-five apartment buildings. The adjusted subcontract price was $29,170. That plaintiff performed this' subcontract is-undisputed.’ The controversy over count 2 involves' the allocation of payments. Defendants made payments for plaintiff on pay rolls," insurance,' taxes,'"etc., on the Liberator Village work, totaling- $34;827.47. Plaintiff separated these payments into ' two parts, charging himself and crediting defendants with $16,745.70- advanced bn the work done under the written ’ contract ánd $18,081.77 on thé extra' *481 work involved in count 3 of the petition. The jury made a special finding that plaintiff had established that the amount of such advancements allocated by plaintiff for necessary expense for the work done under the written contract was correct. Accordingly the jury found plaintiff entitled to $11,509.73 on count 2. The record- does not'show -why the jury reduced the allowance on‘count 2 to this figure.'

The jury made: another special finding that plaintiff had established $18,081.77 to be the reasonable amount of necessary expense for labor, taxes,- social security, and insurance in performing and carrying out extra work on Liberator Village under the oral agreement referred to in count 3. As above noted, plaintiff credited defendants with "that -amount out of the $34,827.42 advanced. -‘Of said $18,081.77, $16,702.15 was for pay roll and the remainder for taxes,' social security, and insurance. Plaintiff’s claim on count 3 is based, upon the claimed unpaid balanée of ten per cent of said labor cost ($16,702.15) for- ‘ overhead and ten per ■ cent for -profit. The jury allowed $3,340.46 on count 3. . •

The basis for plaintiff’s claim in- count 3 for extra work on Liberator Village is as follows:

Under the contract defendants were to have exterior window and door frames and exterior trim set by' others and to furnish the millwork, cabinets, windows, doors, etc., and'plaintiff was to do the interior - finish carpenter work and hang the doors, windows, screens, etc: -At'the-time the written contract was made and plaintiff’s work started,' the'work of the principal contractor on a few of-the buildings had progressed far enough that the same wer-e ready1 for the work under plaintiff’s subcontract. These buildings were in satisfactory condition, as was also the small amount of the interior- millwork which was then on the job.

The buildings later turned over to plaintiff were not in proper condition and much of the millwork and trim’ delivered later was defective or unprocessed. The window and door frames which the job specifications required to be set plumb and level and blocked with wedges were not so set nor blocked. In all of the buildings except the fir st^ few they were made of wet, green lumber that had' warped and twisted out of 'shape. Upon *482 complaint of plaintiff, defendants sent some carpenters to adjust the defects but they were unable to do so satisfactorily. Thereupon defendants told plaintiff to do the work and he would be paid for it; that as long as plaintiff was already working on the windows it would be cheaper and better to have him make the corrections than to send other men to do it. Plaintiff and his men made these corrections by straightening the bowed members, plumbing and leveling the frames and wedging and blocking them and in some eases replacing them. Approximately fifty-five hundred window and door frames were corrected.

Other defects appeared in the windows and window and door frames and defendants again told plaintiff defendants would have to take care of it, that plaintiff should get it done and he would be paid for it. Much of the millwork which the subcontract required defendants to furnish was not properly processed or was not processed at all. When plaintiff showed this to defendants he was told to stop bothering defendants about it, to go ahead and do that and they would pay him for it. Plaintiff then had his workmen reprocess the millwork in his shop. Plaintiff’s shop foremen testified ninety per cent of the shop time was devoted to remilling.

The screens furnished were not the proper size and plaintiff was told to take them to the shop and do that work and defendants would pay plaintiff for it. Plaintiff told Mr. Kucharo it would cost in the neighborhood of $500 to correct a certain shipment of screens. Mr. Kucharo said he thought that would be too much but told plaintiff to go ahead and do it.

The exterior doors were defective. Mr. Kucharo asked plaintiff to put some men on that work and said they were satisfied to have him make some money on that. This required considerable work on five hundred doors.

The baseboards did not comply with specifications. When plaintiff so advised Mr. Kucharo he was told to install them and that if it should be necessary to take them out defendants would take the responsibility. The inspectors for the government required them to be removed and replaced in about sixty of the buildings.

Plaintiff testified also concerning extra work to remedy *483

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Passehl Estate v. Passehl
712 N.W.2d 408 (Supreme Court of Iowa, 2006)
Humiston Grain Co. v. Rowley Interstate Transportation Co.
483 N.W.2d 832 (Supreme Court of Iowa, 1992)
Central Iowa Grading, Inc. v. Ude Corp.
392 N.W.2d 857 (Court of Appeals of Iowa, 1986)
Ida Grove Roofing v. City of Storm Lake
378 N.W.2d 313 (Court of Appeals of Iowa, 1985)
Shinrone, Inc. v. Tasco, Inc.
283 N.W.2d 280 (Supreme Court of Iowa, 1979)
Hetherington Letter Co. v. O. F. Paulson Construction Co.
171 N.W.2d 264 (Supreme Court of Iowa, 1969)
Dopheide v. Schoeppner
163 N.W.2d 360 (Supreme Court of Iowa, 1968)
Central Ready Mix Co. v. John G. Ruhlin Construction Co.
139 N.W.2d 444 (Supreme Court of Iowa, 1966)
Baie v. Nordstrom
29 N.W.2d 211 (Supreme Court of Iowa, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
21 N.W.2d 561, 237 Iowa 478, 1946 Iowa Sup. LEXIS 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berg-v-kucharo-construction-co-iowa-1946.