Stewart v. Cunningham

548 P.2d 740, 219 Kan. 374, 1976 Kan. LEXIS 374
CourtSupreme Court of Kansas
DecidedApril 10, 1976
Docket47,893
StatusPublished
Cited by19 cases

This text of 548 P.2d 740 (Stewart v. Cunningham) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stewart v. Cunningham, 548 P.2d 740, 219 Kan. 374, 1976 Kan. LEXIS 374 (kan 1976).

Opinion

The opinion of the court was delivered by

Fromme, J.:

This is an action to foreclose a contractor’s lien for labor and materials filed pursuant to' K. S. A. 60-1102, against the owners of real property. The owners, Larry and Joleen Cunningham, contracted to construct a motel in Dodge City, Kansas. The con *375 tractor, Edward T. Stewart, contracted to do the plumbing, heating and air conditioning work on this motel. The owners were dissatisfied with the work and on completion of the project refused to make final payment on the contract, which payment was to include “extras” furnished by the contractor under written change orders. The contractor filed suit. The owners counterolaimed for alleged damages arising from loss of revenues caused by delay in completing the work on the motel and for further damages because of inferior work and future expenses necessary to oorrect defects in the work.

After a trial to the court a judgment was entered determining the amount remaining due under the contract ($5,087.93) and ordering foreclosure of the contractors hen. The owners were, denied relief under their counterclaim. The owners appeal. The points raised on appeal depend largely upon the facts developed by the evidence. A recital of the facts surrounding this controversy will be helpful.

In 1971, the owners beoame interested in constructing a motel and discussed their plans with a contractor in York, Nebraska, by the name of Cleveland. Cleveland had constructed a number of motels and he provided the Cunninghams with basic blueprints for the proposed motel. As the discussions between Cleveland and the Cunninghams progressed the two met with Stewart to determine the requirements for plumbing, heating and air conditioning necessary to complete the Cleveland plans. Stewart reviewed the plans and designed the, necessary plumbing, heating and air conditioning with the guidance of Cleveland. The cost was estimated and a bid was submitted of $32,590.00 by Stewart.

The Cunninghams wanted Cleveland to act as general contractor for the construction project. He was unable to do so because of his work schedule. The Cunninghams then employed a local firm, Mid-Way Construction Company, to fill the shoes of Cleveland. Stewart first submitted the $32,590,000 bid on the project to the Cunninghams in writing and Larry Cunningham accepted the, bid by approving the same and affixing his signature.

Thereafter the Cunninghams entered into a contract with MidWay as a general contractor and advised Stewart his plumbing contract should be submitted to Mid-Way and attached to Mid-Way’s construction contract. Payments on all contracts were to be made through Mid-Way as required by the agency financing the. construction of the motel. Stewart complied.

*376 Construction on the motel began in April, 1972, and periodic payments were made by the Cunningham's to Mid-Way. Mid-Way in turn forwarded payments to Stewart for his work. On August 11, 1972, Mid-Way submitted its final request for payment. Payment was made to Mid-Way for the balance due them but the, sum of $3,500.00 was withheld 'by the Cunninghams on Stewarts contract because some of his work remained undone. During the period of construction fourteen “change orders” in writing were made in connection with the plum'bing contract. Most of these, “change orders” were approved as shown by the signatures of either Larry Cunningham or of his father, Earl Cunningham. The $3,500.00 balance on the contract and the amounts due under the change orders, less certain corrections, represent the amount found due. Other evidentiary facts will be developed later as we discuss the points on appeal.

The first point raised by the owners attacks the validity of Stewart’s lien on the motel premises. Our decision on this point depends upon whether Stewart was a contractor or a subcontractor. Although no copy of the lien as filed by Stewart appears in the record on appeal it is conceded the lien was properly filed and recorded in the form required by K. S. A. 60-1102 which covers liens of contractors.

It is further conceded that it was not served upon the owner as required by K. S. A. 1975 Supp. 60-1103 to perfect the lien of a subcontractor.

