Ray Bell Construction Company, Inc. v. State of Tennessee, Tennessee Department of Transportation

356 S.W.3d 384, 2011 Tenn. LEXIS 1143, 2011 WL 6148667
CourtTennessee Supreme Court
DecidedDecember 12, 2011
DocketE2009-01803-SC-R11-CV
StatusPublished
Cited by43 cases

This text of 356 S.W.3d 384 (Ray Bell Construction Company, Inc. v. State of Tennessee, Tennessee Department of Transportation) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ray Bell Construction Company, Inc. v. State of Tennessee, Tennessee Department of Transportation, 356 S.W.3d 384, 2011 Tenn. LEXIS 1143, 2011 WL 6148667 (Tenn. 2011).

Opinion

OPINION

JANICE M. HOLDER, J„

delivered the opinion of the Court,

in which CORNELIA A. CLARK, C.J., and GARY R. WADE, WILLIAM C. KOCH, JR., and SHARON G. LEE, JJ., joined.

A construction company entered into a contract with the State of Tennessee to restructure an interstate interchange. The contract provides that the contract completion date “may be extended in accordance with the Standard Specifications, however, no incentive payment will be made if work is not completed in its entirety by December 15, 2006.” The Claims Commission found that the contract contained a latent ambiguity requiring extrinsic evidence to interpret the contract. The Claims Commission considered extrinsic evidence and concluded that the construction company was entitled to the maximum incentive payment and an extension of the contract completion date. A divided Court of Appeals affirmed the judgment of the Claims Commission. We hold that the contract is unambiguous- and does not permit an extension of the incentive date. Accordingly, we reverse the Court of Appeals and remand to the Claims Commission for modification of the final judgment.

I. Facts and Procedural History

Ray Bell Construction Company (“Ray Bell”) entered into a contract on May 28, 2003, with the Tennessee Department of Transportation (“TDOT”) to reconstruct the 1-240 and 1-40 interchange located in Memphis, Tennessee. Construction began on June 18, 2003, and was to be completed on or before December 15, 2006. The contract between Ray Bell and TDOT contained a provision that included both an incentive clause and a disincentive clause. The incentive clause provided Ray Bell a bonus if the contract work was completed on or before December 15, 2006. The disincentive clause provided a penalty for every day contract work remained incomplete after December 15, 2006.

The contract also provided for an extension of the completion date when work delays were caused by events outside the contractor’s control. During construction, Ray Bell encountered delays due to bridge closings by TDOT and other events beyond Ray Bell’s control. Ray Bell sought to extend the completion date of the contract to accommodate these delays.

*386 Ray Bell first requested a 289-day extension of the contract completion date. In response to Ray Bell’s request, TDOT proposed Supplemental Agreement 24, which would have extended the completion date and the disincentive date of the original contract by 137 calendar days to May 1, 2007. Ray Bell refused to execute the supplemental agreement, however, because the agreement stated that the incentive date would remain December 15, 2006.

Ray Bell notified the TDOT Engineer that it considered the contract work substantially complete. The Engineer inspected the project site and determined that the contract had been satisfactorily completed on December 17, 2006.

Following the completion of the contract, Ray Bell requested a 862-day extension of the completion date, the disincentive date, and the incentive date. TDOT again responded that it would grant a 137-day extension as to both the completion and disincentive dates but that the incentive date would remain December 15, 2006.

Ray Bell filed a complaint in the Tennessee Claims Commission alleging that TDOT had breached the contract by refusing to grant an appropriate time extension of the completion date, the disincentive date, and the incentive date. Ray Bell specifically sought an extension of the contract incentive date and the maximum award of $2,500,000 based on the language of the contract. TDOT maintained in its answer that the contract was deliberately and clearly written to allow for an extension of both the completion date and the disincentive date but that the contract did not permit an extension of the incentive date.

Both parties filed motions for summary judgment, which the Commissioner denied. The Commissioner conducted a trial to determine whether Ray Bell was entitled to the maximum incentive bonus “even though the contract was not completed by December 15, 2006, as seemingly strictly required by ... the original contract.” The Claims Commission found the contract contained “an egregious ambiguity” that required extrinsic evidence to interpret the contract. The Claims Commission considered extrinsic evidence and found that Ray Bell was entitled to the maximum incentive payment and to an extension of the completion date, the disincentive date, and the incentive date. The Claims Commission entered a judgment in favor of Ray Bell for $2,948,696.77. 1 A divided Court of Appeals affirmed the judgment of the Claims Commission. 2 Ray Bell Const. Co. v. Tenn. Dep’t of Transp., No. E2009-01803-COA-R3-CV, 2010 WL 4810670, at *15 (Tenn.Ct.App. Nov. 24, 2010). We granted TDOT permission to appeal.

II. Analysis

In interpreting a written contract, we review a written agreement de novo without affording any presumption of correctness to the lower court’s conclusions of law. Allstate Ins. Co. v. Watson, 195 S.W.3d 609, 611 (Tenn.2006). This *387 Court’s initial task is to determine whether the language in the contract is ambiguous. Planters Gin Co. v. Fed. Compress & Warehouse Co., 78 S.W.3d 885, 890 (Tenn. 2002). If the contract language is unambiguous, then the parties’ intent is determined from the four corners of the contract. See Whitehaven Cmty. Baptist Church v. Holloway, 973 S.W.2d 592, 596 (Tenn.1998).

The Claims Commission found that the contract between Ray Bell and TDOT contained a latent ambiguity when several contract provisions were read together. The provisions at issue were Special Provision 108B (the “Completion Provision”), which contains an incentive clause and a disincentive clause, and Standard Specification 108.06 (the “Extension Provision”), which addresses the extension of the completion date of the contract.

With respect to the incentive date, the Completion Provision provides:

For each calendar day prior to December 15, 2006, that all work in the original contract has been completed and all lanes are opened to the free, safe and unrestricted passage of traffic, an incentive payment of ten thousand dollars ($10,000) per day shall be made to the contractor as an incentive. However, the maximum amount of incentive payments shall not exceed two million five hundred thousand dollars ($2,500,000).

The Completion Provision’s disincentive clause provides:

For each day after December 15, 2006, that all work in the original contract is not completed, the sum of ten thousand dollars ($10,000) per day shall be deducted from monies due the Contractor as a disincentive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodney DeWayne Barrentine v. Jimmy J. Kinsler
Court of Appeals of Tennessee, 2024
Jackie L. Jones v. Unrefined Oil Company, Inc.
Court of Appeals of Tennessee, 2024
A & P Excavating And Materials, LLC v. David Geiger
Court of Appeals of Tennessee, 2020
Daphne Saunders v. Y-12 Federal Credit Union
Court of Appeals of Tennessee, 2020
Highlands Physicians, Inc. v. Wellmont Health System
Court of Appeals of Tennessee, 2020
Tennessee State Bank v. Douglas v. Mashek
Court of Appeals of Tennessee, 2020
In Re Estate of John E. Mayfield
Court of Appeals of Tennessee, 2019
Waste Servs. of Decatur, LLC v. Decatur Cnty.
367 F. Supp. 3d 792 (W.D. Tennessee, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
356 S.W.3d 384, 2011 Tenn. LEXIS 1143, 2011 WL 6148667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ray-bell-construction-company-inc-v-state-of-tennessee-tennessee-tenn-2011.