Maryland Casualty Co. v. City of Tacoma

90 P.2d 226, 199 Wash. 72
CourtWashington Supreme Court
DecidedMay 9, 1939
DocketNo. 27335. Department One.
StatusPublished
Cited by7 cases

This text of 90 P.2d 226 (Maryland Casualty Co. v. City of Tacoma) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. City of Tacoma, 90 P.2d 226, 199 Wash. 72 (Wash. 1939).

Opinion

Jeffers, J.

This is an appeal by Maryland Casualty Company, Glens Falls Indemnity Company, The Steel Tank & Pipe Company of Oregon, Felix Arcorace and Joe Coluccio, copartners, and T. A. Morrey, from judgments rendered in consolidated actions Nos. 78471 and 78581, Pierce county superior court, in favor of Queen City Construction Company, J. F. Bachelor, National Bank of Washington (formerly National Bank of Tacoma) as assignee of J. F. Bachelor, C. S. Barlow & Sons Company, Bergh-Griggs Company, and Frank Sussman. The appeals from judgments in favor of C. S. Barlow & Sons Company and Bergh-Griggs Company have been dismissed.

For brevity, we will hereinafter refer to Maryland Casualty Company and Glens Falls Indemnity Company as sureties, to The Steel Tank & Pipe Company as the Pipe Co., to Felix Arcorace and Joe Coluccio as the copartnership, and to Queen City Construction Company as Queen City.

About January 14, 1936, the Pipe Co. entered into a written contract with the city of Tacoma, whereby it *76 agreed to furnish and install approximately 12,160 feet of steel pipe and to construct certain structures, in accordance with a contract known as Federal docket No. 5594. This was a P. W. A. project, and the total contract price was over two hundred thousand dollars. Maryland Casualty Company and Glens Falls Indemnity Company were joint sureties on the bond of the Pipe Co., and guaranteed the faithful performance of the contract and payment of all laborers, mechanics, subcontractors, and materialmen, and all persons supplying the principal or subcontractors with provisions or supplies for carrying on the work.

On January 18, 1936, the Pipe Co. sublet to the co-partnership all of the work to be done under the general contract, except the fabrication of the pipe and a few minor items. This subcontract provided, among other things, that the work was to be done and the materials furnished in accordance with the plans and specifications of Federal docket No. 5594, which plans and specifications were accepted as a part of the subcontract. It was further provided that the work should be completed within two hundred days from the date of the contract, and that the subcontractors should be responsible for all work to be performed under the contract after the delivery of the pipe by the general contractor. This subcontract was approved by the city of Tacoma and the P. W. A. director.

On May 7, 1936, the copartnership sublet to Queen City the following portions of the general contract: Clearing and grubbing, four thousand dollars; excavation at the rate of one dollar per lineal foot; backfilling at twenty-five cents per lineal foot; and excavation for J street control house, five hundred dollars. This contract further provided that monthly payments should be made, based on the estimates furnished by the city. While this contract was never filed with the city, Queen *77 City was recognized by all parties hereto as a subcontractor and was, in fact, a subcontractor.

On February 21, 1936, the copartnership sublet to J. F. Bachelor the concrete work to be done under the general contract.

The work under the general contract was not completed and accepted by the city until June 14, 1937. The city had retained the sum of $36,211.48, that amount representing fifteen per cent of the contract price; and after these suits were instituted, this sum was paid into court for the benefit of those having unpaid claims for labor and material. Many claims were filed with the city, and liens claimed against the fund. Among these claimants were Queen City, J. F. Bachelor, National Bank of Washington, T. A. Morrey, and Frank Sussman. These claims were all filed within the statutory period.

Controversy having arisen in regard to the claims filed and between the general contractor and the subcontractors, the sureties on the bond of the general contractor brought an interpleader suit in Pierce county, making parties defendant all persons claiming liens, and also the Pipe Co. and the copartnership. Queen City appeared in that action, and by way of answer and cross-complaint, set up its contract with the copartnership and further alleged that its prices were based upon the agreement that the copartnership would furnish full supervision for the work, and that the work would be completed within the two hundred days; that it entered promptly upon the performance of its contract, but that the copartnership did not carry out its part of the agreement, but soon after Queen City had commenced work, the copartnership withdrew practically all supervision from the job; that, by reason thereof, the work was prolonged and Queen City had to furnish additional supervision and incur additional expense; *78 that Queen City was not paid its monthly installments, as provided in the contract; that it was required to do extra work and furnish extra material; that the reasonable value of the labor performed and materials furnished was $32,817.26. Of this amount, Queen City was paid $7,167.02, leaving a balance of $25,815.72, for which amount it filed a claim with the city on April 27, 1937.

The copartnership answered the cross-complaint of Queen City, and admitted that Queen City furnished certain labor and supplies, but denied that the reasonable value of the same was more than $13,173.30; admitted that Queen City furnished other extras which, if allowed by the city, would entitle Queen City to an additional sum of approximately seven thousand dollars. It was further alleged that Arcorace, without the knowledge or consent of his partner Coluccio, and for the purpose of defrauding the copartnership, entered into a secret agreement with Queen City, whereby it was agreed that Arcorace should have twenty-five per cent of the profits made by Queen City on the contract, or if there was a loss, that Arcorace would stand twenty-five per cent of it; that, after this secret agreement was entered into, Arcorace induced Coluccio to sign the contract of May 7th, under which Queen City was to do the work; that Queen City refused to do certain work required of it under the contract and did not diligently and promptly carry out its part of the contract. It was denied that any delay was due to the acts of the copartnership.

The Pipe Co. and the sureties answered the cross-complaint of Queen City, and after denying liability, set up the agreement between Arcorace and Queen City, and alleged that they had no knowledge of this agreement until after the work was completed; that they did not have sufficient information to determine *79 what the effect of this contract would be. They further alleged that Queen City failed, within ten days after the date of the first delivery of material and supplies, to notify the principal contractor.

About the time the action hereinbefore referred to was begun, J. F. Bachelor instituted an action in Pierce county against the city of Tacoma, the Pipe Co., the sureties on the Pipe Co. bond, and the copartnership, alleging therein the execution of the general contract and his subcontract with the copartnership; that he started to perform work under his contract; that thereafter the contract was breached by the copartnership to such an extent that it was impossible for him to further perform his work, and that he was forced to abandon the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norris Industries v. Halverson-Mason Constructors
529 P.2d 1113 (Court of Appeals of Washington, 1974)
Elmore v. Graystone of Centralia, Inc.
399 P.2d 4 (Washington Supreme Court, 1965)
Hendricks v. Dahlgren
323 P.2d 658 (Washington Supreme Court, 1958)
Bank v. Nelson
92 P.2d 711 (Washington Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
90 P.2d 226, 199 Wash. 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-city-of-tacoma-wash-1939.