Austin v. C. v. Wilder & Co.

397 P.2d 1019, 65 Wash. 2d 456, 1965 Wash. LEXIS 734
CourtWashington Supreme Court
DecidedJanuary 7, 1965
Docket37010
StatusPublished
Cited by9 cases

This text of 397 P.2d 1019 (Austin v. C. v. Wilder & Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin v. C. v. Wilder & Co., 397 P.2d 1019, 65 Wash. 2d 456, 1965 Wash. LEXIS 734 (Wash. 1965).

Opinion

Weaver, J.

May 28, 1959, defendant (appellant) Wilder & Co. contracted to construct a sanitary sewer project for the City of Bellingham.

The contract provided:

“The said Contractor [Wilder & Co.] agrees to pay the wages of all persons and for assistance of every kind em *457 ployed upon or about said work, and for all materials purchased therefor, and the City of Bellingham may withhold any and all payments under the contract until satisfied that such wages, assistance and materials have been fully paid for.”

The contract also provided that:

. . The Contractor [Wilder & Co.] shall not assign or transfer the contract for this improvement or sub-let any of the work embraced in it without the written consent of the Board of Public Works.” (Italics ours.)

June 15, 1959, Wilder & Co. entered into a subcontract with Glen Eyerly to do certain drilling and blasting for the sewer project. This subcontract was made without the written consent of the Board of Public Works of the city as required by the terms of the prime contract quoted supra.

Eyerly ordered blasting and other supplies from plaintiff Austin. The materials were delivered, invoiced, and billed to Eyerly. Plaintiff Austin knew that Eyerly was a subcontractor of Wilder & Co. Subsequently, Eyerly became bankrupt without having paid the amount he owed plaintiff.

Plaintiff Austin (the materialman) commenced this action against defendant Wilder & Co. (the prime contractor) for materials delivered to Eyerly (the subcontractor). This action does not involve the prime contractor’s performance bond, the City of Bellingham, or any percentage of the contract payment that might have been retained by the city. Defendant appeals from a money judgment against it.

This appeal brings into sharp focus the application of RCW 39.08.065 to the facts. RCW 39.08.065, omitting provisions not material here, provides:

“Every person [Plaintiff Austin] . . . furnishing materials . . . to be used in the construction . . . of any work for the . . . city [of Bellingham] . . . shall, not later than ten days after the date of the first delivery of such materials ... to any subcontractor [Eyerly] or agent . . . having a subcontract [Eyerly] for the construction . . . deliver or mail to the contractor [Defendant Wilder & Co.] a notice in writing stating in substance and effect that such person [Plaintiff Austin] . . . has commenced to deliver materials . . . and that such *458 contractor [Defendant Wilder & Co.] and his bond will be held for the payment of the same, and no suit or action shall be maintained in any court against the contractor [Defendant Wilder & Co.] or his bond . . . unless the provisions of this section have been complied with.” (Italics ours.)

It is admitted that plaintiff did not give written notice to defendant as required by the statute.

This statute has been before the court on a number of occasions. It would not be accurate to say that we find the decisions completely consistent in all facets of the statute’s application to the varying factual situations discussed therein.

In our analysis of the cases we start with the proposition that the legislature, by enacting RCW 39.08.065, has given us a guideline by which to determine when a materialman may recover from a prime contractor for materials delivered to a subcontractor. The purpose of the written notice is to enable the prime contractor to protect himself against the obligations of the subcontractor, so that he may not be compelled to pay twice for the same materials. Cascade Lbr. & Shingle Co. v. Wright, 99 Wash. 421, 426, 169 Pac. 833 (1918). Absent the 10-day statutory written notice the prime contractor is protected against a suit by a materialman of a subcontractor unless the prime contractor has waived his rights under the statute, or, by his action, misled the materialman.

In Ledingham v. Blaine, 105 Wash. 253, 177 Pac. 783 (1919), the materialman of a subcontractor was denied recovery against the prime contractor and his bondsman; he had failed to give the statutory notice. Cf. Denham v. Pioneer Sand & Gravel Co., 104 Wash. 357, 176 Pac. 333 (1918).

Niemi v. Brewster, 154 Wash. 181, 281 Pac. 488 (1929) and Maryland Cas. Co. v. Tacoma, 199 Wash. 384, 92 P. (2d) 203 (1939), illustrate the correct application of RCW 39.08-.065 to the facts of the instant case. In both cases the materialman of a subcontractor was denied recovery against the prime contractor because the statutory 10-day notice was not given.

*459 Apparent inconsistencies, to which we have alluded, spring from language, quoted out of context or unnecessary to the decision, discussing the question of whether the prime contractor has waived the 10-day notice provision of the statute under the varying factual pattern of each particular case. Generally, there are two fact patterns to which the statute is not applicable. The first is the situation in which the subcontractor is made the agent of the contractor by the prime contract. The cases refer to this as a waiver. Both Niemi, supra, and Maryland Cas., supra, recognize that the notice required by the statute may be waived. In Niemi the court said:

. . the burden was upon Niemi [the materialman] to show facts constituting such waiver by Brewster [the prime contractor].”

Hence, deliveries made by a materialman to the agent would be deliveries to the prime contractor for which he would be liable, and the statute under discussion would not apply. Rachow v. Philbrick & Nicholson, 148 Wash. 214, 268 Pac. 876 (1928); Maeder Steel Products Co. v. Brewster, 154 Wash. 120, 281 Pac. 14 (1929); and Union Oil Co. of California v. Turner, 34 Wn. (2d) 25, 207 P. (2d) 733 (1949), are illustrative. In each, the prime contract provided in substance:

“ ‘All subcontractors shall be considered the agent of the contractor and the latter shall be responsible for all work and material furnished and any indebtedness incurred by such agent.'" (Italics ours.)

Thus the prime contractor waived the requirement of the 10-day statutory notice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell Crane & Rigging Services, Inc. v. Dynamic International AK, Inc.
186 P.3d 1193 (Court of Appeals of Washington, 2008)
LRS Electric Controls, Inc. v. Hamre Construction Inc.
153 Wash. 2d 731 (Washington Supreme Court, 2005)
LRS Electric Controls, Inc. v. Hamre Const., Inc.
107 P.3d 721 (Washington Supreme Court, 2005)
LRS Electric Controls, Inc. v. Hamre Construction, Inc.
82 P.3d 248 (Court of Appeals of Washington, 2004)
LRS Elec. Controls, Inc. v. HAMRE CONST., INC.
82 P.3d 248 (Court of Appeals of Washington, 2004)
Better Financial Solutions, Inc. v. Transtech Electric, Inc.
51 P.3d 108 (Court of Appeals of Washington, 2002)
National Concrete Cutting, Inc. v. Northwest GM Contractors, Inc.
107 Wash. App. 657 (Court of Appeals of Washington, 2001)
Nat. Concrete Cutting v. Nw Gm Contractors
27 P.3d 1239 (Court of Appeals of Washington, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
397 P.2d 1019, 65 Wash. 2d 456, 1965 Wash. LEXIS 734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-v-c-v-wilder-co-wash-1965.