Howard G. Lewis Construction Co. v. Lee

830 S.W.2d 60, 1991 Tenn. App. LEXIS 782
CourtCourt of Appeals of Tennessee
DecidedSeptember 27, 1991
StatusPublished
Cited by21 cases

This text of 830 S.W.2d 60 (Howard G. Lewis Construction Co. v. Lee) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard G. Lewis Construction Co. v. Lee, 830 S.W.2d 60, 1991 Tenn. App. LEXIS 782 (Tenn. Ct. App. 1991).

Opinion

TOMLIN, Presiding Judge, Western Section.

Howard G. Lewis Construction Company, Inc., (hereafter “Lewis” or “plaintiff”), filed suit in the Chancery Court of Shelby County to enforce a mechanic’s and materi-almen’s lien against Jerry Lee, Trustee, and Sheu Chong Lee, d/b/a Jade East Restaurant, (hereafter “defendant” or “Jade East”). Lewis sought a judgment for unpaid labor and material pursuant to a construction contract with defendant in the amount of $25,664.20. Jade East filed its answer as well as a counter-claim, subsequently amended, by which it sought damages from Lewis for amounts paid by Jade East to Lewis’ sub-contractors to settle claims against Jade East. In addition, Jade East sought damages for alleged deficiencies in the work Lewis performed for defendant. Jade East subsequently filed an amended complaint against Exchange Mutual Insurance Company (hereafter “Exchange Mutual”) seeking recovery under a performance bond issued by Exchange Mu[62]*62tual in favor of Lewis. The specific questions were referred to a Master, pursuant to court order.

The chancellor confirmed the Master’s report. Following a bench trial, summary judgment was granted in favor of Exchange Mutual on defendant’s counterclaim. The chancellor also entered judgment for plaintiff in the amount of $11,-651.90 plus pre-judgment interest, post-judgment interest, and reasonable attorney fees. Following a hearing by a special chancellor, plaintiff was awarded attorney fees in the amount of $22,852.00.

Defendant raises five issues on appeal. Did the trial court err: (1) in awarding attorney fees to plaintiff; (2) in awarding pre-judgment interest to plaintiff; (3) in denying defendant the opportunity to present proof on damages concerning repairs made to the kitchen floor; (4) in confirming the Master’s report notwithstanding that the Master heard evidence outside the scope of the reference; and (5) in dismissing the counter-claim against Exchange Mutual. Exchange Mutual has raised as an issue on appeal whether or not the appeal is frivolous. We reverse the trial court as to the award of attorney fees and pre-judgment interest. In all other respects we affirm.

In December, 1978, plaintiff entered into a contract with defendant for the purpose of making certain improvements on defendant’s property known as the Jade East Restaurant. Exchange Mutual issued a performance bond to secure Lewis’ performance in favor of Jade East. Lewis, as general contractor, and his sub-contractors undertook to do the work specified by the contract. Jade East was represented by an architect during the course of construction.

There appear to be no problems concerning payment being made from time to time during the course of the construction. Jade East occupied the building in mid-January, 1980 and opened its restaurant on January 30, 1980. Lewis thereafter submitted a written request for final payment, which was refused by Jade East. In July, 1980 Lewis instigated this suit by filing a “Complaint to Enforce Mechanic’s and Ma-terialmen’s Lien, and for Attachment.”

Plaintiff’s complaint against defendant alleged in essence that defendant was the owner of certain real property in Memphis, that it entered into a contract with plaintiff for the construction of certain improvements on the property, and that plaintiff, as general contractor, furnished labor and materials for the erection of the building specified. The complaint further alleged that plaintiff was not paid for labor and material and that defendant was liable to plaintiff for the amount stated. Plaintiff stated that a notice of lien had been timely filed against the property, a lien was claimed, and that the property should be attached to satisfy the lien and defendant’s obligation to plaintiff.

Jade East’s answer contained its initial counter-claim against Lewis which alleged that three of Lewis’ sub-contractors had not been paid for work done on the Jade East job. It was contended that those subcontractors filed suits to enforce their mechanic’s and materialmen’s lien. Those suits resulted in payments to them in excess of $19,000 to settle their claims, and this sum was credited on Lewis’ account with the sub-contractors. Jade East demanded judgment against Lewis for that sum.

