Opinion
NORCOTT, J.
The plaintiffs, Michael G. Economos and Bessie Economos, appeal, following our grant of certification,
from the judgment of the Appellate Court reversing the judgment of the trial court granting their application to vacate an arbitration award and denying the motion of the defendant, Liljedahl Brothers, Inc., to confirm that award in its favor.
Economos
v.
Liljedahl Bros., Inc.,
86 Conn. App. 578, 587, 862 A.2d 312 (2004). The plaintiffs claim that the Appellate Court improperly concluded that the arbitrator did not manifestly disregard the law when he awarded the defendant contractor damages for the breach of a home improvement con
tract, despite changes to the contract that failed to comply with the Home Improvement Act, General Statutes § 20-418 et seq., specifically General Statutes § 20-429 (a).
We disagree and, accordingly, we affirm the judgment of the Appellate Court.
The record and the Appellate Court opinion reveal the following relevant facts and procedural history. “On April 3, 2000, the parties entered into a home improvement contract in which the defendant agreed to renovate a bathroom and laundry room in the home of the plaintiffs. On September 15, 2000, the parties entered into a second home improvement contract in which the defendant agreed to remodel a kitchen and add a den to the plaintiffs’ house. Under the terms of each contract, any controversy arising out of the contracts was to be settled by arbitration.”
Economos
v.
Liljedahl Bros., Inc.,
supra, 86 Conn. App. 579.
During the course of the remodeling projects, the defendant submitted change orders
for additional work
completed on the project. The total added cost to the bathroom and laundry room project was $4460.49; the total added cost to the kitchen and den project was $16,348.12.
***5
“Subsequently, a dispute arose between the parties, and the defendant filed a demand for arbitration and a mechanic’s lien on the plaintiffs’ house. The plaintiffs responded by filing an answer, special defenses and an amended counterclaim. On December 17, 2001, the plaintiffs filed a motion for summary judgment, which was denied. Following the arbitration hearing, which encompassed nine days of testimony, the arbitrator awarded the defendant $81,890.24 and the plaintiffs $30,423.69 for a net award of $51,466.55 for the defendant. The award concluded: ‘This award is in full settlement of all claims and counterclaims submitted to this
Arbitration. All claims not expressly granted herein are hereby, denied.’ Subsequently, the arbitrator died, and the parties were referred to the court system by the American Arbitration Association for the resolution of any outstanding issues.
“On October 23, 2002, the plaintiffs, pursuant to General Statutes §§ 52-418 and 52-419, filed an application to vacate or to modify the arbitration award, claiming that the arbitrator ‘acted with evident partiality or corruption,’ refused to hear pertinent evidence and exceeded his powers. On November 7, 2002, the defendant, pursuant to General Statutes § 52-417, filed a motion to confirm the arbitration award and for an award of postarbitration interest. Following a hearing on the parties’ motions, the court denied the defendant’s motion to confirm the arbitration award and vacated the award because it failed to address three of the claims raised by the plaintiffs.” Id., 579-80.
The defendant appealed, claiming that the trial court “improperly (1) denied its motion to confirm the arbitrator’s award and (2) vacated the arbitrator’s award.” Id., 580. The plaintiffs countered that the trial court “properly vacated the arbitrator’s award and denied the defendant’s motion to confirm the award because the award (1) did not conform to the submission, (2) violated public policy and (3) was an ‘egregious application of the law . . . .’ ” Id. The Appellate Court did not reach the plaintiffs’ public policy claim; id., 587 n.2; but reversed the trial court’s judgment based on its conclusions that the award conformed with the submission
and was not an egregious application of the law.
Id., 583-84. This certified appeal followed as to the plaintiffs’ manifest disregard claim. See footnote 1 of this opinion.
Our analysis is guided by well established principles regarding a party’s application to vacate a consensual arbitration award resulting from an unrestricted submission. “Judicial review of arbitral decisions is
narrowly
confined. . . . When the parties agree to arbitration and establish the authority of the arbitrator through the terms of their submission, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . . Because we favor arbitration as a means of settling private disputes, we undertake judicial review of arbitration awards in a manner designed to minimize interference with an efficient and economical system of alternative dispute resolution. . . .
“Where the submission does not otherwise state, the arbitrators are empowered to decide factual and legal questions and an award cannot be vacated on the grounds that . . . the interpretation of the agreement by the arbitrators was erroneous. Courts will not review the evidence nor, where the submission is unrestricted, will they review the arbitrators’ decision of the legal questions involved. ... In other words, [u]nder an unrestricted submission, the arbitrators’ decision is considered final and binding; thus the courts will not review the evidence considered by the arbitrators nor will they review the award for errors of law or fact. . . .
