Economos v. Liljedahl Bros., Inc.

901 A.2d 1198, 279 Conn. 300, 2006 Conn. LEXIS 310
CourtSupreme Court of Connecticut
DecidedAugust 8, 2006
DocketSC 17394
StatusPublished
Cited by26 cases

This text of 901 A.2d 1198 (Economos v. Liljedahl Bros., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Economos v. Liljedahl Bros., Inc., 901 A.2d 1198, 279 Conn. 300, 2006 Conn. LEXIS 310 (Colo. 2006).

Opinion

Opinion

NORCOTT, J.

The plaintiffs, Michael G. Economos and Bessie Economos, appeal, following our grant of certification, 1 from the judgment of the Appellate Court reversing the judgment of the trial court granting their application to vacate an arbitration award and denying the motion of the defendant, Liljedahl Brothers, Inc., to confirm that award in its favor. Economos v. Liljedahl Bros., Inc., 86 Conn. App. 578, 587, 862 A.2d 312 (2004). The plaintiffs claim that the Appellate Court improperly concluded that the arbitrator did not manifestly disregard the law when he awarded the defendant contractor damages for the breach of a home improvement con *302 tract, despite changes to the contract that failed to comply with the Home Improvement Act, General Statutes § 20-418 et seq., specifically General Statutes § 20-429 (a). 2 We disagree and, accordingly, we affirm the judgment of the Appellate Court.

The record and the Appellate Court opinion reveal the following relevant facts and procedural history. “On April 3, 2000, the parties entered into a home improvement contract in which the defendant agreed to renovate a bathroom and laundry room in the home of the plaintiffs. On September 15, 2000, the parties entered into a second home improvement contract in which the defendant agreed to remodel a kitchen and add a den to the plaintiffs’ house. Under the terms of each contract, any controversy arising out of the contracts was to be settled by arbitration.” 3 Economos v. Liljedahl Bros., Inc., supra, 86 Conn. App. 579.

During the course of the remodeling projects, the defendant submitted change orders 4 for additional work *303 completed on the project. The total added cost to the bathroom and laundry room project was $4460.49; the total added cost to the kitchen and den project was $16,348.12. 5 ***5

“Subsequently, a dispute arose between the parties, and the defendant filed a demand for arbitration and a mechanic’s lien on the plaintiffs’ house. The plaintiffs responded by filing an answer, special defenses and an amended counterclaim. On December 17, 2001, the plaintiffs filed a motion for summary judgment, which was denied. Following the arbitration hearing, which encompassed nine days of testimony, the arbitrator awarded the defendant $81,890.24 and the plaintiffs $30,423.69 for a net award of $51,466.55 for the defendant. The award concluded: ‘This award is in full settlement of all claims and counterclaims submitted to this *304 Arbitration. All claims not expressly granted herein are hereby, denied.’ Subsequently, the arbitrator died, and the parties were referred to the court system by the American Arbitration Association for the resolution of any outstanding issues.

“On October 23, 2002, the plaintiffs, pursuant to General Statutes §§ 52-418 and 52-419, filed an application to vacate or to modify the arbitration award, claiming that the arbitrator ‘acted with evident partiality or corruption,’ refused to hear pertinent evidence and exceeded his powers. On November 7, 2002, the defendant, pursuant to General Statutes § 52-417, filed a motion to confirm the arbitration award and for an award of postarbitration interest. Following a hearing on the parties’ motions, the court denied the defendant’s motion to confirm the arbitration award and vacated the award because it failed to address three of the claims raised by the plaintiffs.” Id., 579-80.

The defendant appealed, claiming that the trial court “improperly (1) denied its motion to confirm the arbitrator’s award and (2) vacated the arbitrator’s award.” Id., 580. The plaintiffs countered that the trial court “properly vacated the arbitrator’s award and denied the defendant’s motion to confirm the award because the award (1) did not conform to the submission, (2) violated public policy and (3) was an ‘egregious application of the law . . . .’ ” Id. The Appellate Court did not reach the plaintiffs’ public policy claim; id., 587 n.2; but reversed the trial court’s judgment based on its conclusions that the award conformed with the submission 6 and was not an egregious application of the law. *305 Id., 583-84. This certified appeal followed as to the plaintiffs’ manifest disregard claim. See footnote 1 of this opinion.