This subcontractor statute in pertinent part provides:

“. . . The claimant shall either cause a copy of the lien statement to be served personally upon the owner and any party obligated to pay the same in the manner provided for the service of summons within the state by K. S. A. 1965 Supp. 60-304 ... or shall mail a copy of the lien statement to the owner of the property and to any party obligated to pay the same by restricted registered or certified mail, . . .”

At the trial the parties stipulated that the court, in advance of trial, should determine whether Stewart was a contractor and that this factual issue should be determined upon the pleadings and the depositions of both Cunningham and Stewart, which had been taken earlier. The court made the following ruling:

“That the evidence abundantly supports plaintiff’s position that his contract was with Larry Cunningham and was not a sub-contract with Mid-Way Construction Co., Inc.”

The evidence on the issue of whether Stewart was an original contractor or a subcontractor within the meaning of the mechanic’s *377 lien statute is conflicting. The evidence before the trial court shows that Stewart and the owners discussed a contract directly. Stewart made his offer, which was accepted by Larry Cunningham, before any contract was entered between the owners and the general contractor. Although the Stewart contract was eventually included in the Mid-Way contract and Stewart’s progress payments were disbursed through Mid-Way, the owners dealt directly with Stewart during the construction of the motel to request changes and to solve plumbing, heating and air conditioning problems which arose.

A contractor is one who furnishes labor or materials under a contract direct with the owner for the improvement of property. (57 C. J. S., Mechanics’ Liens, § 90, p. 602.)

A subcontractor is one who assumes a portion of a contract from the original contractor or another subcontractor for the performance of all or part of the services or work which the other has obligated himself to perform under contract with the owner. (57 C. J. S., Mechanics’ Liens, § 98, p. 608.)

K. S. A. 1975 Supp. 60-1101 provides:

“. . . When two or more such contracts are entered into applicable to the same improvement, the liens of all claimants shall be similarly preferred to the date of the earliest lien of any of them.”

There can be little doubt that the above statute contemplates that more than one contractor may be employed by one property owner to perform labor or furnish material for the same construction project.

In Toler v. Satterthwaite, 200 Kan. 103, 106, 434 P. 2d 814, it is pointed out that the lien of a subcontractor is created by the statute when said subcontractor has no contract with the owner and is not a direct creditor of the owner of the property. In Toler we say:

“. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. RHF 1
Court of Appeals of Kansas, 2025
Drouhard v. City of Argonia
551 P.3d 156 (Court of Appeals of Kansas, 2024)
Peterson v. Ferrell
349 P.3d 1269 (Supreme Court of Kansas, 2015)
Tarlton v. MILLER'S OF CLAFLIN, INC.
227 P.3d 23 (Court of Appeals of Kansas, 2010)
Alliance Steel, Inc. v. Piland
187 P.3d 111 (Court of Appeals of Kansas, 2008)
Southwest & Associates, Inc. v. Steven Enterprises, LLC
88 P.3d 1246 (Court of Appeals of Kansas, 2004)
State v. Strickland
933 P.2d 782 (Court of Appeals of Kansas, 1997)
Hall v. Add-Ventures, Ltd.
695 P.2d 1081 (Alaska Supreme Court, 1985)
Jackson v. Nangle
677 P.2d 242 (Alaska Supreme Court, 1984)
Calvert Western Exploration Co. v. Diamond Shamrock
675 P.2d 871 (Supreme Court of Kansas, 1984)
Interlake, Inc. v. Kansas Power & Light Co.
644 P.2d 385 (Supreme Court of Kansas, 1982)
Interlake, Inc. v. Kansas Power & Light Co.
644 P.2d 385 (Court of Appeals of Kansas, 1981)
Negley v. Massey Ferguson, Inc.
625 P.2d 472 (Supreme Court of Kansas, 1981)
Dondlinger & Sons' Construction Co. v. Emcco, Inc.
606 P.2d 1026 (Supreme Court of Kansas, 1980)
American Buildings Co. v. Wheelers Stores
585 P.2d 845 (Wyoming Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
548 P.2d 740, 219 Kan. 374, 1976 Kan. LEXIS 374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-v-cunningham-kan-1976.