Thayer v. Wright Company

362 S.W.2d 805, 50 Tenn. App. 515, 1961 Tenn. App. LEXIS 147
CourtCourt of Appeals of Tennessee
DecidedAugust 31, 1961
StatusPublished
Cited by22 cases

This text of 362 S.W.2d 805 (Thayer v. Wright Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thayer v. Wright Company, 362 S.W.2d 805, 50 Tenn. App. 515, 1961 Tenn. App. LEXIS 147 (Tenn. Ct. App. 1961).

Opinion

BEJACH, J.

In this cause, The Wright Company, Inc. and United Pacific Insurance Company appeal from a *518 decree in the sum of $44,235.09, recovered against them in the Chancery Court of Shelby County by F. T. Thayer, Jr. Complainant F. T. Thayer, Jr. was the general contractor for the building of a branch store for Sears Roebuck & Company on Poplar Avenue in Memphis, Tennessee, and The Wright Company, Inc., formerly known as Frank A. Wright, Masonry Contractor, Inc., was subcontractor for part of the structure involving the installation of terra cotta tiles. The United Pacific Insurance Company, as surety for said subcontractor, guaranteed faithful performance of its contract with F. T. Thayer, Jr., — which contract was dated October 24, 1956. In this opinion the parties will be referred to as complainant and defendants, as general contractor, subcontractor, and surety, or called by their respective names. Under its contract with the general contractor, the subcontractor agreed to install the terra cotta tiles in a workmanlike manner, according to plans and specifications for the building, and in accordance with printed directions of the manufacturer of the material; and said contract provided that all work was to be performed in a workmanlike manner. After the work was completed, it was found that some of the terra cotta was loose, and some of it began to fall from the places where it had been installed; following which, the general contractor, the architect, the manufacturer of the tile, and the subcontractor’s representative conducted an investigation to determine why the terra cotta failed to adhere to the walls and why some of it fell from the places where it had been installed. The explanation, as was asserted by complainant Thayer, and as was found by the verdict of the jury, was that the defendant, The Wright Company, Inc., did not originally perform the work in a workman *519 like manner, and did not abide by and follow tbe specifications and manufacturer’s directions in applying tbe terra cotta tile. More specifically, it was found tbat tbe subcontractor did not apply a brush coat of Portland cement and water to many of tbe sections prior to setting same, and failed to apply a full bed of mortar to tbe outside walls of tbe building prior to setting in place tbe terra cotta, so tbat tbe back of tbe terra cotta would adhere thoroughly throughout its entire surface to tbe bed of mortar, and so tbat tbe full bed of mortar would be applied to tbe wall of tbe building and fill tbe entire space between tbe wall building and the terra cotta tile. Tbe complainant, the general contractor, was required to remove all tbe terra cotta which was not bedded with a solid bed of mortar, and not properly bonded to tbe structure, and to perform all work necessary to installation of tbe terra cotta in accordance with tbe original specifications. Tbe complainant thereupon made demand on tbe defendant, Tbe Wright Company, as tbe subcontractor, and also on its surety, tbe United Pacific Insurance Company, to comply with these requirements; but both of them refused to do so. After such refusal by Tbe Wright Company and its surety, tbe complainant sought bids from several masonry contractors to furnish tbe labor and equipment to remove and replace all terra cotta tbat was not installed in accordance with tbe plans and specifications. A contract to tbat end was awarded to V. C. Kindig for tbe sum of $58,843.98. To tbat sum the complainant added 5% or $2,442.20, claimed as compensation for his time, overhead, office and miscellaneous expenses incurred incident to tbe performance of tbe work by Y. C. Kindig, and brought suit on August 24, 1959 to recover the sum of $51,286.18, together with interest thereon.

