Southern Construction, LLC v. Christopher Caleb Horton

2020 Ark. App. 361, 609 S.W.3d 16
CourtCourt of Appeals of Arkansas
DecidedSeptember 2, 2020
StatusPublished
Cited by6 cases

This text of 2020 Ark. App. 361 (Southern Construction, LLC v. Christopher Caleb Horton) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Construction, LLC v. Christopher Caleb Horton, 2020 Ark. App. 361, 609 S.W.3d 16 (Ark. Ct. App. 2020).

Opinion

Cite as 2020 Ark. App. 361 Reason: I attest to the accuracy and integrity of this document ARKANSAS COURT OF APPEALS Date: 2021-07-08 09:13:20 DIVISION II Foxit PhantomPDF Version: No. CV-19-783 9.7.5

Opinion Delivered: September 2, 2020 SOUTHERN CONSTRUCTION, LLC APPELLANT APPEAL FROM THE MARION V. COUNTY CIRCUIT COURT [NO. 45CV-18-106] CHRISTOPHER CALEB HORTON APPELLEE HONORABLE ANDREW S. BAILEY, JUDGE

AFFIRMED IN PART; REVERSED AND REMANDED IN PART

RITA W. GRUBER, Chief Judge

Appellant Southern Construction, LLC, appeals two orders of the Marion County

Circuit Court awarding judgment in favor of appellee Christopher Horton following a

dispute regarding construction work. On appeal, Southern argues that the circuit court erred

in its interpretation of the construction contract and application of Arkansas Code

Annotated section 17-25-103(d) (Supp. 2019) to preclude an offset against a judgment for

the balance due under the agreement. We affirm in part and reverse and remand in part.

On June 26, 2017, the parties entered into a construction contract wherein Southern,

which is owned by Jared Forbus, agreed to perform construction services to remodel

Horton’s home. Horton agreed to pay Southern $63,490 for the services. The contract

required the work to be completed in a “workmanlike manner according to standard

practices” and any “alteration or deviation” from the specified work involving extra costs to be executed “only upon written orders.” On November 21, 2017, the parties entered

into a supplemental agreement, which described the remaining work and set a completion

date of December 15, 2017.

In July 2018, Horton filed a complaint against Southern for negligent construction

and breach of contract, alleging that Southern failed to complete the work as required and

that the work performed was not completed in a “professional or competent” manner.

Horton alleged that Southern was negligent in the supervision and remodeling of the home,

which resulted in serious defects to the home. Horton claimed that as a result of the

negligent construction and breach of contract, he suffered damages that would require him

to make significant repairs to correct improperly completed work and that the repairs would

require him to reside elsewhere and to incur additional interest on his construction loan.

Southern filed an answer denying the claims as well as a counterclaim alleging that

Horton defaulted under the agreement by failing to pay the final invoice of $16,998. Horton

moved for summary judgment, seeking dismissal of the counterclaim and arguing that

Southern was prohibited from pursuing a claim against him under Arkansas Code Annotated

section 17-25-103(d) because it was licensed to contract for only residential jobs of less than

$50,000. At the outset of the May 2019 bench trial, the circuit court found as a matter of

law that Southern was precluded from pursuing the counterclaim and dismissed it with

prejudice.

At trial, Horton testified that he entered into the June 2017 contract with Southern

to remodel a house for a total cost of $63,490. He explained that there was a November

2017 agreement, which listed the remaining work to be done by December 15, 2017. The

2 job was not completed by December 17, and he terminated the relationship with Southern

“a month or two later.” Horton said that Southern presented a bill in early 2018 for final

payment of $12,698 due under the contract plus “extras” that he never signed off on.

On cross-examination, Horton testified that he thought the provision of the June

2017 contract stating “remove rotten siding and damaged wood work” meant any rotten

woodwork in the house and thus included any rotten floor joists. When asked whether

“damaged woodwork” referred to woodwork behind the siding, Horton responded,

“That’s, I mean, sounds to me like it is covering the whole house. That’s why I wanted

more description.” He acknowledged having signed the agreement without further

description.

On redirect, when asked about his expectation regarding the floor joists,1 Horton

testified that he thought any rotten wood would be replaced and the floors leveled. He

explained that the cabinets did not sit properly because the floors were not leveled. Horton

added that he communicated by text with Forbus regarding the floor joists.2 Two undated

texts included the following response when Horton asked Forbus for progress updates: (1)

“Get rotten floor joist repaired and new subfloor and outside 4ft up around house checked

and repaid [sic] made. So when windows get here and doors. We can put them right in and

1 Southern objected to this question, stating that it was not allowed under the parol- evidence rule. The court allowed Horton to answer, stating that Horton’s “expectation doesn’t mean that I’m going to ascribe that as a part of the contract.” 2 Southern objected to the introduction of the text messages on the basis of the parol- evidence rule, arguing that the contract term “remove rotten siding and damaged woodwork” was not ambiguous. Horton argued that it was ambiguous whether damaged woodwork included rotten floor joists. In allowing the introduction of the texts, the circuit court noted Southern’s continuing parol-evidence objection.

3 do siding.”; and (2) “Got all but like to [sic] floor joist[s] repair[ed] that were all rotten got

the framing around the door repaired[.]”

The next witness to testify was Joe Flowers of the Crawl Space People, which does

home leveling, support beams, and termite- and water-damage repair. Flowers stated that

the foundation “looked to be okay” but there was a lot of water damage to the floor joists

and part of the beam system. He gave Horton a $5,765 bid to make the necessary repairs to

shore up the home, which included attaching up to fifty new floor joists to the beams,

adding six block piers between piers on the beam system, and possibly adding floor joists

under the existing walls. Flowers stated that some of the existing joists were rotten. When

asked whether a remodel could have been done on that foundation, Flowers said it could

be done but it would not be “straight.” He added that the home may never be “straight.”

Flowers agreed on cross-examination that after the repairs, the floors will likely still have

unevenness.

Home inspector Christopher Cochran inspected the property and prepared a report.

He spoke of numerous problems, which were outlined in the summary report introduced

into evidence, including problems with the siding, the roof, the plumbing, the HVAC and

duct work, and the foundation. Regarding the foundation, Cochran noticed rotted joists,

which he attributed to moisture in the crawl space that caused mold growth on the joists

and the subfloor and rotted the wood. He said that some repairs had been done, such as

bridge work between the joists, but the vast majority of the bad areas did not look like they

had been addressed. He added that the best time to repair the beams and joists is when the

floors are up because the crawl space is tight in some areas of the house. Cochran testified

4 that if the floor problems are not fixed, “everything else above it is going to be

problematic[.]” On cross-examination, Cochran said that he had no knowledge of the

remodeling contract.

Contractor John Mitchell submitted a $25,550 proposal to make the inspector’s

recommended repairs, with the exception of the floor joists.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ark. App. 361, 609 S.W.3d 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-construction-llc-v-christopher-caleb-horton-arkctapp-2020.