Maeder Steel Products Co. v. Brewster

281 P. 14, 154 Wash. 120, 1929 Wash. LEXIS 991
CourtWashington Supreme Court
DecidedOctober 9, 1929
DocketNo. 21558. Department Two.
StatusPublished
Cited by4 cases

This text of 281 P. 14 (Maeder Steel Products Co. v. Brewster) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maeder Steel Products Co. v. Brewster, 281 P. 14, 154 Wash. 120, 1929 Wash. LEXIS 991 (Wash. 1929).

Opinion

Millard, J.

The work covered by a contract between J. M. Brewster and the state for clearing, grading and construction of a certain state road was completed in September, 1926, and accepted by the state. The Fidelity & Casualty Company of New York was the surety upon the contractor’s bond to the state. Brewster entered into several subcontracts, one of which was with B. Gr. Henley, for the construction of a portion of the road. A copy of the subcontract with Henley was filed with the state resident engineer, who notified the district engineer of such filing. A copy of the subcontract was not, however, filed with the state highway engineer at Olympia. Brewster was advised by the resident engineer at South Bend, in a letter dated February 18, 1926, that the subcontractor would not be recognized:

*122 “Received your copy of the subcontract with B. GL Henley. As before stated, the state highway department does not recognize any subcontractor and will expect the work to be carried on as specified by your contract. If, at any time, we find that the work is not being done satisfactorily, you will be expected to terminate the subcontract and complete the work yourself.”

Henley contracted with Maeder Steel Products Company for steel; with the Longview Concrete Pipe Company for culvert pipe, gravel and cement; and with the Brookfield Quarry & Towage Company for transportation of gravel. The three companies named instituted actions against the contractor, the bond and the reserved fund held by the state. The causes were tried to the court without a jury, resulting in judgments in favor of the claimants. Brewster and his surety have appealed from the three judgments, which, by stipulation, have been consolidated for the purpose of this appeal.

Appellants argue that the Maeder Steel Products Company is not entitled to' recover because of failure to give to the principal contractor the ten days’ notice required by Rem. Comp. Stat., § 1159-1.

The contract between the principal contractor and the state provides that,

“The contractor shall not let, assign, or transfer this contract, or any interest therein or any part thereof, without the consent, in writing, of the state highway engineer. The contractor shall give personal attention to the work at all times, and shall be present, either in person or by duly authorized representative, on the site of the work continually during its progress, and shall receive instructions from the state highway engineer. Any subcontractor shall be considered the agent of the contractor, and the latter shall be responsible for any indebtedness incurred by such agent. If any subcontractor fails to perform his work in a satis *123 factory manner, his subcontract may be terminated by the state highway engineer.”

The trial court held it was unnecessary for the claimant to give to the principal contractor notice of the furnishing of the steel in view of the foregoing provision of the contract; that the purported subcontract with Henley did not become a subcontract, as it was not consented to in writing by the state highway engineer, and that Henley was the agent of Brewster for the purpose of contracting for the purchase of the steel that went into the road.

In Cascade Construction Co. v. Snohomish County, 105 Wash. 484, 178 Pac. 470, it is stated:

The provision in the original contract that the contractor shall not let, assign, or sublet the work provided to be done, or any part thereof, without the consent of the board, and that the contractor shall file with the board a duplicate of all contracts made by him as aforesaid, was for the protection not only of the board itself, but of all persons who furnished supplies, material and provisions for the work to be done; and since that contract was not filed with the board as the original contract required, it gives no notice to persons furnishing material or supplies that they were not furnishing such supplies for the original contractor, whose contract was on file. When the original contractor fails to file his subcontract he thereby waives the right to the notice required by Bern. Code, §1159-1.”

We held in the recent case of Rachow v. Philbrick & Nicholson, 148 Wash. 214, 268 Pac. 876, that, where a subcontract was entered into with the principal contractor without the consent of the state, such subcontractor was the agent of the principal contractor and the principal contractor would be responsible for any indebtedness contracted by such agent. In that case, Judge Tolman, speaking for the court, said:

*124 “A provision in a contract, such as we have here, is not made for the protection of the state alone, but also for the protection of those furnishing material. The state has an interest in seeing that the material going into its work is paid for; that its citizens are not deprived of their just dues, and that no causes for dissatisfaction and litigation shall arise to the embarrassment or loss of any concerned in completing the work.”

Henley was not recognized by the state as a subcontractor. The resident engineer treated him as an agent or representative of the principal contractor. True, Brewster filed with the resident engineer a copy of his subcontract with Henley, but no copy was filed with the state highway engineer, nor did the state highway engineer ever consent to the making of such subcontract. Brewster was positively and clearly informed that the state highway department would “not recognize any subcontractor.” Manifestly Henley acted solely in the capacity of agent for Brewster, the principal contractor; therefore, Brewster is responsible for any indebtedness contracted by Henley in the purchase of steel for road construction; and the trial court correctly held that notice to the principal contractor was not essential to the establishing of respondent’s claim.

"We are convinced by our examination of the evidence brought here in the statement of facts that the respondent made a good faith delivery to Henley, at Deep River, of steel on the order of Henley, and that the steel was used in the construction of the road. Respondent cut and bent, according to specifications prepared by the state resident engineer, twenty thousand pounds of reinforcing steel. That steel was shipped by steamer from Portland, consigned to B. Gr. Henley, Deep River, Washington, a point one and one-half miles from the nearest point on the state road under construction by Henley for Brewster. The bills *125 of lading disclose delivery to the carrier at Portland. There is not the slightest intimation of fraud between the respondent and the contractor’s agent, Henley. There is evidence that the steel was used in the construction of the road. Brewster, while denying that all of the steel was used, admits in his letter of June 23, 1926, to the respondent, that the steel was shipped to, and received by, Henley:

“The steel that you shipped Mr. Henley has not been used with the exception of a very small portion. I am giving Henley every opportunity and all the assistance possible in order that he can finish his contract, and pay his bills.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W. P. Simpson Co. v. Crompton-Richmond Co.
210 So. 2d 467 (District Court of Appeal of Florida, 1968)
Austin v. C. v. Wilder & Co.
397 P.2d 1019 (Washington Supreme Court, 1965)
Union Oil Co. v. Turner
207 P.2d 733 (Washington Supreme Court, 1949)
Hamilton v. Whittaker
186 P.2d 609 (Washington Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
281 P. 14, 154 Wash. 120, 1929 Wash. LEXIS 991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maeder-steel-products-co-v-brewster-wash-1929.