In its answer to the counter-claim Lewis denied fault insofar as the sub-contractors were concerned. Rather, Lewis asserted that the sub-contractors had not performed their work completely or properly pursuant to the contract, and that defendant elected to pay and release them, leaving Lewis with no effective recourse against them.

In Jade East’s amendment to its counterclaim, it asserted many deficiencies in the performance of the construction contract by Lewis, maintaining that those imperfections were never corrected or completed, and that the deficiencies constituted damages for which they were entitled to compensation from Lewis. These new allegations were, of course, denied by Lewis.

Defendant filed a motion to have the chancellor submit the issues of damages and the question of whether or not Lewis [63]*63complied with the contract’s specifications to the Clerk and Master. Although opposed by Lewis, an order of reference was entered. The order provided that the Master was directed to hear proof and report to the court as follows:

1. What deficiences [sic], if any, there are in the work performed with respect to the contract specifications.
2. Whether the Cross-Plaintiff is entitled to have these deficiences [sic] corrected under the terms of the contract.
3. What damages have resulted, if any, as a result of any deficiences [sic] in the job.
All other matters are reserved until the incoming of the Master’s report.

A hearing or hearings were held by the Master pursuant to the order of reference. However, there is no transcript of such a hearing or hearings in this record. The crux of the Master’s report is as follows:

QUERY 1:
What deficiencies, if any, are there in the work performed with respect to the contract specifications.
FINDING 1:
During the course of the hearing, the defendant waived some of the minor defects as contained in earlier punch lists. The major deficiencies were: kitchen floor, roof, and parking lot.
The Master finds that the parking lot was not laid according to specifications; that the kitchen floor did not drain properly; and that the roof did not drain properly. The Master finds that the negotiations of the parties relative to the kitchen ventilation systems has relieved the contractor of any liability for faulty design, installation or substitution of the system specified in the plans. (Ref.Ex. 43).
QUERY 2:
Whether the Cross-Plaintiff is entitled to have these deficiencies corrected under the terms of the contract.
FINDING 2:
The Master finds that the Cross-Plaintiffs are entitled to have the deficiencies corrected.
QUERY 3:
What damages have resulted, if any, as a result of any deficiencies in the job.
FINDING 3:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher J. Etheridge, Selena A. v. YMCA and West Tennessee
391 S.W.3d 541 (Court of Appeals of Tennessee, 2012)
Stephen George Beem v. Joan Nan Gallina Beem
Court of Appeals of Tennessee, 2010
Parkway Associates, LLC v. Harleysville Mutual Insurance
129 F. App'x 955 (Sixth Circuit, 2005)
Fossett v. Gray
173 S.W.3d 742 (Court of Appeals of Tennessee, 2004)
Paul Rector v. Elizabeth Halliburton
Court of Appeals of Tennessee, 2003
Wills Electric Co., Inc. v. Hassan Mirsaidi
Court of Appeals of Tennessee, 2001
William Patrick Varley, Jr. v. Pamela Dawn Varley
Court of Appeals of Tennessee, 2001
Thomas C. Farnsworth, Jr. v. Gary P. Faulkner
Court of Appeals of Tennessee, 2001
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Molin, M.D., et . ux. v. Perryman Construction Co.
Court of Appeals of Tennessee, 1998
Reliance Insurance Co. v. WSN Leasing, Inc.
Court of Appeals of Tennessee, 1997
Morrow v. Bobbitt
943 S.W.2d 384 (Court of Appeals of Tennessee, 1996)
Varley v. Varley
934 S.W.2d 659 (Court of Appeals of Tennessee, 1996)
Carol Louise Kepler v. Scott James Kepler
Court of Appeals of Tennessee, 1996
Wilder v. Tennessee Farmers Mutual Insurance
912 S.W.2d 722 (Court of Appeals of Tennessee, 1995)
Meyer v. Bryson
891 S.W.2d 223 (Court of Appeals of Tennessee, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
830 S.W.2d 60, 1991 Tenn. App. LEXIS 782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-g-lewis-construction-co-v-lee-tennctapp-1991.