Perfection Tire & Rubber Co. v. Kellogg-Mackay Equipment Co.

194 Iowa 523
CourtSupreme Court of Iowa
DecidedMarch 7, 1922
StatusPublished
Cited by14 cases

This text of 194 Iowa 523 (Perfection Tire & Rubber Co. v. Kellogg-Mackay Equipment Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perfection Tire & Rubber Co. v. Kellogg-Mackay Equipment Co., 194 Iowa 523 (iowa 1922).

Opinion

De Gjsaff,, J.

On October 7, 1919 the defendant filed statement for a mechanics’ lien in the office of the clerk of the district court of Lee County, Iowa and it is to this lien that plaintiff’s petition relates.

1. Mechanics’ liens: collateral security: retention. of title to improvement. On February' 20, 1918 plaintiff and defendant entered into a written contract under which the defendant agreed to erect and install a system of automatic sprinklers in the plaintiff’s manufacturing plant at Fort Madison, Iowa for the sum of $19,726. It is unnecessary to recite in detail the terms and conditions of the contract. The work was performed according to the contract, and was fully completed August 8, 1919 and was approved as provided by the terms of said contract. The amount due for said work under the contract was not paid by the plaintiff, and after filing the lien by defendant as heretofore stated plaintiff filed its petition in equity to cancel of record said lien. Defendant’s demurrer to said petition was overruled, and defendant then filed its cross-petition to which plaintiff interposed a general equitable demurrer which was sustained. Defendant then filed answer and counterclaim to plaintiff’s petition in which the defendant prayed for judgment against the plaintiff in the sum of $20,801 with interest, which represented the amount due under the written contract for installing the automatic sprinkling system in plaintiff’s factory, and also prayed that the mechanics’ lien be foreclosed against the plaintiff’s real estate therein described and for costs. To this pleading plaintiff filed a motion to strike on the grounds that the counterclaim as filed was identically the same pleading and contained the same matter as the cross-petition formerly filed and to which demurrer had been sustained. This motion was by the court [525]*525sustained and subsequently an order was entered dismissing defendant’s cross-petition and counterclaim and judgment was entered against defendant.

Plaintiff’s position throughout the progress of the case is predicated on the provision of the written contract which reads as follows: “The Kellogg-Mackay Equipment Company retains title to the material and equipment until full cash payment shall have been made therefor, and which, in the meantime, at the option of the Kellogg-Mackay Equipment Company, shall be held on storage as its property, but without any storage charges to it, with the right to the Kellogg-Mackay Equipment Company to enter upon the premises and remove the same in case of any default.” Plaintiff’s petition alleges that the said provision in the contract is collateral security in the. form of conditional sale and does not entitle defendant to a mechanics’ lien.

A statute of this state gives a party who has performed labor or furnished material, machinery or fixtures for any build-ing, erection or other improvement upon land, a right to a mechanics’ lien upon such building, erection or improvement, and upon the land belonging to the owner on which the same is situated, to secure the payment for such labor done or materials, machinery or fixtures furnished. Code Section 3089.

It is further provided that “No person shall be entitled to a mechanic’s lien who, at the time of making or executing a contract for furnishing material or performing labor, or during the progress of the work, erection, building or other improvement, shall take any collateral security on such contract. But after the completion of such work, and when the contractor or other person shall have become entitled to claim or establish a lien, the taking of such or other security shall not affect the right thereto, unless such new security shall, by express agreement, be given and received in lieu of such lien.” Code Section 3088.

We will briefly note the history of oux state legislation on this subject. The Eevised Statutes of the Territory of Iowa of 1843 (Reprint 1912, page 269) contain no provision relative to the waiver of a lien by taking collateral security. In the Code of 1851 (Section 1009) we find this provision: “No per[526]*526son is entitled to a mechanic's lien who takes collateral security on the same contract.” The Revision of 1860 (Section 1845) and the Code of 1878 (Section 2129) contain the same provision. In 1876 the legislature repealed the mechanics’ lien law as it then existed (Chapter 1.00 Acts of the Sixteenth General Assembly) and the present law was enacted and with slight verbal changes appears in the present Code.

