Meyer v. CDI CONTRACTORS, LLC

284 S.W.3d 530, 102 Ark. App. 290, 2008 Ark. App. LEXIS 416
CourtCourt of Appeals of Arkansas
DecidedMay 21, 2008
DocketCA 07-1307
StatusPublished
Cited by3 cases

This text of 284 S.W.3d 530 (Meyer v. CDI CONTRACTORS, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meyer v. CDI CONTRACTORS, LLC, 284 S.W.3d 530, 102 Ark. App. 290, 2008 Ark. App. LEXIS 416 (Ark. Ct. App. 2008).

Opinion

Robert J. Gladwin, Judge.

This is the third time that this case, which involves a construction contract, has been before us; on both previous appeals, we dismissed for lack of an appealable order. Appellant Robert Meyer, d/b/a Meyer Excavators Contractors, challenges the circuit court’s entry of summary judgment for appellee CDI Contractors, LLC, and the award of attorney’s fees to CDI. We affirm the circuit court’s decision in all respects.

Meyer filed a complaint against CDI in the Pulaski County Circuit Court, alleging that, in September 2001, it entered into a subcontract with CDI to perform earthwork as part of a construction project for the Church at Rock Creek, in which CDI had falsely represented to Meyer that it had a contract; that, in December 2001, CDI attempted to cancel the contract; and that Meyer’s out-of-pocket costs associated with preparing to perform were $496,566 and his lost profits were $114,490. Claiming fraudulent inducement and breach of contract, Meyer requested damages of $636,055 and punitive damages in the amount of $1,300,000. Asking that the contract be rescinded, CDI responded that an unavoidable event had rendered the contract impossible to perform. Meyer filed an amended complaint alleging that his lost profits were $233,094 and requesting punitive damages of $700,000.

In June 2005, CDI moved for summary judgment, asserting that Meyer was barred from bringing his claims because he had entered into the underlying contract in violation of the Arkansas Contractors Licensing Law. CDI alleged that the church had asked it to obtain a bid from Meyer to perform a portion of the site work; that, when it contacted him about the bid, it learned that he was not a licensed contractor and was, therefore, disqualified from bidding on or entering into a contract for work in excess of $20,000; that it postponed the bidding process in order to allow him time to apply for his license, which he received in July 2001; that, as part of his application for a license, Meyer signed an affidavit, swearing that he was not currently performing any work costing $20,000 or more and did not have an outstanding bid for such work; and that this statement was not accurate, as he was working on a large project, the “Berry Farm Project,” costing over $20,000. Among the supporting exhibits, CDI attached copies of Meyer’s July 2001 license application; excerpts of his 2003 and 2005 depositions; 1 copies of his 2001 invoices for the “Berry Farm Project”; and an itemization of payments he received from June through August 2001. Citing Meyer’s deposition testimony, CDI asserted that, in July 2001, when Meyer applied for his license, he had billed over $84,700; had performed over $70,000 worth of work; and had collected over $90,800 for previous work on the Berry Farm Project. CDI argued that, because Meyer entered into this contract while holding a license that he had obtained by submitting false information, all of his claims were unenforceable under Arkansas Code Annotated section 17-25-103(d) (Repl. 2001), which stated: “No action may be brought either at law or in equity to enforce any provision of any contract entered into in violation of this chapter. No action may be brought either at law or in equity for quantum meruit by any contractor in violation of this chapter.”

Appellant responded: “[Meyer] has controverted the facts alleged by [CDI] as detailed in [Meyer’s] Brief in Support of this Response. [Meyer] incorporates by reference his Brief in Support of his Response.” Meyer’s brief, however, is not contained within the addendum, nor is it in the record. From CDI’s reply brief, it appears that Meyer did submit this response in a brief:

In Meyer’s Brief in Response to CDI’s Motion for Summary Judgment, Meyer fails to refute or counter any of the evidence presented by CDI in support ofits motion. Specifically, Meyer does not deny the fact that he was working on a project in excess of $20,000 at the time he applied for his contractor’s license, and he does not deny that he presented false information to the licensing board. As a result, it should be clear there are no genuine issues of fact remaining. Meyer’s claims against CDI are barred as a matter of law under Ark. Code Ann. § 17-25-103 (2005)....
Meyer makes three arguments in his Response Brief: (1) Meyer did not violate the Licensing Act because he did not know he was presenting false information to the board; (2) Meyer must not have violated the Licensing Act because his license was not revoked; (3) the statute of limitations applying to proceedings brought by the Licensing Board should apply to CDI’s affirmative defense in this lawsuit.

CDI argued that this case could not be distinguished from Williams v. Joyner-Cranford-Burke Construction Co., 285 Ark. 134, 685 S.W.2d 503 (1985), in which the supreme court held that the $20,000 amount provided in the licensing statute applies to the total amount of a project, not just its subparts.

On July 26, 2005, the circuit court entered an order granting CDI’s motion for summary judgment, stating:

Here, [appellant] entered into a contract with CDI Contractors, LLC in violation of the Arkansas Contractors Licensing Act. Specifically, he presented false evidence to the Licensing Board by affirming in an affidavit that, at the time he applied for his license, he was not working on any project the cost of which exceeded $20,000. This was false. The undisputed evidence has shown that [appellant] was in the midst of a multi-million dollar project, called “The Berry Farm Project,” at the time he applied for his license, earning hundreds of thousands of dollars in the month in which he applied for his license alone. In sum, [appellant] presented false evidence to the Licensing Board in order to obtain his contractors license, used such license to enter into a contract with CDI, then sued to enforce the very contract he entered into in violation of the Licensing Statute. Strictly construing Ark. Code Ann. § 17-25-101 et seq., the Court finds that [appellant’s] claims against CDI are statutorily barred and must be dismissed.
Applying Williams to the facts at hand, the Court finds that the cost of the Berry Farm Project, on which [appellant] was working when he applied for his contractors license, far exceeded $20,000. Therefore, he presented false evidence to the Licensing Board when he affirmed that he was not working on any project in excess of $20,000. Because [appellant] entered into the contract with CDI in violation of the Arkansas Contractors Licensing Act, his claims are statutorily barred and are hereby dismissed.

CDI moved for an award of attorney’s fees under Arkansas Code Annotated section 16-22-308 (Repl. 1999), which permits the circuit court to award fees to the prevailing party in any civil action to recover on a contract, and attached the affidavit of its counsel, James C. Baker, Jr., and copies of his time records. Meyer responded that this case did not warrant an award of attorney’s fees because it sounded primarily in tort and, in any event, the requested fee was not properly documented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Construction, LLC v. Christopher Caleb Horton
2020 Ark. App. 361 (Court of Appeals of Arkansas, 2020)
J & J Excavating v. Doyne Construction Co.
391 S.W.3d 367 (Court of Appeals of Arkansas, 2012)
NCCF Support, Inc. v. Harris McHaney Real Estate Co.
376 S.W.3d 459 (Court of Appeals of Arkansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
284 S.W.3d 530, 102 Ark. App. 290, 2008 Ark. App. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meyer-v-cdi-contractors-llc-arkctapp-2008.