Advanced Concrete Tools, Inc. v. Herman Beach

525 F. App'x 317
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 1, 2013
Docket12-5590
StatusUnpublished
Cited by5 cases

This text of 525 F. App'x 317 (Advanced Concrete Tools, Inc. v. Herman Beach) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Concrete Tools, Inc. v. Herman Beach, 525 F. App'x 317 (6th Cir. 2013).

Opinions

OPINION

BERNICE B. DONALD, Circuit Judge.

In this diversity action, Appellee Advanced Concrete Tools, Inc. (“ACT”) brought a breach of contract claim against Appellant Herman W. Beach and Manown Engineering Co., Inc. (“Manown”). Beach and Manown filed a counterclaim for breach of contract. Subsequently, Beach and Manown filed a motion for partial summary judgment on the sole issue of damages, contingent upon the court finding them liable for breach. The district court granted the motion, determined the amount of damages, and, sua sponte, entered judgment in favor of ACT on the issue of liability. For the following reasons, we reverse the judgment of the district court and remand for further proceedings.

I.

On June 5, 2007, Beach and Manown entered into an Asset Purchase Agreement (“APA”) with ACT. Under the APA, Beach and Manown were to purchase certain assets from ACT, including various tools and equipment manufactured by ACT, for $1,100,000. On July 1, 2007, the parties amended the terms of the APA, allocating payment as follows:

(i) $600,000 cash payable upon completion of the sale of assets hereunder on the following schedule:
a. $290,000.00 on the date of closing.
b. $10,000.00 escrow deposit.
[319]*319c. $200,000.00 within 60 days following the date of closing together with interest thereon at the rate of six percent (6%) per annum.
d. $100,000.00 within 90 days following the date of closing together with interest thereon at the rate of six percent (6%) per annum.
(ii) Plus quarterly payment equal to 2% of gross sales of screeds, screed bars, saddle clamps, concrete bomb, and other screed related products sold by Advanced Concrete Tools Inc. at the time of closing of this transaction until seller has been paid $500,000. Such payments will begin fifteen months after completion of the sale hereunder.

The amendment did not contain an acceleration clause.

On July 10, 2007, the parties closed on the sale. Pursuant to the terms of the amended APA, within ninety days of closing, Beach and Manown paid ACT $600,000; the remaining $500,000 was due in installments beginning in October 2008.

Beach and Manown claimed that, subsequent to closing, they discovered problems with the materials purchased from ACT under the APA. They further argued that these problems affected the gross sales of the products, thereby affecting their ability to make the 2% payments required under Section (ii) of the APA. Consequently, Beach and Manown did not make any payments towards the $500,000 balance.

ACT filed a suit for breach of contract in state court, and Beach and Manown successfully removed the action to federal court based on diversity jurisdiction. Beach and Manown also filed four counterclaims, three of which were dismissed on statute of limitations grounds on ACT’s motion for partial summary judgment, with a breach of contract counterclaim remaining. On October 4, 2011, Beach and Manown filed a motion for partial summary judgment on the sole issue of the proper measure of damages on ACT’s breach of contract claim. The district court granted the motion, determined that the amount of damages was $500,000, plus prejudgment interest, and, sua sponte, entered judgment on the issue of liability in favor of ACT. Beach and Manown timely appealed.1

II.

Beach first challenges the district court’s sua sponte entry of summary judgment in favor of ACT. He contends that because the district court failed to provide him with sufficient notice that it would rule on the issue of liability, it erred as a matter of law in entering judgment. We review a district court’s sua sponte grant of summary judgment for abuse of discretion. Bennett v. City of Eastpointe, 410 F.3d 810, 816 (6th Cir.2005). A finding of an abuse of discretion is nonetheless subject to harmless error analysis, in which the aggrieved party must demonstrate prejudice in order to prevail. Smith v. Perkins Bd. of Educ., 708 F.3d 821, 829 (6th Cir.2013).

A. Notice

While the practice is not favored, we have long recognized a district court’s authority to enter summary judgment on grounds not advanced by either or any party. See id.; Excel Energy v. Cannelton Sales Co., 246 F. App’x 953, 959 (6th Cir.2007). This, however, is only permitted where “the losing party was on notice [320]*320that [it] had to come forward with all of [its] evidence.” Celotex Corp. v. Catrett, 477 U.S. 317, 326, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986) (emphasis added). “The clearly established rule in this circuit is that a district court must afford the party against whom sua sponte summary judgment is to be entered ten-days notice and an adequate opportunity to respond.” Yashon v. Gregory, 737 F.2d 547, 552 (6th Cir.1984). “Notice and opportunity are determined from the totality of the proceedings below, including whether any party filed a motion for summary judgment on the claim and whether the losing party addressed the claim in its arguments.” Aubin Indus., Inc. v. Smith, 321 Fed. Appx. 422, 423 (6th Cir.2008).

Considering the totality of the proceedings, we find that the district court erred in sua sponte granting summary judgment. Although ACT and Beach each filed motions for summary judgment, neither party moved for summary judgment on the issue of liability for breach of contract. While unusual, Beach filed a motion for summary judgment on damages alone — in the event the court were to subsequently find him liable for breach. The issue of liability was not briefed by Beach, and the evidence submitted pertained to the calculation of damages based on revenue records and deposition testimony on the lack of a requirement of future manufacturing of ACT products, products Beach was required to sell in order to pay the 2% due under the amended APA. ACT’s memorandum of law in response to Beach’s motion for partial summary judgment assumes breach on the part of Beach, but nonetheless, argues contract interpretation only as it applies to the measure of damages. And, most importantly, the district court did not inform Beach that it was considering the issue of liability in conjunction with the measure of damages prior to its ruling.

Even if Beach had been on notice, the district court’s opinion failed to address his counterclaim for breach of contract, which, in this case, we view as potentially relevant to determining liability.2 Beach’s counterclaim was based on certain warranties in the APA. Under the Uniform Commercial Code (“UCC”), to which Tennessee adheres, a counterclaim for breach of warranty would surely require an analysis of rejection or acceptance of the goods and any potential setoff damages. See Audio Visual Artistry v. Tanzer, 403 S.W.3d 789, 806-08, No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
525 F. App'x 317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-concrete-tools-inc-v-herman-beach-ca6-2013.