“Even in the case of an unrestricted submission, we have . . . recognized three grounds for vacating an award: (1) the award mies on the constitutionality of a statute ... (2) the award violates clear public policy
. . . [and] (3) the award contravenes one or more of the statutory proscriptions of § 52-418.” (Internal quotation marks omitted.)
Harty
v.
Cantor Fitzgerald & Co.,
275 Conn. 72, 80-81, 881 A.2d 139 (2005). This appeal is limited to the third ground for vacatur, namely, noncompliance with § 52-418.
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion
NORCOTT, J.
The plaintiffs, Michael G. Economos and Bessie Economos, appeal, following our grant of certification,
from the judgment of the Appellate Court reversing the judgment of the trial court granting their application to vacate an arbitration award and denying the motion of the defendant, Liljedahl Brothers, Inc., to confirm that award in its favor.
Economos
v.
Liljedahl Bros., Inc.,
86 Conn. App. 578, 587, 862 A.2d 312 (2004). The plaintiffs claim that the Appellate Court improperly concluded that the arbitrator did not manifestly disregard the law when he awarded the defendant contractor damages for the breach of a home improvement con
tract, despite changes to the contract that failed to comply with the Home Improvement Act, General Statutes § 20-418 et seq., specifically General Statutes § 20-429 (a).
We disagree and, accordingly, we affirm the judgment of the Appellate Court.
The record and the Appellate Court opinion reveal the following relevant facts and procedural history. “On April 3, 2000, the parties entered into a home improvement contract in which the defendant agreed to renovate a bathroom and laundry room in the home of the plaintiffs. On September 15, 2000, the parties entered into a second home improvement contract in which the defendant agreed to remodel a kitchen and add a den to the plaintiffs’ house. Under the terms of each contract, any controversy arising out of the contracts was to be settled by arbitration.”
Economos
v.
Liljedahl Bros., Inc.,
supra, 86 Conn. App. 579.
During the course of the remodeling projects, the defendant submitted change orders
for additional work
completed on the project. The total added cost to the bathroom and laundry room project was $4460.49; the total added cost to the kitchen and den project was $16,348.12.
***5
“Subsequently, a dispute arose between the parties, and the defendant filed a demand for arbitration and a mechanic’s lien on the plaintiffs’ house. The plaintiffs responded by filing an answer, special defenses and an amended counterclaim. On December 17, 2001, the plaintiffs filed a motion for summary judgment, which was denied. Following the arbitration hearing, which encompassed nine days of testimony, the arbitrator awarded the defendant $81,890.24 and the plaintiffs $30,423.69 for a net award of $51,466.55 for the defendant. The award concluded: ‘This award is in full settlement of all claims and counterclaims submitted to this
Arbitration. All claims not expressly granted herein are hereby, denied.’ Subsequently, the arbitrator died, and the parties were referred to the court system by the American Arbitration Association for the resolution of any outstanding issues.
“On October 23, 2002, the plaintiffs, pursuant to General Statutes §§ 52-418 and 52-419, filed an application to vacate or to modify the arbitration award, claiming that the arbitrator ‘acted with evident partiality or corruption,’ refused to hear pertinent evidence and exceeded his powers. On November 7, 2002, the defendant, pursuant to General Statutes § 52-417, filed a motion to confirm the arbitration award and for an award of postarbitration interest. Following a hearing on the parties’ motions, the court denied the defendant’s motion to confirm the arbitration award and vacated the award because it failed to address three of the claims raised by the plaintiffs.” Id., 579-80.
The defendant appealed, claiming that the trial court “improperly (1) denied its motion to confirm the arbitrator’s award and (2) vacated the arbitrator’s award.” Id., 580. The plaintiffs countered that the trial court “properly vacated the arbitrator’s award and denied the defendant’s motion to confirm the award because the award (1) did not conform to the submission, (2) violated public policy and (3) was an ‘egregious application of the law . . . .’ ” Id. The Appellate Court did not reach the plaintiffs’ public policy claim; id., 587 n.2; but reversed the trial court’s judgment based on its conclusions that the award conformed with the submission
and was not an egregious application of the law.
Id., 583-84. This certified appeal followed as to the plaintiffs’ manifest disregard claim. See footnote 1 of this opinion.