Our analysis is guided by well established principles regarding a party’s application to vacate a consensual arbitration award resulting from an unrestricted submission. “Judicial review of arbitral decisions is narrowly confined. . . . When the parties agree to arbitration and establish the authority of the arbitrator through the terms of their submission, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . . Because we favor arbitration as a means of settling private disputes, we undertake judicial review of arbitration awards in a manner designed to minimize interference with an efficient and economical system of alternative dispute resolution. . . .

“Where the submission does not otherwise state, the arbitrators are empowered to decide factual and legal questions and an award cannot be vacated on the grounds that . . . the interpretation of the agreement by the arbitrators was erroneous. Courts will not review the evidence nor, where the submission is unrestricted, will they review the arbitrators’ decision of the legal questions involved. ... In other words, [u]nder an unrestricted submission, the arbitrators’ decision is considered final and binding; thus the courts will not review the evidence considered by the arbitrators nor will they review the award for errors of law or fact. . . .

“Even in the case of an unrestricted submission, we have . . . recognized three grounds for vacating an award: (1) the award mies on the constitutionality of a statute ... (2) the award violates clear public policy *306 . . . [and] (3) the award contravenes one or more of the statutory proscriptions of § 52-418.” (Internal quotation marks omitted.) Harty v. Cantor Fitzgerald & Co., 275 Conn. 72, 80-81, 881 A.2d 139 (2005). This appeal is limited to the third ground for vacatur, namely, noncompliance with § 52-418.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torrington v. Council 4, AFSCME, AFL-CIO, Local 442
232 Conn. App. 45 (Connecticut Appellate Court, 2025)
Karen v. Loftus
228 Conn. App. 163 (Connecticut Appellate Court, 2024)
Ahmed v. Oak Management Corp.
Supreme Court of Connecticut, 2023
Blondeau v. Baltierra
337 Conn. 127 (Supreme Court of Connecticut, 2020)
Benistar Employer Services Trust Co. v. Benincasa
207 A.3d 67 (Connecticut Appellate Court, 2019)
Toland v. Toland
182 A.3d 651 (Connecticut Appellate Court, 2018)
Ippolito v. Olympic Construction, LLC
Connecticut Appellate Court, 2016
Edwards v. North American Power & Gas, LLC
120 F. Supp. 3d 132 (D. Connecticut, 2015)
Richards v. Direct Energy Services, LLC
120 F. Supp. 3d 148 (D. Connecticut, 2015)
Nxegen, LLC v. Carbone
Connecticut Appellate Court, 2015
Town of Marlborough v. AFSCME, Council 4, Local 818-052
23 A.3d 798 (Connecticut Appellate Court, 2011)
FCM Group, Inc. v. Miller
17 A.3d 40 (Supreme Court of Connecticut, 2011)
Walpole Woodworkers, Inc. v. Manning
11 A.3d 165 (Connecticut Appellate Court, 2011)
Marulli v. Wood Frame Construction Co., LLC
5 A.3d 957 (Connecticut Appellate Court, 2010)
Dupont v. Tobin, Carberry, O'malley, Riley, Selinger, PC
322 F. App'x 66 (Second Circuit, 2009)
Hees v. Burke Construction Inc.
961 A.2d 373 (Supreme Court of Connecticut, 2009)
State v. Connecticut State Employees Ass'n, SEIU Local 2001
947 A.2d 928 (Supreme Court of Connecticut, 2008)
Newtown Pool Construction, LLC v. Errico
930 A.2d 50 (Connecticut Appellate Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
901 A.2d 1198, 279 Conn. 300, 2006 Conn. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/economos-v-liljedahl-bros-inc-conn-2006.