Claiborne Hauling, LLC v. Wisteria Park, LLC

CourtCourt of Appeals of Tennessee
DecidedAugust 16, 2010
DocketE2009-02667-COA-R3-CV
StatusPublished

This text of Claiborne Hauling, LLC v. Wisteria Park, LLC (Claiborne Hauling, LLC v. Wisteria Park, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Claiborne Hauling, LLC v. Wisteria Park, LLC, (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE July 7, 2010 Session

CLAIBORNE HAULING, LLC v. WISTERIA PARK, LLC

Appeal from the Chancery Court for Knox County No. 170952-2 Daryl R. Fansler, Chancellor

No. E2009-02667-COA-R3-CV - AUGUST 16, 2010

Claiborne Hauling, LLC, contracted with Wisteria Park, LLC, to perform the excavating and grading, including installation of storm sewers and sanitary sewers, for a residential subdivision Wisteria was developing. The contract calls for Claiborne Hauling to commence work on November 6, 2006, with a substantial completion date of April 5, 2007. The contract further provides that Claiborne Hauling will receive a bonus of $500 per day for early completion but will pay a $500 per day “penalty” if completion extends past May 31, 2007. Claiborne did not finish by May 31, 2007. Wisteria “fired” Claiborne Hauling during a heated exchange in August 2007, and confirmed termination of the contract in a letter from counsel. The ground stated for termination is failure to complete the project by May 31, 2007. However, Wisteria did not secure approval of its plans for construction of the sewer system until June 8, 2007. When Wisteria did not pay the invoices and change orders outstanding at the time of the termination, Claiborne Hauling first sent a “prompt pay notice” and then filed this action alleging breach of contract against Wisteria. Wisteria answered and filed a counterclaim asserting, among other things, that it was entitled to recover $500 per day from May 31, 2007, until substantial completion, as liquidated damages. After a bench trial, the court found that Wisteria was guilty of the first material breach and awarded Claiborne Hauling a judgment in the amount of $301,430.62, which included attorney fees under the Prompt Pay Act, Tenn. Code Ann. § 66-34-602 (2004). Wisteria appeals. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

C HARLES D. S USANO, J R., J., delivered the opinion of the Court, in which H ERSCHEL P. F RANKS, P.J., and J OHN W. M CC LARTY, J., joined.

W. Tyler Chastain and Margo J. Maxwell, Knoxville, Tennessee, for the appellant, Wisteria Park, LLC. Garrett P. Swartwood, Knoxville, Tennessee, for the appellee, Claiborne Hauling, LLC.

OPINION

I.

The contract between the parties is dated November 6, 2006. In the contract Claiborne Hauling undertakes to do site preparation for the subdivision per the furnished plans “in the listed scope of work for a lump sum of $1,077,488.00.” The listed scope of work is limited to soil erosion control, clearing and grubbing, earthwork, storm sewer system, sanitary sewer system, water system, and mobilization. “Any work not listed” is excluded from Claiborne Hauling’s scope of work. The contract specifically excludes, from Claiborne Hauling’s responsibility, rock excavation, fees or permits, utility relocation, dewatering, and unsuitable soil removal. With regard to rock excavation and unsuitable soil the contract includes a unit price and provides

These additional quantities would be submitted along with an engineering letter verifying such qualities & quantities. These charges would be paid as an extra/change order to the lump sum/draw submitted for this contract agreement.

(Capitalization in original omitted.) The contract sets a commencement and completion date in the following terms:

Date of commencement to be November 6, 2006 with a substantial completion date of April 5, 2007, if in fact the contractor listed would complete scope of work shown before April 5, 2007 a $500.00 per day fee would be paid from the owner to such contractor for early completion. Paving and/or utilities not listed would not be a part of this restriction and in return if in fact completion date extends past May 31, 2007 exclusions again being utilities not listed or the paving process a $500.00 per day penalty fee could be assessed to the final payment owed for such work.

