Greeter Construction Co. v. Tice

11 S.W.3d 907, 1999 Tenn. App. LEXIS 568, 1999 WL 631748
CourtCourt of Appeals of Tennessee
DecidedAugust 20, 1999
Docket01A01-9808-CH-00427
StatusPublished
Cited by6 cases

This text of 11 S.W.3d 907 (Greeter Construction Co. v. Tice) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greeter Construction Co. v. Tice, 11 S.W.3d 907, 1999 Tenn. App. LEXIS 568, 1999 WL 631748 (Tenn. Ct. App. 1999).

Opinion

OPINION

CAIN, Judge.

This appeal represents a consolidated case commenced by Appellant, Greeter Construction Company (hereafter Greeter) against the Appellees Richard and Nancy Tice. Greeter had sued the Tices for an amount allegedly owed under a construction contract. The Tices counterclaimed for breach of said contract.

The Tices contracted with Greeter for the renovation of their Brook Hollow Drive home. The primary portion of this renovation was an 1100 square foot addition to the house. The construction contract reads in pertinent part as follows:

All work is to be performed in a professional workmanlike manner, free from all hens or claims of mechanics or mate-rialmen, subject to the stipulations and other provisions on the additional attached documents:
“Estimate & Project Outline” and “Stipulations”.
In case of conflict between the plans and specs the plans shall control over the specifications and the provisions of this contract shah control both.
• The work to be performed by [Greeter] to the Agreement and shall be substantially commenced approximately on August IQ, 17, 1994 and shah be substantially completed on November ¾- 8, 1994.
• [TICES] promise[ ] to pay or cause to be paid to [Greeter] in consideration for his performance all costs for material and labor plus 15% payable as follows: Not to exceed total estimate of Construction project of $49,750.00 unless agreed upon by “owner. ”/s/ JAG /s/ NT

This agreement, complete with handwritten and initialized addenda and alteration, was entered into by the parties on August 14, 1994. From this point on, the Owners Tice and Greeter enjoyed what the record reveals to be at best a problematic relationship. Despite Nancy Tice’s frequent presence on the job site and extensive correspondence between the Tices and Greeter, the renovation project experienced significant delay and cost inflation. In addition to unexpected cost increases and labor delays, three different rains, occurring in September October and November of 1994 caused extensive damage to the original structure as well as to the addition. Without any specific prior notice, the Tices terminated Greeter Construction on December 5,1994.

On April 24, 1995, Greeter filed a complaint in the Davidson County Chancery Court to enforce a materialman’s lien in the amount of $12,000 allegedly due on the contract. The Tices responded and counterclaimed for breach, alleging the following:

1. [Greeter] breached the contract between the parties by:
a. Failing to construct the improvements in accordance with the plans and specifications.
b. Failing to construct the improvements within the budget estimate.
c. Failing to construct the improvements in a professional workmanlike manner.
d. Failing to complete the improvements in a timely manner.
e. Failing to obtain authorization from Defendants before ordering *909 material, the cost of which exceeded the agreed to estimate.
2. As a result of [Greeterj’s breach of the contract, Defendants have suffered damages in the amount of approximately $52,500, the exact amount to be determined at trial.

The case was tried without a jury before Hon. Claudia Bonnyman, Special Chancellor, on April 6, 1998. The Chancellor’s memorandum discloses the following findings of fact which are entitled to a presumption of correctness on appeal absent a showing that the evidence preponderates against those findings. Tenn.R.App.P. 13(d).

Work on the project began in August of 1994. Even the first stage, demolition, took longer than Alan Greeter anticipated. He asserts that the Owners made changes in the project which caused delay. However, Greeter did not provide written change orders to support that position. By the end of September, Alan Greeter admitted to the Owners that the cost overrun for the first stage was already 10-15%. He advised the Owners that the contract price was still valid, however, because there were cost savings to be had later in the project. In fact, the cost overruns continued. At trial he did not know what the revised cost would be if he had completed the project. The Owners paid Greeter almost twenty thousand ($20,000) dollars (including the deposit) by the time of termination in early December.
The project had numerous problems. First, the Owners proved that Alan Greeter was inexperienced and had previous large cost overruns on one of the few projects he had supervised before the Owner’s project. It became obvious to the Owners that this project could not be completed for any amount near the contract price. Second, after the work began, Alan Greeter concluded that the design for the back of the house was not possible for him to follow. This was disappointing for the Owners but they accepted such deviations for a few months. Third, the renovations design required removal of an exterior wall and a new roof for the addition which would tie into the old roof. It was expected that for a brief period, the inside of the house would be exposed to weather. Alan Greeter admitted that Greeter had a duty to protect the house from rain to the extent that could be done. The Owners proved that Greeter failed to take precautions to protect the interior of the house during rains in October and November. The last rain resulted in major water damage to the interior costing the Owners $26,078.19 to repair....
On December 5,1994, the Owners terminated the project with Greeter because of the problems discussed above. Builder’s Group completed the project, (reworking much of the Greeter construction) pursuant to the original plans_ Greeter was aware that delay and cost problems can and do arise.

From the order below Greeter appeals asserting as its issue “[wjhether the Tices are entitled to damages after unilaterally terminating the building contract with Greeter Construction Company.”

The Special Chancellor concluded regarding the liability of the parties:

The construction agreement Greeter Drafted, however, did not provide for cost contingencies. Although the contract was captioned a “cost plus” contract, the agreement was amended to establish a set building cost which could only be changed by agreement. The Owners did not agree to increase the contract price of $49,750....
The Owners are awarded a judgment against Greeter Construction Company in the amount of sixty three thousand, four hundred thirty-three ($63,433.00) dollars.

*910 So much of this case depends on an appraisal of the credibility of Allen Greeter as opposed to the credibility of Richard and Nancy Tice. On appeal, we are bound by the same rules as were articulated in Weaver v. Nelms, 750 S.W.2d 158 (Tenn. App.1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 S.W.3d 907, 1999 Tenn. App. LEXIS 568, 1999 WL 631748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greeter-construction-co-v-tice-tennctapp-1999.