Patricia Harper v. Eric Dixon

CourtCourt of Appeals of Tennessee
DecidedMay 16, 2016
DocketE2015-00411-COA-R3-CV
StatusPublished

This text of Patricia Harper v. Eric Dixon (Patricia Harper v. Eric Dixon) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patricia Harper v. Eric Dixon, (Tenn. Ct. App. 2016).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs January 7, 2016

PATRICIA HARPER v. ERIC DIXON ET AL.

Appeal from the Circuit Court for Sevier County No. 13-CV-451-IV O. Duane Slone, Judge

No. E2015-00411-COA-R3-CV-FILED-MAY 16, 2016

This is a breach of contract action involving a residential kitchen remodeling project. The plaintiff homeowner filed a complaint against the defendant contractor and his construction company, alleging that the contractor had breached the parties‟ contract by failing to complete the project and walking off the job. The contractor filed a counter- complaint, alleging, inter alia, that the homeowner owed the construction company funds for work completed and reimbursement of material costs. Following a bench trial, the trial court dismissed the individual contractor as a party but found that the construction company had materially breached the contract. Setting off the amount the homeowner owed contractually from the damages determined, the court awarded a judgment to the homeowner in the amount of $3,555.40. The homeowner appeals the amount of the damages award and the set-off. She further appeals the trial court‟s denial of her oral motion to allow her substitution as party plaintiff in the capacity of trustee for her son, to whom she had conveyed her interest in the home in trust. Having determined that the trial court made two mathematical errors in calculating the final award to the homeowner, we modify the award to $4,055.40. We affirm the judgment in all other respects.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed as Modified; Case Remanded

THOMAS R. FRIERSON, II, J., delivered the opinion of the court, in which D. MICHAEL SWINEY, C.J., and CHARLES D. SUSANO, JR., J., joined.

Steven E. Marshall, Sevierville, Tennessee, for the appellant, Patricia Harper.

Bryan E. Delius and Bryce W. McKenzie, Sevierville, Tennessee, for the appellee, Eric Dixon Construction, LLC.

1 OPINION

I. Factual and Procedural Background

On January 10, 2013, the plaintiff, Patricia Harper DeArmond, entered into a written contract with the defendant construction company, Eric Dixon Construction, LLC, (“Dixon Construction”), represented by co-defendant Eric Dixon. Ms. Harper1 agreed to pay a total of $12,000.00 in return for Dixon Construction‟s remodeling the kitchen in Ms. Harper‟s residence (“Remodeling Project”), located at 305 Evergreen Drive in Sevierville, Tennessee (“the Property”). Mr. Dixon previously had constructed houses working with Ms. Harper‟s husband, David DeArmond, who had also worked as a contractor. Dixon Construction had performed limited work for Ms. Harper in the past.

The contract, admitted as an exhibit at trial, specifically provides in pertinent part:

This contract is for the remodel of kitchen flooring removal and reinstallation labor (approx. 310sq.ft.), removal of existing kitchen cabinets and reinstallation labor of new cabinets, the removal of 23'lx8'h existing frame wall and installation of new beam and support post in place of existing wall, the reworking of existing plumbing in slab floor for island sink and new kitchen sink, the framing of a false ceiling in the new [addition] of kitchen already existing (approx. 23'x8'), [i]nstallation of 3'x6'8" door thru existing frame wall between new [addition] and pantry, the wiring of 3 electrical circuits for new kitchen receptacles, stove, and lights, also the labor of leveling the floor in new [addition] back to older existing kitchen floor. Materials furnished by Contractor will consist of framing material for beam, support, false ceiling framing, wiring for 3 electric circuits and rough-in boxes for switches and receptacles. [T]he rest of materials to be furnished by Patricia Ann Harper De[A]rmond. The cost of the contract is to be twelve thousand dollars ($12,000.00), to be paid as follows, three thousand dollars ($3,000.00) to be paid up front, five thousand dollars ($5,000.00) to be paid after cabinets, flooring, wall has been removed and beam and new false ceiling framing installed, three thousand dollars ($3,000.00) to be paid after new tile flooring existing of 16"x16" porcelian [sic] tiles is installed, and the remaining one thousand dollars ($1,000.00) is to be paid after cabinet installation. Contractor agrees to set formica kitchen tops only, all others will be responsibility of

1 Ms. Harper executed the contract using her full married name of Patricia Ann Harper DeArmond. Although she is referred to alternatively as Ms. Harper and Ms. DeArmond throughout the record, in keeping with the style of the case, we will refer to the plaintiff as “Ms. Harper” throughout this opinion. 2 Patricia Ann Harper De[A]rmond. In the case of collections all fees and charges will be paid by Patricia Ann Harper De[A]rmond.

