Liberty Construction Company, LLC v. Peter H. Curry

CourtCourt of Appeals of Tennessee
DecidedOctober 21, 2020
DocketM2019-00951-COA-R3-CV
StatusPublished

This text of Liberty Construction Company, LLC v. Peter H. Curry (Liberty Construction Company, LLC v. Peter H. Curry) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liberty Construction Company, LLC v. Peter H. Curry, (Tenn. Ct. App. 2020).

Opinion

10/21/2020 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE February 4, 2020 Session1

LIBERTY CONSTRUCTION COMPANY, LLC v. PETER H. CURRY, ET AL.

Appeal from the Chancery Court for Davidson County No. 15-1332-III Ellen Hobbs Lyle, Chancellor ___________________________________

No. M2019-00951-COA-R3-CV ___________________________________

This is an action by a construction company to recover on a written stipulated sum contract and an oral cost-plus contract for the construction of a commercial building. The construction company sought to recover for additional work performed that was not included in the scope of the stipulated sum contract and the remaining balance of the cost- plus contract. The building owners contended that the construction company was not entitled to additional payment under the written agreement and counterclaimed for payments the owners made directly to suppliers for work included in the scope of the stipulated sum contract, and for reimbursement of funds expended to correct a defect caused by the construction company. The trial court held that neither the construction company nor the owners were entitled to recover under the stipulated sum contract; that the owners were not entitled to reimbursement because they failed to establish that the construction company caused the defect or, in the alternative, failed to provide a reasonable opportunity to cure; and that the construction company was entitled to judgment for work performed in connection with the cost-plus agreement. We reverse the court’s determination that the owners were not entitled to a credit for certain payments made directly to suppliers, that prejudgment interest commenced on November 10, 2014, when the notice of completion was filed, and that the owners did not provide the construction company with notice and an opportunity to cure. We affirm the trial court’s holding in all other respects.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed in Part, Reversed in Part, and Remanded

ANDY D. BENNETT, J., delivered the opinion of the court, in which THOMAS R. FRIERSON, II, J., joined. RICHARD H. DINKINS, J., not participating.

1 This matter was assigned to the author on October 2, 2020. Gregory H. Oakley, Nashville, Tennessee, for the appellants, Patricia P. Curry and Peter H. Curry.

Todd E. Panther and Hunter C. Branstetter, Nashville, Tennessee, for the appellee, Liberty Construction Company.

OPINION

I. FACTUAL AND PROCEDURAL BACKGROUND

Peter H. Curry and Patricia B. Curry (“the Currys”) entered into a contract with Liberty Construction Company, LLC (“Liberty”) in July 2013 for the construction of a commercial retail facility, to be known as Curry Plaza (“the Property”), on West Trinity Lane in Davidson County, for the fixed sum of $329,000. The initial contract provided for the construction of the shell building and the finishing out of the interior of one of three bays, referred to as the “Cashville bay.” As work progressed, the scope expanded to include modifications to the original plans as well as the interior finish of the other two tenant bays, to be occupied by a single tenant for the operation of a convenience market, referred to as the “Market Finish.” The parties orally agreed that the Market Finish project would be completed on a cost-plus 15 percent basis. On November 10, 2014, a notice of completion was filed. The parties were unable to agree on whether Liberty was entitled to additional payment under the stipulated sum contract or what the remaining balance was under the cost-plus agreement.

Liberty filed suit on November 5, 2015, asserting claims for breach of contract and a mechanic’s and materialman’s lien. The Currys answered and filed a breach of contract counterclaim alleging that Liberty failed to construct the Property in accordance with the plans and failed to perform the work in a workmanlike and timely manner. The Currys also counterclaimed that Liberty had “willfully and grossly exaggerated the amount” of its lien. The three-day bench trial began on February 19, 2019.

On April 1, the court entered its memorandum and order of findings of fact and conclusions of law, which were later incorporated into the final order entered on April 30. The court awarded Liberty $90,302.61 in damages, plus prejudgment interest in the amount of $39,658.92, for the total sum of $129,691.53; it dismissed the counterclaim for lack of proof.