A mechanics’ lien is purely statutory, and is in derogation of the common law. In determining the issue in this case it is necessary that we confine ourselves to our statutory provisions in this particular, and the decisions of courts of other states are of little value as precedent unless the cases were decided under statutes similar to our own.

I. The material question on this appeal is: Does the retention of title to the material and equipment by the defendant until the same is fully paid for, with the right reserved in case of default in making any payment on the part of the plaintiff, to take possession and enter the premises to remove the material and equipment, extinguish the vendor’s right to a mechanics’ lien under the provision of Section 3088 of the Code? In other words, is the retention of title under such circumstances the taking of collateral security “on such contract?”

2. Words and phrases: “collateral security.” The word “collateral” in its commonly accepted legal definition means additional security to the principal obligation and subsidiary thereto. The etymology of the word indicates that it is something that runs along with and parallel to something else of a similar character. It is something that stands by the side of the prin-

cipal promise as an additional or cumulative means for securing the payment of the debt. Moffatt v: Corning 14 Colo. 104 (24 Pac. 7). It is a security in addition to the responsibility of the debtor. In re Waddell-Entz Co. 67 Conn. 324 (35 Atl. 257).

. If it were not for the provision contained in the first sentence of Section 3088 a creditor within the purview of the mechanics’ lien statute could have as- many securities for his debt as he can obtain. In the Nebraska statute there is no provision against the taking of collateral security at the time of executing a contract for furnishing material or performing labor or during the progress of the work, and it is said in Great Western Mfg. [527]*527Co. v. Hunter Bros., 15 Neb. 32 (16 N. W. 759) tbat “A creditor may liave as many securities for bis debt as he can obtain.” Under the Michigan statute of like tenor it is said: ‘ ‘ There can be no objection to a creditor’s having more than one security for the same debt.” Peninsular Gen. Elec. Co. v. Norris, 100 Mich. 496 (59 N. W. 151). This latter case refers to Case Mfg. Co. v. Smith, 40 Fed. 339, which construed a Tennessee statute which does not contain a provision against the taking of collateral security. In the Wisconsin statute there is not only an absence of this provision but it provides: "The taking of a promissory note or other evidence of indebtedness for any such work, labor or materials done or furnished shall not discharge the lien therefor hereby given unless expressly received as payment therefor and so specified therein.” Section 3317 Chapter 143 Volume 2. Wisconsin Statutes 1921. See also Cooper v. Cleghorn, 50 Wis. 113 (6 N. W. 491).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Builders Kitchen & Supply Co. v. Pautvein
601 N.W.2d 72 (Supreme Court of Iowa, 1999)
Quirk v. Edwards
504 N.W.2d 879 (Supreme Court of Iowa, 1993)
State v. Iowa District Court for Polk County
492 N.W.2d 666 (Supreme Court of Iowa, 1992)
Clemens Graf Droste Zu Vischering v. Kading
368 N.W.2d 702 (Supreme Court of Iowa, 1985)
Chicago Title Insurance Co. v. Huff
256 N.W.2d 17 (Supreme Court of Iowa, 1977)
Harper v. Ford
179 N.W.2d 772 (Supreme Court of Iowa, 1970)
Central Ready Mix Co. v. John G. Ruhlin Construction Co.
139 N.W.2d 444 (Supreme Court of Iowa, 1966)
In Re Estate of Finch
32 N.W.2d 819 (Supreme Court of Iowa, 1948)
Spangler v. Misner
28 N.W.2d 5 (Supreme Court of Iowa, 1947)
Fitchner v. Walling
279 N.W. 417 (Supreme Court of Iowa, 1938)
Galvin v. Citizens Bank
250 N.W. 729 (Supreme Court of Iowa, 1933)
Fire Protection Co. v. Hawkeye Tire & Rubber Co.
8 F.2d 810 (Eighth Circuit, 1925)
Jaeger v. American Bonding & Casualty Co.
196 Iowa 850 (Supreme Court of Iowa, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
194 Iowa 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perfection-tire-rubber-co-v-kellogg-mackay-equipment-co-iowa-1922.