MacMillan v. Higgins

822 A.2d 246, 76 Conn. App. 261, 2003 Conn. App. LEXIS 163
CourtConnecticut Appellate Court
DecidedApril 15, 2003
DocketAC 22390
StatusPublished
Cited by11 cases

This text of 822 A.2d 246 (MacMillan v. Higgins) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacMillan v. Higgins, 822 A.2d 246, 76 Conn. App. 261, 2003 Conn. App. LEXIS 163 (Colo. Ct. App. 2003).

Opinion

Opinion

LAVERY, C. J.

The plaintiff Kevin F. MacMillan1 appeals, and the defendants Harrison Scott Higgins and [263]*263Linda Park Higgins2 cross appeal, from the judgment of the trial court, adopting the findings and recommendations of the attorney trial referee (referee) in this action to foreclose a mechanic’s lien. The plaintiff claims that the court improperly accepted the findings of the referee (1) that the defendants did not act in bad faith during their dealings with the plaintiff and (2) that the contract between the parties was not in practical compliance with General Statutes § 20-418 et seq., the Home Improvement Act (act). The plaintiff also argues, contrary to the recommendation of the referee, that our legislature did not intend to provide to the defendants, whose agent drafted the contract, the protection of the act. In their cross appeal, the defendants challenge the findings and recommendations of the referee that they (1) did not overpay the plaintiff, (2) were not entitled to an award for costs to complete the contract and (3) were not entitled to an award of attorney’s fees and punitive damages under General Statutes § 42-110a et seq., the Connecticut Unfair Trade Practices Act (CUTPA). We affirm the judgment of the trial court.

The record discloses the following facts and procedural history. In December, 1991, the defendants solicited the plaintiff, a New Hampshire general contractor, for a construction job. The defendants hired the plaintiff to perform certain improvements to their home in Greenwich. On February 21, 1992, the parties entered into a written contract.3 The plaintiff had started work on the defendants’ house on January 20,1992, and hired [264]*264various subcontractors.4 Difficulties at the construction site occurred, and the plaintiff, under protest, prepared various change orders5 and performed additional work, for which he received additional compensation. The relationship between the parties continued to deteriorate and on August 7, 1992, the plaintiffs employment was terminated by the defendants.

The plaintiff filed an action against the defendants, alleging that he was owed $45,214.12 for work completed pursuant to the contract. The plaintiff also sought to foreclose on a mechanic’s lien that had been placed on the defendants’ property.6 The defendants filed an answer, denying the plaintiffs claims, alleged several special defenses and filed a counterclaim alleging that the plaintiff was paid for work that he did not complete and that he violated CUTPA.

The matter was referred to the referee pursuant to General Statutes (Rev. to 1991) § 52-434 (a)7 and Practice Book § 19-2.8 The referee heard evidence on June [265]*26510 and 11, 1998, at which time the parties stipulated that the plaintiffs work on the defendants’ home was controlled by the act. Additionally, they agreed9 that the contract did not conform to the act’s mandatory requirements, as set forth in General Statutes § 20-249 (a).10 Specifically, the contract did not contain a notice of the defendants’ three day cancellation right, as required by the act.* 11 Finally, the parties agreed that the plaintiff could not prevail on his claims absent a [266]*266finding that the defendants acted in bad faith.12

After hearing evidence, the referee issued a report on November 24, 1998, finding that the defendants did not act in bad faith.13 The court filed its memorandum of decision on September 7, 1999. Prior to accepting the report, it remanded the matter to the referee with instructions to consider three issues. First, the referee was instructed to consider whether Wright Bros. Builders, Inc. v. Dowling, 247 Conn. 218, 720 A.2d 235 (1998), in which our Supreme Court held that practical and not perfect compliance was all that was required under the act, applied to the facts of the present case. Second, the court requested that the referee determine the significance, if any, of the fact that the contract was not prepared by the plaintiff, but by the defendants and their agents. Third, the referee was asked to determine the significance, if any, of the fact that the defendants and their attorney were familiar and experienced with the provisions of the act, as demonstrated by their involvement in Meadows v. Higgins, 249 Conn. 155, 733 A.2d 172 (1999). In addition to addressing those issues, the referee also was also instructed to complete the trial regarding the defendants’ counterclaim.

On April 28, 2000, the referee issued a report addressing the three issues raised by the court. Initially, he concluded that although Wright Bros. Builders, Inc. v. Dowling, supra, 247 Conn. 218, was applicable to the present case, because of the parties’ stipulation that [267]*267the contract did not conform to the requirements of the act, the only issue was whether the defendants had acted in bad faith. The referee then stated that although he had considered the fact that the defendants and their agents had prepared the contract, and that the preparation by the defendants’ attorney “fell far short in terms of quality,” he did not conclude that the preparation “was done intentionally and in bad faith.” In addressing the third question, the referee considered the fact that the defendants and their attorney were “experienced, knowledgeable, and competent in dealing with matters involving [the act],” as demonstrated by their participation in the Meadows case. ” The referee concluded, however, that he was unable to make a factual determination that the defendants’ attorney intentionally had prepared the contract to deceive the plaintiff or had acted fraudulently or in bad faith.14

The referee then heard evidence on the defendants’ counterclaim. The defendants alleged that they were entitled to a return of the money that they had paid to the plaintiff for work that was not completed, as well as compensation for additional funds in the amount of $164,350 that they had expended to complete the work on the house. Additionally, the defendants alleged that the plaintiff had violated CUTPA and that they were, therefore, entitled to an award of attorney’s fees and punitive damages. On February 1, 2000, the referee issued a supplemental report detailing his findings of fact and recommendations with respect to the defendants’ counterclaim. He found that the defendants did not overpay the plaintiff and that they were not entitled to compensation for the $164,350 they spent to complete the construction on their house. Additionally, the referee concluded that the defendants did not suffer an ascertainable loss of money as specified by CUTPA, [268]*268and, therefore, declined to award attorney’s fees or punitive damages.

The court then issued a supplemental memorandum of decision on August 28,2001.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burns v. Adler
Supreme Court of Connecticut, 2017
Gaynor v. Hi-Tech Homes
89 A.3d 373 (Connecticut Appellate Court, 2014)
Marinos v. Poirot
33 A.3d 282 (Connecticut Appellate Court, 2011)
Hees v. Burke Construction Inc.
961 A.2d 373 (Supreme Court of Connecticut, 2009)
Scrivani v. Vallombroso
916 A.2d 827 (Connecticut Appellate Court, 2007)
Robichaud v. Hewlett Packard Co.
848 A.2d 495 (Connecticut Appellate Court, 2004)
Swerdloff v. Rubenstein
841 A.2d 222 (Connecticut Appellate Court, 2004)
Doe v. Rapoport
833 A.2d 926 (Connecticut Appellate Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
822 A.2d 246, 76 Conn. App. 261, 2003 Conn. App. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macmillan-v-higgins-connappct-2003.