The Currys appeal, raising the following issues:

1. Whether the evidence preponderates against the trial court’s award of damages to Liberty in the amount of $90,302.61 for the cost of the Market Finish.

-2- 2. Whether the trial court erred in ruling that the Currys were not allowed a credit of $24,986.40 for amounts paid by them directly to suppliers for materials used in the construction of work covered under the stipulated sum contract.

3. Whether the evidence preponderates against the trial court’s ruling that the Currys were not entitled to recover $9,635 for the cost of correcting defects in a stormwater detention pond caused by Liberty’s failure to construct the pond according to construction plans.

4. Whether the trial court erred in awarding prejudgment interest on the award for the Market Finish from the date of completion of construction rather than the date when Liberty provided the Currys with the amount it claimed for the Market Finish.

II. ANALYSIS

A. Award of Damages under the Cost-Plus Contract

The Currys contend that the evidence preponderates against the court’s award of damages under the cost-plus contract because the award was based on Liberty’s approximation of costs incurred for the construction of the Market Finish. Although they concede in their brief that they are liable to Liberty, the Currys argue they are only liable for $25,877.80 according to their calculation of costs based on Liberty’s records. The Currys also assert that Liberty failed to satisfy its burden of itemizing the costs of the work performed and proving that the costs were reasonable.

As we consider this issue, we are guided by the following principles:

Determinations concerning the amount of damages are factually driven. Thus, the amount of damages to be awarded in a particular case is essentially a fact question. However, the choice of the proper measure of damages is a question of law to be decided by the court.

Beaty v. McGraw, 15 S.W.3d 819, 827 (Tenn. Ct. App. 1998) (citations omitted), abrogated on other grounds by Bowen ex rel. Doe v. Arnold, 502 S.W.3d 102 (Tenn. 2016). Review of the trial court’s findings of fact is de novo upon the record, accompanied by a presumption of correctness, unless the preponderance of the evidence is otherwise. TENN. R. APP. P. 13(d); Kaplan v. Bugalla, 188 S.W.3d 632, 635 (Tenn. 2006). Review of the trial court’s conclusions of law is de novo with no presumption of correctness afforded to the trial court’s decision. Kaplan, 188 S.W.3d at 635.

-3- 1. Itemization of Costs

The first issue we address is whether Liberty’s records sufficiently itemized the costs associated with the construction of the Market Finish. The trial court did not make any factual findings regarding the sufficiency of Liberty’s records of the costs incurred in the construction of the Market Finish. In Shore v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Velda J. Shore v. Maple Lane Farms, LLC
411 S.W.3d 405 (Tennessee Supreme Court, 2013)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Barnes v. Barnes
193 S.W.3d 495 (Tennessee Supreme Court, 2006)
Hickman v. Continental Baking Co.
143 S.W.3d 72 (Tennessee Supreme Court, 2004)
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Ganzevoort v. Russell
949 S.W.2d 293 (Tennessee Supreme Court, 1997)
GSB Contractors, Inc. v. Hess
179 S.W.3d 535 (Court of Appeals of Tennessee, 2005)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
Otis v. Cambridge Mutual Fire Insurance Co.
850 S.W.2d 439 (Tennessee Supreme Court, 1993)
Kaplan v. Bugalla
188 S.W.3d 632 (Tennessee Supreme Court, 2006)
Kerner v. Gilt
296 So. 2d 428 (Louisiana Court of Appeal, 1974)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
W. H. Lyman Construction Co. v. Village of Gurnee
475 N.E.2d 273 (Appellate Court of Illinois, 1985)
Spencer Ex Rel. Spencer v. A-1 Crane Service, Inc.
880 S.W.2d 938 (Tennessee Supreme Court, 1994)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
John J. Heirigs Const. Co., Inc. v. Exide
709 S.W.2d 604 (Court of Appeals of Tennessee, 1986)
Bowen ex rel. Doe v. Arnold
502 S.W.3d 102 (Tennessee Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Liberty Construction Company, LLC v. Peter H. Curry, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liberty-construction-company-llc-v-peter-h-curry-tennctapp-2020.