Rachow v. Philbrick & Nicholson

268 P. 876, 148 Wash. 214, 1928 Wash. LEXIS 865
CourtWashington Supreme Court
DecidedJune 25, 1928
DocketNo. 21044. Department One.
StatusPublished
Cited by10 cases

This text of 268 P. 876 (Rachow v. Philbrick & Nicholson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rachow v. Philbrick & Nicholson, 268 P. 876, 148 Wash. 214, 1928 Wash. LEXIS 865 (Wash. 1928).

Opinion

Tolman, J.

Appellant Philbrick & Nicholson, Inc., contracted with the state through its highway committee to clear, grade and construct a certain state highway. Appellant Maryland Casualty Company became the surety on the contractor’s bond given to the state. After the work was completed and accepted by the state, thirteen separate actions were commenced in the superior court for Thurston county against the contractor, the bond and the reserve fund in the hands of the state. Eleven of these actions were to recover for material and supplies furnished to and through respondents Eachow and A. E. Wilber, who had entered into written subcontracts, and the remaining two were upon the claims of the respondents last named.

The actions were tried together to the court sitting without a jury, resulting in judgments against the contractor and the surety, and they have appealed from four of these judgments only. By stipulation, these *217 four cases are consolidated for the purpose of this appeal.

In the interest of clarity and brevity, we will state only such facts as are necessary to an understanding of each point raised, in conjunction with the point discussed. '

(1) Those here claiming for materials furnished, filed their claims with the state highway department, and afterwards, but within thirty days after the completion and acceptance of the work, again filed substantially the same claims. The actions were commenced within four months after the last filing. Appellants contend that the claimants were bound by the first filing in each instance, and that suits not having been commenced within four months after the first filing, the bond is released, or in other words, that by re-filing their claims the claimants cannot extend the period fixed by the statute, and are bound by their first act of filing. We seem never to have passed upon this identical question, but it involves exactly the same principle as the taking of appeals and the filing of mechanics’ liens and we think we cannot sustain appellants ’ contentions without, in effect, overruling Lindley v. McGlauflin, 58 Wash. 636, 109 Pac. 118; Sligh v. Shelton Southwestern R. Co., 20 Wash. 16, 54 Pac. 763; Tatum v. Geist, 40 Wash. 575, 82 Pac. 902; Carstens & Earles v. Seattle, 84 Wash. 88, 146 Pac. 381.

We conclude that this objection is not well taken.

(2) The claimants furnishing material to and through respondents Bachow and A. E. Wilber, who had entered into written subcontracts with the principal contractor, did not give to the principal contractor a ten days’ notice as provided for in Bern. Comp. Stat., § 1159-1 [P. C. § 9725]. The omission to give the statutory, or any notiee, was by the trial court held immaterial because of a certain provision of the *218 contract between tbe principal contractor and the state which reads:

“Besponsibility Non-Transperrable :
“XIII. The contractor shall not let, assign, or transfer this contract, or any interest therein or any part thereof, without the consent, in writing of the State Highway Engineer.
“The contractor shall give his personal attention to the work at all times, and shall be present, either in person or by duly authorized representative, on the site of the work continually during its progress, and shall receive instructions from the State Highway Engineer. Any sub-contractor shall be considered the agent of the contractor, and the latter shall be responsible for any indebtedness incurred by such agent. If any sub-contractor fails to perform his work in a satisfactory manner, his sub-contract may be terminated by the State Highway Engineer”

and because it was stipulated that the state never in any way consented to or recognized the subcontracts.

Appellants and amicus curiae argue with much confidence and considerable force that our cases of Crane Co. v. Maryland Casualty Co., 102 Wash. 59, 172 Pac. 866, and Cascade Construction Co. v. Snohomish County, 105 Wash. 484, 178 Pac. 470, are not decisive upon this question, and that, if as they contend, this provision was inserted in the contract for the benefit of the state alone, respondents cannot claim protection thereunder.

The bond here involved was a statutory bond and its terms applicable to the question now under consideration seem to be identical with the provisions of the bonds considered in the cases cited. The contract here does not require the filing of the subcontracts with the state, but, in view of the conditions already quoted, we cannot now see that this difference warrants any distinction. In the Crane Company case, the question of the giving of the ten days’ notice was not raised. *219 Hence, that case may not be directly in point upon that issue, but in the Cascade Construction Co. case, the failure to give the ten days’ statutory notice was directly raised and relied upon, and after analyzing the holding in the Crane case, this court there said:

“What was meant there was that, so far as the original contractor and the surety upon that contract were concerned, Musgrave and Blake were agents of the original contractor for the purpose of purchasing supplies used in the building. There was no question of notice in that case, and the use of the word ‘subcontractors’ was to denote agency, as the whole context indicates. In so far as these claimants are concerned, under the facts in this appeal, the subcontract as to them was of no force. The provision in the original contract that the contractor shall not let, assign or sublet the work provided to be done, or any part thereof, without the consent of the board, and that the contractor shall file with the board a duplicate of all contracts made by him as aforesaid, was for the protection not only of the board itself, but of all persons who furnished supplies, material and provisions for the work to be done; and since that contract was not filed with the board as the original contract required, it gave no notice to persons furnishing material or supplies that they were not furnishing such supplies for the original contractor, whose contract was on file.
“When the original contractor fails to file his subcontract he thereby waives the right to the notice required by Bern. Code, § 1159-1.”

This language answers every contention now made, and holds directly that a provision in the contract, such as we have here, is not made for the protection of the state alone, but also for the protection of those furnishing material. The state has an interest in seeing that the material going into its work is paid for; that its citizens are not deprived of their just dues, and that no causes for dissatisfaction and litigation shall arise to the embarrassment or loss of any concerned in com *220 pleting the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airefco, Inc. v. Yelm Community Schools No. 2
758 P.2d 996 (Court of Appeals of Washington, 1988)
Shope Enterprises, Inc. v. Kent School District
702 P.2d 499 (Court of Appeals of Washington, 1985)
Austin v. C. v. Wilder & Co.
397 P.2d 1019 (Washington Supreme Court, 1965)
Hamilton v. Whittaker
186 P.2d 609 (Washington Supreme Court, 1947)
Maryland Casualty Co. v. City of Tacoma
92 P.2d 203 (Washington Supreme Court, 1939)
H. Earl Clack Co. v. Staunton
72 P.2d 1022 (Montana Supreme Court, 1937)
Western Steel Casting Co. v. Edland
61 P.2d 155 (Washington Supreme Court, 1936)
Lidral-Wiley, Inc. v. United States Fidelity & Guaranty Co.
38 P.2d 346 (Washington Supreme Court, 1934)
Niemi v. Brewster
281 P. 488 (Washington Supreme Court, 1929)
Maeder Steel Products Co. v. Brewster
281 P. 14 (Washington Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
268 P. 876, 148 Wash. 214, 1928 Wash. LEXIS 865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rachow-v-philbrick-nicholson-wash-1928.