John J. Heirigs Const. Co., Inc. v. Exide

709 S.W.2d 604, 1986 Tenn. App. LEXIS 2717
CourtCourt of Appeals of Tennessee
DecidedJanuary 7, 1986
StatusPublished
Cited by56 cases

This text of 709 S.W.2d 604 (John J. Heirigs Const. Co., Inc. v. Exide) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John J. Heirigs Const. Co., Inc. v. Exide, 709 S.W.2d 604, 1986 Tenn. App. LEXIS 2717 (Tenn. Ct. App. 1986).

Opinion

CRAWFORD, Judge.

Plaintiff John J. Heirigs Construction Company, Inc., sued defendants, Exide and the Electric Storage Battery Company for a money judgment and to enforce its mechanic’s lien. The Chancery Court, sitting without a jury, awarded plaintiff a money judgment, but denied plaintiff a mechanic’s lien and defendants appeal.

Plaintiff’s complaint alleges that defendants owned real estate in Shelby County and that improvements were made on the property by Synergo, Inc., under a contract with the defendants, and that plaintiff furnished labor and material incorporated into the improvement pursuant to Synergo’s purchase order issued to plaintiff, which provides in pertinent part:

CONFIRMING ORDER — DO NOT DUPLICATE Confirming telephone conversation between our Mr. E.B. DeLuca and Mr. J. Heirigs, Nov. 25, 1981.
Furnish all labor, material, applicable taxes, fees, and insurance to complete the Work as itemized on the attached Phase I Specification (Revised November 2,1981) for the Effluent Treatment Facility to be installed at the Exide Corporation Memphis Plant, 3454 Chelsea Avenue, Memphis, Tennessee 38108.
A Performance Bond will be furnished for the Contract amount.
Delivery of metal building — 5 weeks. Project completion 8 to 10 weeks, subject to lost time due to winter weather conditions.
Time shall be of the essence of this Agreement. Contractor agrees to prosecute the Work continuously and diligently following the notification of award.
This Purchase Order is issued in accordance with the attached documentation:
a. Drawing No. M-l, Rev., O
b. Phase I Specification (Revised 11/2/81)
c. John J. Heirigs Construction Co., Inc. Proposal.
d. Synergo, Inc. Standard Terms and Conditions for Field Construction Contract
All the above in accordance with your proposal of October 30,1981 . $109,459.00
Addition for IV2 inch grating (telephone quote 11/2/81). 386.00
Addition to complete electrical work. Rewire two (2) existing agitator motors (telephone quote 11/3/81). $ 350.00
TOTAL $110,195.00
Addition for Professional Seal if required 750.00
TOTAL This Purchase
Order $110,945.00

REF. Exide PH47057

The Standard Terms and Conditions for Field Construction Contract forming a part of the purchase order, as pertinent here, specifically provide:

4.17 Covenant Against Mechanics’ Liens. The Contractor covenants that neither it nor any Subcontractor, materi-alman, or any other person furnishing labor, material and services or any of them, shall have, file or maintain a mechanic’s or material’s lien for materials delivered for use in, or for work done in, the performance of the Contract; and the right to have or maintain such lien against the premises, against materials, fixtures, apparatus or machinery furnished, or against any moneys or other sums due or to become due the Contractor under the provisions of the Contract, *606 by any or all of the above named parties shall be, and is hereby expressly waived.

Plaintiff asserts that it is entitled to a mechanic’s lien for the balance unpaid by Synergo and further avers that the purchase order was issued by Synergo as the agent of the defendants and that the defendants are bound on the purchase order contract.

Defendants filed an answer and counterclaim asserting that plaintiff had executed a written general release and had waived all claims against defendants, that plaintiff did not comply with the notice requirements of the mechanic’s lien statutes and had waived the right to claim such liens by virtue of its contract with Synergo, denying that Synergo was defendants’ agent, denying that defendants were bound on Synergo’s contract with plaintiff and denying that plaintiff was entitled to any recovery against it or entitled to a lien on defendants’ property. Defendants also filed a counterclaim against plaintiff seeking damages allegedly incurred in defending against the claimed mechanic’s lien which defendants aver was wrongfully filed against them.

Prior to issuing the purchase order, on which suit is brought, to plaintiff, Synergo itself received a purchase order from Exide covering the project and providing in pertinent part:

Synergo will provide the following items and they will become the “Contract Documents.”:
• Appendix A — Revised 2 November, 1981 — Project # 81500
• Project Sketch
• Revised Building Specifications
• All insurance documents as per agreement
• * Waivers of Liens (see below)
• Payment for this project will be made in four (4) equal installments of $34,-252.25.* The “final payment” will not be made until all waivers of liens are held by EXIDE Corporation. SYNER-GO, Inc. will submit, along with their invoice, a transmittal of all payments to contractors/subcontractors.
All change orders for amounts greater than $300.00 will be handled by a separate Purchase Order from EXIDE Corporation. Corporate Purchasing # 5 Penn Center.
All travel expenses relating to this project by SYNERGO, Inc. will be handled on a Purchase Order from EXIDE Corporation.
• SYNERGO, Inc. does not guarantee the pH system. This project and its reliability are the sole responsibility of EX-IDE Corporation.

To perform specific construction as outlined in Appendix “A” (attached).

Building per quotation by Heirigs Construction and in accordance with revised building specifications (attached) 109,459.
Professional Seal 750.
Grating up to l'A” 400.
Electrical wiring for two (2) agitators 400.
TOTAL 111,009.
Acid Dump Station Pump — two (2) per space. 7,000.
SYNERGO Management fee — NOT TO EXCEED 19,000.
GRAND TOTAL 137,009.

THE DATE OF COMPLETION ON THIS PROJECT IS TO BE NO LATER THAN 1, APRIL, 1982.

At the conclusion of the proof the trial court found that Synergo was acting as the agent of Exide and that plaintiff should recover on the theories of quantum meruit and unjust enrichment. The court further found that plaintiff had waived its lien. The court entered judgment against the defendants for a total of $35,135.04 as the balance due plus prejudgment interest. Defendants have presented several issues which we rephrase as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leonard Gamble v. Eric Brian Friend
Court of Appeals of Tennessee, 2025
Kong v. Chatham Village HOA
W.D. Tennessee, 2025
Liberty Construction Company, LLC v. Peter H. Curry
Court of Appeals of Tennessee, 2020
Clara Manley v. Humboldt Nursing Home, Inc.
Court of Appeals of Tennessee, 2020
Moore v. Michalski
2018 Ohio 3021 (Ohio Court of Appeals, 2018)
Steve Perlaky v. Jimmy Chapin
Court of Appeals of Tennessee, 2018
Estate of David Lyons v. Latony Baugh
Court of Appeals of Tennessee, 2018
Joyce Bradley Watts v. Colin Wade Watts
519 S.W.3d 572 (Court of Appeals of Tennessee, 2016)
Baxter Bailey Investments LLC v. APL Limited Inc.
Court of Appeals of Tennessee, 2015
SecurAmerica Business Credit v. Karl Schledwitz
Court of Appeals of Tennessee, 2014
ICG Link, Inc. v. Philip Steen v. TN Sports, LLC v. ICG Link, Inc.
363 S.W.3d 533 (Court of Appeals of Tennessee, 2011)
Dennis W. Blackmon v. LP Pigeon Forge, LLC
Court of Appeals of Tennessee, 2011

Cite This Page — Counsel Stack

Bluebook (online)
709 S.W.2d 604, 1986 Tenn. App. LEXIS 2717, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-j-heirigs-const-co-inc-v-exide-tennctapp-1986.