United Pacific Casualty Insurance v. Port of Everett

46 P.2d 736, 182 Wash. 285, 1935 Wash. LEXIS 637
CourtWashington Supreme Court
DecidedJune 25, 1935
DocketNo. 25476. Department One.
StatusPublished
Cited by1 cases

This text of 46 P.2d 736 (United Pacific Casualty Insurance v. Port of Everett) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Pacific Casualty Insurance v. Port of Everett, 46 P.2d 736, 182 Wash. 285, 1935 Wash. LEXIS 637 (Wash. 1935).

Opinion

Geraghty, J.-

The port of Everett made a contract with James N. Main, by the termsi of which Main agreed to furnish and put in place approximately ten thousand tons of rock rip-rap on Tract 0 fill in the harbor of Everett. After the placing of this quantity of rock, the contractor, under a supplemental agreement with the port, furnished and put in place somewhat more than ten thousand additional tons of rock. The work was formally accepted by the port May 1, 1933, and a final estimate allowed the contractor.

Thereafter and within the thirty days allowed by statute, claims were filed against the contractor and his bond for labor and material, aggregating approxi *287 mately six thousand dollars, or considerably more than the retained percentage due the contractor. Thereupon, the plaintiff, United Pacific Casualty Insurance Company, surety on the contractor’s bond, instituted this action against the port, the contractor, and all claimants for labor and material, seeking to have the respective rights and liabilities of all parties concerned adjudicated by the court.

The essential facts, as they appear from the record, are as follows: The contract, made August 13, 1932, provided for the delivery and placing of approximately ten thousand tons of rock at an agreed price of $1.23 per ton. As to the manner of payment, it was stipulated :

“Estimates of the work completed shall be made by the Engineer each month. During the time allowed in the contract for the completion of the work and on or about the 17th day of the month following the issuance of the estimate, the Port Commission shall deliver to the contractor a warrant upon....................................Construction Fund in an amount equal to eighty-five (85%) per cent of such estimate, and the balance of said contract price, being fifteen (15%) per cent of .such estimate, shall be retained for a period of thirty (30) days after the final completion of the improvement, and no improvement shall be deemed completed until the same is approved and declared completed by the Port Commission. . . . No payment shall be issued to the contractor in any event for any part of said fifteen (15%) per cent reserve until the Engineer shall certify to the Port Commission that the thirty (30) days following the final acceptance of said improvement or work have elapsed, and that no uncompleted or defective work has been discovered for which the Port makes claim.”

The contractor gave a performance bond in the sum of $12,300, which the plaintiff executed as surety. Installation of the rock provided for in the contract was completed about January 16, 1933. February 6, 1933, *288 the port made a supplemental agreement with the contractor for delivery of approximately four thousand additional tons of rock, at an increase of ten per cent over the price stipulated in the original contract. The supplemental agreement made reference to the former contract and recited that 10,300 tons of rock had been delivered pursuant to its terms, and that approximately four thousand tons, in addition to the amount already delivered, would be required for the work, and provided for the delivery and placing of this additional quantity by the contractor. The supplemental agreement contained the following stipulation:

“It is further agreed that that certain bond for the sum of Twelve Thousand Three Hundred ($12,300.00) Dollars given by the said contractor as Principal and executed by the United Pacific Casualty Insurance Company as Surety guaranteeing the performance of the contract shall be continued in full force and effect until the completion of this supplemental agreement, and the said surety agrees to be bound by the terms of this supplemental agreement.”

The supplemental agreement was approved in writing by the plaintiff surety company.

The quantity of rock — four thousand tons — provided for in the supplemental agreement having been delivered and placed by the contractor, it was found that additional rock would be required, and on March 4, 1933, the commissioners of the port made an order, entered upon the minutes, “that approximately 2,500 tons, or enough rock to finish the west face of Tract O, be placed,” and the port’s attorney was instructed to arrange for continuation of the contractor’s bond to cover this additional rock. The consent of the bonding company to the delivery by the contractor of rock in addition to the four thousand tons provided for in the supplemental agreement was never obtained by the port. Ten thousand and ninety-one tons were deliv *289 ered by the contractor in addition to the quantity delivered under the original contract, being 6,091 tons more than the quantity stipulated in the supplemental agreement consented to and approved by the surety.

The minutes of the port district show that, on February 6, 1933, the contractor requested a payment of fifteen hundred dollars on account of rock delivered under the original contract, payable out of the retained percentage. The port agreed to pay this sum, conditioned upon the contractor furnishing a letter from the surety releasing the port from all liability for unpaid outstanding obligations incurred under the contract. The port also addressed a letter to the surety saying that it was willing to pay the contractor, as requested, with its consent. The surety did not reply to this letter or otherwise give its consent to the payment, but the port, nevertheless, made the requested payment to the contractor.

The trial court reached the conclusion that the liability of the surety was limited to claims growing out of the original and supplemental agreements, and that it was not liable for the claims of laborers and mate-rialmen arising out of the six thousand odd tons supplied in addition to the quantities of rock specifically covered by the agreements. The court also found that the port had improperly paid the contractor fifteen hundred dollars out of the retained fund provided for in the original contract, and considered the rights of the parties as if that sum were still in the fund. The court allowed unpaid claims aggregating $1,140.61 arising out of the work done under the original and supplemental agreements, and $4,589.62 on account of the last 6,091 tons, not supplied under the agreements.

After the payment of the fifteen hundred dollars to the contractor, there remained in the retained fund, available for the payment of claims arising out of the *290 original and supplemental agreements, $1,212.77, and in the retained fund for the rock delivered subsequent to the agreements, $1,233.55. It will be seen that the fund actually retained on account of the original and supplemental agreements, even after the payment of the fifteen hundred dollars to the contractor, was sufficient to pay all of the claims arising out of that part of the work and allowed by the court.

But the Shell Oil Company, one of the defendant claimants, filed a claim on account of oil and gas, furnished to the contractor in the prosecution of the work, in the sum of $1,779.35. Of this claim, $1,198.27 was allowed by the court and charged to the work done subsequent to the agreements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haley v. Brady
137 P.2d 505 (Washington Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
46 P.2d 736, 182 Wash. 285, 1935 Wash. LEXIS 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-pacific-casualty-insurance-v-port-of-everett-wash-1935.