Our analysis is guided by well established principles regarding a party’s application to vacate a consensual arbitration award resulting from an unrestricted submission. “Judicial review of arbitral decisions is
narrowly
confined. . . . When the parties agree to arbitration and establish the authority of the arbitrator through the terms of their submission, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . . Because we favor arbitration as a means of settling private disputes, we undertake judicial review of arbitration awards in a manner designed to minimize interference with an efficient and economical system of alternative dispute resolution. . . .
“Where the submission does not otherwise state, the arbitrators are empowered to decide factual and legal questions and an award cannot be vacated on the grounds that . . . the interpretation of the agreement by the arbitrators was erroneous. Courts will not review the evidence nor, where the submission is unrestricted, will they review the arbitrators’ decision of the legal questions involved. ... In other words, [u]nder an unrestricted submission, the arbitrators’ decision is considered final and binding; thus the courts will not review the evidence considered by the arbitrators nor will they review the award for errors of law or fact. . . .
“Even in the case of an unrestricted submission, we have . . . recognized three grounds for vacating an award: (1) the award mies on the constitutionality of a statute ... (2) the award violates clear public policy
. . . [and] (3) the award contravenes one or more of the statutory proscriptions of § 52-418.” (Internal quotation marks omitted.)
Harty
v.
Cantor Fitzgerald & Co.,
275 Conn. 72, 80-81, 881 A.2d 139 (2005). This appeal is limited to the third ground for vacatur, namely, noncompliance with § 52-418.
“[Section] 52-418 (a) (4) provides that an arbitration award shall be vacated if the arbitrators have exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.”
(Internal quotation marks omitted.) Id., 81. “[A]n award that manifests an egregious or patently irrational application of the law is an award that should be set aside pursuant to § 52-418 (a) (4) because the arbitrator has exceeded [his] powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made. We emphasize, however, that the manifest disregard of the law ground for vacating an arbitration award is narrow and should be reserved for circumstances of an arbitrator’s extraordinary lack of fidelity to established legal principles.
“So delimited, the principle of vacating an award because of a manifest disregard of the law is an important safeguard of the integrity of alternate dispute resolution mechanisms. Judicial approval of arbitration decisions that so egregiously depart from established law that they border on the irrational would undermine society’s confidence in the legitimacy of the arbitration process. . . . Furthermore, although the discretion conferred on the arbitrator by the contracting parties
is exceedingly broad, modem contract principles of good faith and fair dealing recognize that even contractual discretion must be exercised for purposes reasonably within the contemplation of the contracting parties. . . .
“In
Garrity
[v.
McCaskey,
223 Conn. 1, 9, 612 A.2d 742 (1992)], we adopted the test enunciated by the United States Court of Appeals for the Second Circuit in interpreting the federal equivalent of § 52-418 (a) (4). . . . The test consists of the following three elements, all of which must be satisfied in order for a court to vacate an arbitration award on the ground that the arbitration panel manifestly disregarded the law: (1) the error was obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator; (2) the arbitration panel appreciated the existence of a clearly governing legal principle but decided to ignore it; and (3) the governing law alleged to have been ignored by the arbitration panel is well defined, explicit, and clearly applicable.” (Citations omitted; internal quotation marks omitted.)
Saturn Construction Co.
v.
Premier Roofing Co.,
238 Conn. 293, 304 — 305, 680 A.2d 1274 (1996).
Therefore, “an award that manifests an egregious or patently irrational application of the law is an award that should be set aside pursuant to § 52-418 (a) (4) because the arbitrator has ‘exceeded [his] powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.’ We emphasize, however, that the ‘manifest disregard for the law’ ground for vacating an arbitration award is narrow and should be reserved for circumstances of an arbitrator’s extraordinary lack of fidelity to established legal principles.”
Garrity
v.
McCaskey,
supra, 223 Conn. 10.
On appeal, the plaintiffs claim that the arbitrator manifestly disregarded the law by awarding the defendant contract damages based on unsigned change orders.
The plaintiffs argue that the language of § 20-429 (a) mandates that all changes to a home improvement contract must be signed by both the owner and the contractor in order to be valid and enforceable; because five change orders were not signed by the owner,
any arbitration award based on those change orders was, therefore, made in manifest disregard of the law.
The
defendant argues that the high standard of manifest disregard has not been met by the facts of this case. We agree with the defendant.
Although we ultimately reach the same conclusion as the Appellate Court, we elaborate on the correct application of the manifest disregard analysis, which is conjunctive and composed of three closely related elements. As set forth in
Garrity
v.