Approximately one week following execution of the contract, Dixon Construction began work on the Remodeling Project. The parties subsequently executed two addendums to the contract, both dated March 21, 2013. The first addendum required Dixon Construction to add five electrical circuits to the kitchen in return for an additional $1,800.00. The second addendum required Dixon Construction to add two ceiling light boxes, hang two ceiling tiles, and rework the kitchen sink base to accommodate a farm sink for an additional $625.00. The cost of the contract with addendums totaled $14,425.00. It is undisputed that Ms. Harper made the first three payments in respective amounts of $3,000.00; $5,000.00; and $3,000.00 as contracted, for a total amount paid to Dixon Construction of $11,000.00. She did not pay Dixon Construction the final $1,000.00 provided in the original contract; the $1,800.00 provided in the first addendum; or the $625.00 provided in the second addendum. The total unpaid balance was $3,425.00.

Dixon Construction continued work on the Remodeling Project until a disagreement over modification of an oven cabinet and placement of a microwave in the cabinet led to an altercation between Mr. Dixon and Mr. DeArmond.2 A photograph admitted into evidence at trial demonstrates that the microwave placement in the oven cabinet was above Ms. Harper‟s head, and it was undisputed at trial that such placement was unsafe. Although Mr. Dixon testified that Ms. Harper had insisted on the modification because she did not want to wait for shipment of an oven cabinet with the proper specifications, Ms. Harper testified that she never approved the placement of the microwave. Ms. Harper stated that when she confronted Mr. Dixon, asserting that the microwave placement “had to be redone,” Mr. Dixon became angry and struck Mr. DeArmond. Ms. Harper further testified that she felt threatened during the altercation and ordered Mr. Dixon off the Property. Mr. Dixon did not deny that he had struck Mr. DeArmond. Mr. Dixon‟s testimony corroborated that Ms. Harper had ordered him to leave the Property.

Mr. Dixon testified that Dixon Construction had substantially completed the Project except for the installation of a 3'x6'8" door through the existing frame wall between the new addition and the pantry. Ms. Harper, however, maintained that several elements of the Project remained unfinished.

On April 29, 2013, Dixon Construction filed an action in the Sevier County General Sessions Court against Ms. Harper, alleging breach of contract and requesting 2 The record is silent as to the date of the altercation or the date that Dixon Construction‟s work on the Project stopped. 3 damages in the amount of $3,425.00 plus attorney‟s fees and costs. On July 24, 2013, Ms. Harper filed a complaint in the Sevier County Circuit Court against Mr. Dixon individually and Dixon Construction, alleging breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betty Saint Rogers v. Louisville Land Company
367 S.W.3d 196 (Tennessee Supreme Court, 2012)
Delwin L. Huggins, John P. Konvalinka v. R. Ellsworth McKee
403 S.W.3d 781 (Court of Appeals of Tennessee, 2012)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Rondal Akers v. Buckner-Rush Enterprises, Inc.
270 S.W.3d 67 (Court of Appeals of Tennessee, 2007)
Cracker Barrel Old Country Store, Inc. v. Epperson
284 S.W.3d 303 (Tennessee Supreme Court, 2009)
United Brake Systems, Inc. v. American Environmental Protection, Inc.
963 S.W.2d 749 (Court of Appeals of Tennessee, 1997)
Wood v. Starko
197 S.W.3d 255 (Court of Appeals of Tennessee, 2006)
GSB Contractors, Inc. v. Hess
179 S.W.3d 535 (Court of Appeals of Tennessee, 2005)
Jones v. Garrett
92 S.W.3d 835 (Tennessee Supreme Court, 2002)
Rawlings v. John Hancock Mutual Life Ins. Co.
78 S.W.3d 291 (Court of Appeals of Tennessee, 2001)
ARC LifeMed, Inc. v. AMC-Tennessee, Inc.
183 S.W.3d 1 (Court of Appeals of Tennessee, 2005)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
Wilhite v. Brownsville Concrete Co., Inc.
798 S.W.2d 772 (Court of Appeals of Tennessee, 1990)
St. John v. Bratton
150 S.W.2d 727 (Court of Appeals of Tennessee, 1941)
State, Dept. of Human Services v. Hauck
872 S.W.2d 916 (Court of Appeals of Tennessee, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Patricia Harper v. Eric Dixon, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patricia-harper-v-eric-dixon-tennctapp-2016.