Rose Mary Thompson v. Robert Boyd

CourtCourt of Appeals of Tennessee
DecidedApril 9, 2019
DocketE2018-01098-COA-R3-CV
StatusPublished

This text of Rose Mary Thompson v. Robert Boyd (Rose Mary Thompson v. Robert Boyd) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rose Mary Thompson v. Robert Boyd, (Tenn. Ct. App. 2019).

Opinion

04/09/2019 IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs March 1, 2019

ROSE MARY THOMPSON V. ROBERT BOYD

Appeal from the Circuit Court for Knox County No. 1-378-17 Kristi M. Davis, Judge

No. E2018-01098-COA-R3-CV

A homeowner and a contractor entered into a contract requiring the contractor to repair damage to the homeowner’s house caused by a kitchen fire. The repairs to be performed were those covered by the homeowner’s insurance policy as outlined in a detailed estimate of repair work. After the contractor abandoned the project, the homeowner hired another contractor to complete the work and sued the original contractor for breach of contract. We affirm the decision of the trial court to the extent of the court’s determination that the contractor breached the contract by his undue delay and poor workmanship. We have concluded, however, that the trial court’s decision fails to adequately explain the award of damages or to dispose of the contractor’s counterclaim. Therefore, we vacate the damages award and remand for more specific findings regarding the basis for the damages award and a disposition of the counterclaim.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed in Part, Vacated in Part, and Remanded

ANDY D. BENNETT, J., delivered the opinion of the Court, in which D. MICHAEL SWINEY, C.J., and JOHN W. MCCLARTY, J., joined.

Robert Boyd, Knoxville, Tennessee, pro se.

Barbara W. Clark, Knoxville, Tennessee, for the appellee, Rose Mary Thompson. MEMORANDUM OPINION1

FACTUAL AND PROCEDURAL BACKGROUND

A kitchen fire on June 5, 2015, caused damage to Rose Mary Thompson’s home on Spring Place Circle in Knoxville. Ms. Thompson’s insurance company determined that she was entitled to $80,063.552 for the repairs. On October 27, 2015, Ms. Thompson entered into a contract with Robert Boyd to perform the repairs.

On October 13, 2017, Ms. Thompson filed a complaint for breach of contract against Mr. Boyd. The complaint includes the following pertinent allegations:

8. The Defendant commenced work shortly after the contract was signed by the Plaintiff on October 27, 2015, and received his first payment draft on November 18, 2015, in the amount of $40,000.00. The Defendant received subsequent payments in the amount of $13,620.30. 9. Throughout the course of the repair project, the Defendant would fail to show up on numerous occasion[s] causing unnecessary delays, and more than 50% of the repair work remains unfinished. .... 11. The work the Defendant did perform was substandard, causing the Plaintiff to seek the service of other contractors to make corrections to his poor quality workmanship. .... 12. The contract for restoration of Plaintiff’s residence required the Defendant to restore the residence pursuant to the contract signed by the parties on October 27, 2015. The Defendant did not complete work pursuant to the contract, in a timely workmanlike manner. 13. The failure of the Defendant to complete the restoration work constitutes a breach of contract.

Mr. Boyd answered the complaint, denying the allegations and stating his version of events. He also asserted a counterclaim.

1 Rule 10 of the Rules of the Court of Appeals of Tennessee provides:

This Court, with the concurrence of all judges participating in the case, may affirm, reverse or modify the actions of the trial court by memorandum opinion when a formal opinion would have no precedential value. When a case is decided by memorandum opinion it shall be designated “MEMORANDUM OPINION,” shall not be published, and shall not be cited or relied on for any reason in any unrelated case. 2 This figure includes an actual cash value of $67,232.71 and a replacement cash value of $12,830.84. -2- According to Mr. Boyd’s counterclaim, the parties had a meeting on June 25, 2017. At that meeting, Ms. Thompson gave Mr. Boyd a deadline of July 31, 2017, to complete the work, and he told her that he would be focusing on the insurance claims, and not on any additional projects she wanted to be done. The counterclaim further alleges:

12. The Defendant notified Wells Fargo Bank [Ms. Thompson’s mortgage company] to set up an inspection and updated the progress of work. 13. July 5, 2017 the Plaintiff locked the Defendant out of the property 5601 Springplace Circle Knoxville, TN. 14. The Plaintiff stated to the Defendant that his service was no longer needed. 15. The Defendant spoke to the Plaintiff about retrieving his tools and building materials from her property. Also to set up a time for the Wells Fargo Bank inspector. 16. The Plaintiff refused the Defendant[’s] requests. 17. The Defendant immediately contacted Well[s] Fargo Bank[ ] (mortgage lender) and Capstone ISG [insurance adjuster] to inform them of the situation therefore avoiding any confrontation with the Plaintiff. 18. Wells Fargo Bank informed the Defendant that all funds are [frozen] at this time. The Plaintiff and Defendant would have to come up with a mutual agreement before the contract can be closed. 19. Plaintiff refused the Defendant[’s] requests; therefore the Defendant was forced to take legal action. . . .

Mr. Boyd asserted that the work was 75% complete when he received his second payment from the bank and that Ms. Thompson was responsible for change orders and additional work not included on the insurance repair sheets. He requested the following relief:

10. The Plaintiff owes the Defendant $5,000.00. 11. Defendant has the 3rd draw left to be issue[d] to him for the amount [of] $13,612.41 from Wells Fargo Bank. The Defendant would have received the full amount if he had completed the remaining work. 12. Tools, Materials and Supplies Plaintiff refused to return to Defendant [in the] amount of $6,700.00. 13. For actual damages in [the] amount of $25,312.41. 14. Punitive Damages of $50,000.00. 15. [Breach] of contract in the amount of $25,500.00. 16. Defamation of character in [the] amount of $50,500.00.

The case went to trial on June 11, 2018. The record does not include a transcript of the hearing, but it does include a statement of the evidence describing the testimony

-3- presented at trial. The trial court adopted Ms. Thompson’s statement of the evidence as the “fair, accurate, and complete account of what transpired at trial.” According to the statement of the evidence, the trial court heard the following:

Testimony of Rose Mary Thompson

The Plaintiff, Rose Mary Thompson, testified that on or about June 5, 2015, she sustained damage to her home at 5601 Spring Place Circle, Knoxville, TN 37924 because of a kitchen fire. The loss was timely reported to the Plaintiff’s homeowner’s insurance and Capstone ISG, an independent adjusting company, compiled a computer report for repairs to be made at a total cost of depreciation of $80,321.12, exclusive of depreciation of $19,625.00 and the $2,500.00 deductible. A copy of the report was admitted as an exhibit to Plaintiff/Appellee’s testimony.

The Plaintiff/Appellee entered into a contract with the Defendant/Appellant, Robert Boyd, on October 27, 2015, to complete the repairs on her home. Numerous delays caused by the Defendant/Appellant occurred and in July 2017, the parties’ relationship totally broke down and Ms. Thompson told Mr. Boyd to stay away from her residence, and solicited the services of another renovation contractor, Mr. Clayton Johnson, to finish the job Mr. Boyd started in October 2015.

Wells Fargo, Plaintiff/Appellee’s Mortgage Company was responsible for disbursing the funds to Mr. Boyd after an inspection was performed. On April 30, 2016, Wells Fargo performed an inspection of the work[ ] performed by Mr. Boyd and found that he had completed 75% of the repairs. No other inspections were performed. Much of the work performed by Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jennings v. Sewell-Allen Piggly Wiggly
173 S.W.3d 710 (Tennessee Supreme Court, 2005)
Bean v. Bean
40 S.W.3d 52 (Court of Appeals of Tennessee, 2000)
Greeter Construction Co. v. Tice
11 S.W.3d 907 (Court of Appeals of Tennessee, 1999)
Young v. Barrow
130 S.W.3d 59 (Court of Appeals of Tennessee, 2003)
Hessmer v. Hessmer
138 S.W.3d 901 (Court of Appeals of Tennessee, 2003)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
State v. Ballard
855 S.W.2d 557 (Tennessee Supreme Court, 1993)
Nashville Ford Tractor, Inc. v. Great American Insurance Co.
194 S.W.3d 415 (Court of Appeals of Tennessee, 2005)
Memphis Light, Gas & Water Division v. Starkey
244 S.W.3d 344 (Court of Appeals of Tennessee, 2007)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Bayberry Associates v. Jones
783 S.W.2d 553 (Tennessee Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Rose Mary Thompson v. Robert Boyd, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rose-mary-thompson-v-robert-boyd-tennctapp-2019.