McCaskey,
supra, 223 Conn. 9, the first element, that “the error was obvious and capable of being readily and instantly perceived by the average person qualified to seive as an arbitrator,” and the third element, that “the governing law alleged to have been ignored by the arbitration panel is well defined, explicit, and clearly applicable,” are particularly closely related. We therefore turn to a brief review of the law that the plaintiffs claim is applicable, specifically § 20-429 (a).
It is undisputed that the Home Improvement Act, and specifically § 20-429 (a), is the applicable law; it is not, however, well-defined. Section 20-429 (a) explicitly requires, inter alia, that a home improvement contract be in writing and signed by the owner and contractor in order to be valid or enforceable against an owner. Even if we were to assume, however, that the plain language of § 20-429 (a) requires change orders to be signed by both the owner and contractor,
that subsection can not be read by itself when evaluating the arbitrator’s actions in the present case. “We construe a statute as a whole and read its subsections concurrently in order to reach a reasonable overall interpretation.”
(Internal quotation marks omitted.)
Grondin
v.
Curi,
262 Conn. 637, 652, 817 A.2d 61 (2003). In particular, we note that subsection (a) of § 20-429 must be construed in conjunction with subsection (f), which the legislature added to the Home Improvement Act in 1993.
The legislature added subsection (f) to § 20-429 when it enacted No. 93-215, § 1, of the 1993 Public Acts, in order to address what it considered to be the harsh result of
Barrett Builders
v.
Miller,
215 Conn. 316, 322-23, 576 A.2d 455 (1990), in which this court denied a contractor recovery for work performed because the court concluded that the Home Improvement Act was intended to abrogate common-law remedies, including quasi contract claims. See 36 S. Proc., Pt. 10,1993 Sess., p. 3451, remarks of Senator Thomas F. Upson (“As you know, there was a Supreme Court decision that said if it wasn’t in writing and value had been put in . . . the contractor could not get any money back at all. So this at least attempts to alleviate partially that situation.”); 36 H.R. Proc., Pt. 16, 1993 Sess., p. 5611, remarks of Representative Thomas A. Fox, chairman of the general law committee (discussing
Barrett Builders
and stating that it is “somewhat unfair to require that each T be dotted and ‘t’ be crossed”).
Subsection (f) of § 20-429 allows quantum meruit recovery in certain cases of partial noncompliance with subsection (a),
and could be construed as providing an
adequate basis for the arbitrator’s award in the present case, as the arbitrator may have chosen to exercise his discretion to allow a contractor to recover “payment for work performed based on the reasonable value of services which were requested by the owner, provided the [fact finder] determines that it would be inequitable to deny such recovery.” General Statutes § 20-429 (f). We need not fully explicate the relationship between subsections (a) and (f) in the limited context of this review for manifest disregard; that § 20-429 (a) has not been the subject of an appellate level decision since the enactment of subsection (f),
and that a reasonable interpretation of § 20-429 supports the arbitrator’s award, is enough to lead us to conclude that the applicable law is not well-defined and explicit. “The law allegedly ignored by the arbitration panel cannot be considered well defined, explicit, and clearly applicable ... [if] the parameters of the . . . [applicable statute] have never been addressed by this court or the Appellate Court.” (Citation omitted; internal quotation marks omitted.)
Harty
v.
Cantor Fitzgerald & Co.,
supra, 275 Conn. 102-103.
Moreover, with respect to the second element of the test for vacating an arbitration award as a manifest disregard of the law, it is far from clear on the record of this case that the arbitrator “appreciated the existence of a clearly governing legal principle but decided to ignore it . . . .”
Saturn Construction Co.
v.
Premier
Roofing Co.,
supra, 238 Conn. 305. The arbitration award stated only that “[t]he pursuant change orders
did not follow proper procedures
resulting in delays and disputes.” (Emphasis added.) The plaintiffs contend that this statement, followed by the arbitrator’s award to the defendant of payment for work contained only in the unsigned change orders, demonstrates that the arbitrator deliberately ignored the law. This language is, at best, ambiguous, and does not, without more, indicate that the arbitrator considered, but elected to ignore, governing legal principles. Put differently, we cannot tell from the award which “procedure” the arbitrator referred to, be it state statutes and regulations, or, for example, custom followed by the construction industry or these particular parties. Accordingly, the plaintiffs’ claim of manifest disregard fails on the second element of the test as well. The Appellate Court, therefore, properly concluded that the trial court improperly vacated the arbitration award.
The judgment of the Appellate Court is affirmed.
In this opinion the other justices concurred.