Virginia Shipbuilding Corp. v. United States Shipping Board Emergency Fleet Corp.

292 F. 440, 1923 U.S. Dist. LEXIS 1315
CourtDistrict Court, E.D. Virginia
DecidedJanuary 11, 1923
StatusPublished
Cited by1 cases

This text of 292 F. 440 (Virginia Shipbuilding Corp. v. United States Shipping Board Emergency Fleet Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Virginia Shipbuilding Corp. v. United States Shipping Board Emergency Fleet Corp., 292 F. 440, 1923 U.S. Dist. LEXIS 1315 (E.D. Va. 1923).

Opinion

WADDILL, Circuit Judge.

The object of each of these suits is to have an accounting between the Virginia Shipbuilding Corporation, on the one hand, and the United States Shipping Board Emergency Fleet Corporation and others, on the other, growing out of certain contracts entered into between the parties, hereinafter specifically set forth, whereby the Virginia Company bound itself to construct for the Fleet Corporation, at its shipyard in Alexandria, Va., 12 steel ships,! of 9,400 tons dead weight carrying capacity each, 11 knots speed at deep-load draft, for the lump sum purchase price of $1,504,000 for each of said vessels when completed. The specific matter submitted to the court is the determination of the basis upon which such accounts should be made, to the end that it may by its decree instruct the master as to what shall be embraced in the accounting and the rights and liabilities of the parties thereunder.

The United States of America, in the action brought by it, takes the position that it is a mortgagee in possession of the ships, the Virginia Company and its assignees and transferees being only owners of the equity of redemption therein; also, that it has a right in equity to have [442]*442reinstated a lien upon'the plant of the Virginia Company theretofore released, and it seeks to have the accounting proceed on that basis. The Virginia Company insists that the United States is the owner by absolute title of the vessels in question, and has no lien or right of lien upon the plant, but is indebted to the Virginia Company for a portion of the contract price for constructing the vessels, and seeks to have the accounting so made. It is only fair to say in this connection that the position of the Virginia Company at this time is not in conformity with the averments of the bill and amended bill and pleadings in the first-named cause instituted by it, and that certainly, so far as the claim of ownership and title, to the ships is concerned, the parties in the pleadings seem to be in substantial accord.

The first and most important question to be ascertained is the ownership of the vessels, to the end that it may be determined upon what theory the accounting may be had and settled. The necessity of determining this ownership was early recognized on every hand, and hence the contracts, as well the three directly involved, as several incidentally bearing on the issue, were introduced, along with much oral and documentary evidence, showing the circumstances under which the same were severally entered into, with a view of throwing light upon the undertakings and intent of the parties, and of the meaning of the several contracts, so far as the same may not be clear and free from ambiguity. The substance and effect of the three main contracts involved are, namely: (a) That of December 1, 1917, under which the contract to build the 12 ships was first undertaken; (b) that of September 25, 1919, known as the “adjustment agreement”; and (c) that of July 19, 1920, supplemental to the other two. References to these three contracts will be as brief as possible,'though an understanding.of them will require some elaboration, as there are many questions involved in‘their interpretation that are not free from doubt, and the views of the respective parties in interest have been presented fully, both orally and in writing, by counsel of eminence and unusual ability.

First. Construction Contract, December 1, 1917, Known as “Contract 145 S. C.”

By this contract the Virginia Company, as assignee of the Groton Iron Works, undertook to construct for the government the 12 steel ships before referred to. They were to be of 9,400 tons dead weight carrying capacity, 11 knots at deep-load draft, to be constructed under the rules and regulations of the American Bureau of Shipping or Lloyds, and of the Moore & Scott type. Three ships were to be delivered at 10, 11, and 12 months, respectively, from the date of the contract, two each at 13, 14, and 15 months, respectively, and the remaining three within 16 months from the date of the contract. The contract provided for the payment of a lump sum of $1,504,000 for each of such completed vessels, and entered into much detail as to the terms and time of payment, namely, that $210,000 was to be paid for steel material for the construction of each ship when ordered by the contract or, 10 per cent, of the contract price within 30 days after the signing of the contract, and the residue during construction, as the work progressed, as therein specified. The contract further provided [443]*443for possible changes in the cost of construction, alterations, delays, insurance, forfeitures, title to the ships, settlement of disputes, etc.

The contract also provided for the construction, equipment, and maintenance at Alexandria by the contractor, at its cost, of a suitable and complete shipbuilding plant, with all necessary buildings, offices, shops, slips, and housing facilities for employes, adequate for the construction, completion, and delivery of the vessels within the time specified, such plant to be substantially completed within 200 days. It was agreed that title to the vessels completed or under construction, upon proper inspection, should be in the United States of America, and also the title to all material, that time was of the essence of the contract, that no other work was to be accepted which would interfere with that of the government, and that a bonus of $300 a day would be paid by the government for delivery of ships in advance of the time for completion specified in the contract, and a like charge loss for each day of delay after such date, such bonus and loss, however, not to exceed the sum of $25,000 in the case of any one ship.

Much delay ensued, as well in the matter of construction of ships as in the completion of the yard, with the result that not a single vessel was completed until long after the expiration of the time designated, nor was the shipyard completed in the specified time, although the government loaned to the contractor under the contract of May 15, 1918, called “Supplemental Contract S. C. 145,” the sum of $750,000 secured by mortgage upon the shipyard, to facilitate its completion, and at a later date, to wit, 10th of January, 1919, loaned the contractor on second mortgage, for like purposes, a further sum of $394,182.22.

Second. The “Adjustment Agreement” of September 25, 1919. Entitled “To Attach to Contract 145 S. C.,” Made Pursuant to the Preliminary Agreement of September 15, 1919.

This agreement recited, among other things, that the Virginia Company, being the owner of the shipyard at Alexandria, Va., was engaged in constructing vessels for the Fleet Corporation under contract dated December 7, 1917, known as “Contract 145 S. C.” said vessels being hulls 1 to 12, inclusive; that hulls 1, 2, and 3, namely, the “Gunston Hall,” the “Betsy Bell,” and the “Vanada,” had theretofore been completed and delivered to the Fleet Corporation ; that hulls Nos. 11 and 12, had been canceled at an agreed compensation to the contractor of $800,000, the amount to be credited upon the Virginia Company’s obligations to the Fleet Corporation, thus leaving for construction only hulls 4 to 10, inclusive; that advances had been made, subject to audit and confirmation by the Fleet Corporation, for yard and ship construction, of approximately $12,000,000, in addition to approximately $1,000.000 advanced under the two mortgages (on the plant) referred to of 15th of May, 1918, and 10th of January, 1919.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Government of Norway
172 F. Supp. 651 (Court of Claims, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
292 F. 440, 1923 U.S. Dist. LEXIS 1315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/virginia-shipbuilding-corp-v-united-states-shipping-board-emergency-fleet-vaed-1923.