Clean Earth of North Jersey, Inc. v. Northcoast Maintenance Corp.

142 A.D.3d 1032, 39 N.Y.S.3d 165
CourtAppellate Division of the Supreme Court of the State of New York
DecidedSeptember 21, 2016
Docket2013-11017
StatusPublished
Cited by7 cases

This text of 142 A.D.3d 1032 (Clean Earth of North Jersey, Inc. v. Northcoast Maintenance Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clean Earth of North Jersey, Inc. v. Northcoast Maintenance Corp., 142 A.D.3d 1032, 39 N.Y.S.3d 165 (N.Y. Ct. App. 2016).

Opinion

*1033 In an action, inter alia, to recover damages for breach of contract, on an account stated, and on a payment bond, the plaintiff appeals, as limited by its brief, from (1) so much of an order of the Supreme Court, Nassau County (Jaeger, J.), dated August 21, 2013, as denied those branches of its motion which were for summary judgment on the causes of action to recover damages for breach of contract, on an account stated, and on the payment bond, and (2) so much of an order of the same court entered January 8, 2014, as granted the motion of the defendant Colonial Surety Company for leave to reargue its opposition to that branch of the plaintiff’s motion which was for summary judgment on the cause of action to recover on the payment bond and, thereupon, deemed its opposition to be a cross application for summary judgment dismissing the complaint insofar as asserted against it and granted the cross application.

Ordered that the appeal from so much of the order dated August 21, 2013, as denied that branch of the plaintiff’s motion which was for summary judgment on the cause of action to recover on the payment bond is dismissed, as that portion of the order was superseded by the order entered January 8, 2014; and it is further,

Ordered that the order dated August 21, 2013, is affirmed insofar as reviewed; and it is further,

Ordered that the order entered January 8, 2014, is affirmed insofar as appealed from; and it is further,

Ordered that one bill of costs is awarded to the defendant Colonial Surety Company, payable by the plaintiff.

The defendant Northcoast Maintenance Corp., doing business as J. Barwick Landscape & Site Developer (hereinafter Barwick), is an excavation contractor. On February 2, 2010, Barwick obtained a payment bond, issued pursuant to State Finance Law § 137, from the defendant Colonial Surety Company (hereinafter Colonial) in connection with an impending public improvement contract with the defendant New York State Department of Environmental Conservation (hereinafter the DEC). Pursuant to that contract, which was entered into between Barwick and the DEC on March 31, 2010, Barwick agreed to act as general contractor for the excavation and remediation of hazardous soils on a project known as the Fumex Sanitation Site in Nassau County.

On November 23, 2010, a representative of the plaintiff, *1034 Clean Earth of North Jersey, Inc., executed an “Environmental Services Agreement” between the plaintiff and Barwick; however, this agreement was not signed by Barwick’s representative. On November 24, 2010, a Barwick corporate officer completed and signed a “Credit Application” seeking credit from the plaintiff. Other than these documents, there is no evidence that a formal contract was ever executed between the plaintiff and Barwick. Nevertheless, the plaintiff supplied equipment and removed contaminated landfill from the project site.

By invoice dated December 13, 2010, the plaintiff informed Barwick that it owed $74,890.72 for certain work performed by the plaintiff on December 8, 2010, at the project site. Two other invoices from the plaintiff, both dated December 14, 2010, stated that Barwick owed, respectively, $124,332.46 for work performed on December 9, 2010, and $16,869.04 for work performed on December 10, 2010, at the project site. The invoices, which sought a total amount of $216,092.22, indicated that payment was due in “Net 30 Days,” on January 12 and 13, 2011, respectively. Barwick did not remit any payment.

On June 7, 2011, the plaintiff submitted to Colonial a proof of claim form in connection with the plaintiffs request for payment under the payment bond. This form stated that the plaintiffs last work on the project was on December 10, 2010. The form also increased the total amount of the claimed payment due to $232,120.49, which included $16,028.27 in “accrued late charges” in addition to the original amount of $216,092.22 for the work performed. On July 28, 2011, Colonial notified the plaintiff that Barwick was disputing the plaintiffs claim. On August 11, 2011, the DEC accepted the project as completed.