*520 Both defendants filed answers in which, they deified liability. They undertook to rely on the following defenses : 1. That the details of installation did not appear in the plans, drawings, and specifications, and that they were not provided with the manufacturer’s directions containing details for the installation of the terra cotta; and that they installed the terra cotta in a workmanlike manner according to accepted standards and practice in masonry in this locality; 2. That the plans and specifications were faulty in that they failed to provide for expansion joints; 3. That the architect and the contractor had supervisors on the job and did not object to the manner in which The Wright Company installed the tile; 4. That the work had been approved and accepted by the architect and the owner and The Wright Company paid in full. The cause was tried to a jury, and the following issues were submitted:

“ISSUES OF FACT
“I
“Did the defendant subcontractor fail to install the terra cotta in accordance with the general conditions of the contract between Sears Roebuck & Company and F. T. Thayer, Jr., the complainant general contractor, and in accordance with the drawings and specifications prepared by the architect A. L. Aydelott & Associates: Answer Yes or No. If your answer to issue No. I is No it is not necessary that you answer No. II. If your answer to issue No. I is Yes, then you will answer issue No. II.
“II
“What damages were sustained by the complainant general contractor as a result of the failure of the *521 defendant subcontractor to install the terra cotta in accordance with the general conditions of the contract between Sears Roebuck & Company and the complainant general contractor, and in accordance with the drawings and specifications prepared by the architect? Answer in dollars and cents $-”

To issue No. I, the jury answered “Yes”; and to issue No. II, the jury answered $44,235.09”.

Defendants moved for a new trial and the complainant moved for a decree on the verdict, for allowance of a 5% override, and for allowance of attorneys’ fees, which questions the Chancellor had reserved, together with interest on the amount recovered. Proof was heard by the Chancellor on complainant’s claim for 5% override and for attorneys’ fees and for interest, but he denied complainant’s claim for either of these items. After the defendants’ motion for new trial was overruled, both defendants prayed and perfected their appeal to the Court of Appeals. The complainant also prayed and perfected his appeal from the ruling of the Chancellor denying interest on the recovery, denying the 5% override claimed by complainant, and denying the allowance of attorneys’ fees as part of the complainant’s damages.

As appellants in this Court, the defendants, The Wright Company and the United Pacific Insurance Co., have filed thirteen assignments of error. These assignments present eight questions to be determined by this Court. Assignments I and III claim that the verdict was contrary to the preponderance of the evidence, and assignments IV and Y assert that there was no evidence to support the verdict of the jury. Assignment II complains as to the form of issue I as submitted to the jury. *522

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deron A. Hatton v. CSX Transportation
Court of Appeals of Tennessee, 2004
Safeco Insurance Co. of America v. City of White House
133 F. Supp. 2d 621 (M.D. Tennessee, 2000)
Remco Equipment Sales, Inc. v. Manz
952 S.W.2d 437 (Court of Appeals of Tennessee, 1997)
Cassidy v. Spectrum Rents
959 F. Supp. 823 (E.D. Tennessee, 1997)
Howard G. Lewis Construction Co. v. Lee
830 S.W.2d 60 (Court of Appeals of Tennessee, 1991)
Agristor Leasing v. A.O. Smith Harvestore Products
869 F.2d 264 (Third Circuit, 1989)
John J. Heirigs Const. Co., Inc. v. Exide
709 S.W.2d 604 (Court of Appeals of Tennessee, 1986)
Pinney v. Tarpley
686 S.W.2d 574 (Court of Appeals of Tennessee, 1984)
Johnson v. Tennessee Farmers Mutual Insurance Co.
556 S.W.2d 750 (Tennessee Supreme Court, 1977)
Goings v. Aetna Casualty and Surety Company
491 S.W.2d 847 (Court of Appeals of Tennessee, 1972)
Crews v. United Benefit Insurance Co.
472 S.W.2d 887 (Court of Appeals of Tennessee, 1971)
Farmers Chemical Ass'n v. Maryland Casualty Co.
421 F.2d 319 (Sixth Circuit, 1970)
Southern Roofing & Petroleum Co. v. Aetna Insurance Co.
293 F. Supp. 725 (E.D. Tennessee, 1968)
Glazer v. Glazer
278 F. Supp. 476 (E.D. Louisiana, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
362 S.W.2d 805, 50 Tenn. App. 515, 1961 Tenn. App. LEXIS 147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thayer-v-wright-company-tennctapp-1961.