Claiborne Hauling’s draws are subject to a 10% retainage, with the retainage being “due upon completion.”

-2- It is undisputed in this case that Claiborne Hauling could not, as a practical matter, commence work on the sanitary sewer until Wisteria obtained approval of its plans from West Knox Utility District (“WKUD”) and the Tennessee Department of Environmental and Conservation (“TDEC”). It is further undisputed that WKUD did not approve the plans until May 17, 2007, and TDEC did not approve the plans until June 8, 2007. Also, there is no dispute in this case that Wisteria , and not Claiborne Hauling, had the duty to obtain approval of the sewer plans for its development. Todd Claiborne, the general manager for Claiborne Hauling, testified that he was ready to begin work on the sanitary sewer in January 2007, and so informed Wisteria. He further testified that he slowed his work on other phases of the project, even to the point of eliminating one crew, because of the delay in the approval of the sewer plans. Thus, it is Claiborne Hauling’s position that the delay in completion was because of Wisteria’s failure to secure approval of the sewer plans. Wisteria, on the other hand, claims that Claiborne Hauling was so far behind in other phases of the project, including the roads, that the delay in securing the plans had no impact.

Claiborne Hauling commenced work in November 2006, at about the same time the contract was signed. Because of the terrain of the land, including its proximity to a stream, Claiborne Hauling soon encountered soils that were unsuitable for the compaction needed for a road. Claiborne verified the presence and amount of the unsuitable soils through an independent engineering firm, S & ME, and submitted a change order. The change order was approved and paid. Work progressed in much the same manner from November 2006, through the April completion date, until August 2007. Mr. Chip Leonard, one of the owners of Wisteria who monitored the project, testified that even though he was not satisfied that progress on the project was in line with the schedule or the claims made by Claiborne Hauling for draws, he would “sometimes . . . let things go just so we didn’t have conflict and so we didn’t stall the project, just to keep everybody motivated and going.” He made the deliberate choice not to “rock the boat.” The other principal in Wisteria, Mr. David Dalton, testified that he and Chip Leonard discussed the delay in completion and decided that, knowing “we started getting into May and we knew we were nowhere close to being finished[,] . . . we wanted to give Claiborne Hauling every opportunity to get the project finished.” They decided that such an approach “was in our best interest.”

There is no doubt that by early May 2007, Claiborne Hauling was ready to start on the sanitary sewer lines and that it notified Wisteria of its need for approved plans.1 Wisteria then secured the approval of both WKUD and TDEC by June 8, 2007. In an effort to expedite completion of the project, Claiborne Hauling contracted with Robby Giles to install the sanitary sewer. Giles was to use his own crew and oversee installation of one of

1 As we have indicated, there is a dispute in the testimony concerning whether Claiborne Hauling was ready to start work on the sewer in January or February 2007 and so notified Wisteria.

-3- Claiborne Hauling’s crews. Giles encountered solid bedrock at approximately 3 to 4 feet along much of the length of the sewer line. Also, water flooded the ditches from both surface runoff and underground springs. These problems necessitated change orders. Again, S & ME verified the presence of the rock and the wet conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
Kesterson v. Varner
172 S.W.3d 556 (Court of Appeals of Tennessee, 2005)
Barnes v. Barnes
193 S.W.3d 495 (Tennessee Supreme Court, 2006)
Shepherd v. Perkins Builders
968 S.W.2d 832 (Court of Appeals of Tennessee, 1997)
Money & Tax Help, Inc. v. Moody
180 S.W.3d 561 (Court of Appeals of Tennessee, 2005)
Trinity Industries, Inc. v. McKinnon Bridge Co.
77 S.W.3d 159 (Court of Appeals of Tennessee, 2001)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Claiborne Hauling, LLC v. Wisteria Park, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/claiborne-hauling-llc-v-wisteria-park-llc-tennctapp-2010.