In June 2012, the plaintiff commenced this action seeking, among other things, to recover damages for breach of contract, on an account stated, and on the payment bond. The plaintiff alleged that it was not compensated for work it performed on the public improvement project pursuant to an agreement with Barwick. Thereafter, the plaintiff moved, among other things, for summary judgment on the causes of action to recover damages for breach of contract, on an account stated, and on the payment bond. The Supreme Court denied those branches of the motion. Subsequently, the court granted Colonial’s motion for leave to reargue its opposition to that branch of the plaintiff’s motion which was for summary judgment on the cause of action to recover on the payment bond and, thereupon, deemed Colonial’s opposition to be a cross application for sum *1035 mary judgment dismissing the complaint insofar as asserted against it as time-barred and granted the cross application. The plaintiff appeals.

The Supreme Court properly denied that branch of the plaintiff’s motion which was for summary judgment on the cause of action to recover damages for breach of contract. The plaintiff’s submissions in support of its motion failed to establish, prima facie, that the plaintiff and Barwick entered into a binding agreement regarding the plaintiff’s work on the project (see Sunbelt Rentals, Inc. v New York Renaissance, 126 AD3d 481, 481 [2015]; Priceless Custom Homes, Inc. v O’Neill, 104 AD3d 664, 665 [2013]; see also M.V.B. Collision, Inc. v Rovt, 101 AD3d 830, 832 [2012]; Power Cooling Inc. v Churchill School & Ctr., 17 AD3d 148, 148 [2005]). Since the plaintiff failed to meet its initial burden, it is not necessary to consider the sufficiency of the papers submitted in opposition (see Tingling v C.I.N.H.R., Inc., 120 AD3d 570, 571 [2014]).

The Supreme Court also properly denied that branch of the plaintiff’s motion which was for summary judgment on the cause of action to recover on an account stated. “An account stated is an agreement between parties to an account based upon prior transactions between them with respect to the correctness of the account items and balance due” (Branch Servs., Inc. v Cooper, 102 AD3d 645, 646 [2013] [internal quotation marks omitted]; see BRKProps., Inc. v Wagner Ziv Plumbing & Heating Corp., 89 AD3d 883, 884 [2011]). “An agreement may be implied where a defendant retains bills without objecting to them within a reasonable period of time or makes partial payment on the account” (Branch Servs., Inc. v Cooper, 102 AD3d at 646 [internal quotation marks omitted]). In opposition to the plaintiff’s prima facie showing (see Law Offs. of David J. Sutton, P.C. v NYC Hallways & Lobbies, Inc., 105 AD3d 1010, 1010-1011 [2013]; Castle Oil Corp. v Bokhari, 52 AD3d 762, 762 [2008]), Barwick’s submissions, which included an affidavit of its president and emails exchanged by the parties, raised a triable issue of fact as to whether Barwick objected to the plaintiff’s invoices within a reasonable period of time (see Granite State Ins. Co. v Transatlantic Reins. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Townhouse Off. Park Assoc., Inc. v. Townehouse Off. Park of Nanuet Condominium
2025 NY Slip Op 04929 (Appellate Division of the Supreme Court of New York, 2025)
Cohen v. State of New York
2021 NY Slip Op 00147 (Appellate Division of the Supreme Court of New York, 2021)
Ecoline, Inc. v. W.H. Peepels Co., Inc.
2017 NY Slip Op 6253 (Appellate Division of the Supreme Court of New York, 2017)
Caring Professionals, Inc. v. Landa
2017 NY Slip Op 5803 (Appellate Division of the Supreme Court of New York, 2017)
Alumil Fabrication, Inc. v. F.A. Alpine Window Manufacturing Co.
2017 NY Slip Op 4410 (Appellate Division of the Supreme Court of New York, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
142 A.D.3d 1032, 39 N.Y.S.3d 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clean-earth-of-north-jersey-inc-v-northcoast-maintenance-corp-nyappdiv-2016.