Winakor v. Savalle

343 Conn. 773
CourtSupreme Court of Connecticut
DecidedJune 28, 2022
DocketSC20516
StatusPublished
Cited by4 cases

This text of 343 Conn. 773 (Winakor v. Savalle) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winakor v. Savalle, 343 Conn. 773 (Colo. 2022).

Opinion

LEE WINAKOR v. VINCENT SAVALLE (SC 20516) Robinson, C. J., and McDonald, D’Auria, Kahn, Ecker and Keller, Js.

Syllabus

Pursuant to the Home Improvement Act (§ 20-419 (4)), home improvement includes, inter alia, ‘‘the repair, replacement, remodeling, alteration . . . [or] improvement . . . to any land or building or that portion thereof which is used or designed to be used as a private residence’’ but does not include ‘‘(A) [t]he construction of a new home . . . .’’ The plaintiff sought to recover damages from the defendant contractor for, inter alia, breach of contract and violations of the Home Improvement Act (§ 20-418 et seq.). The plaintiff had executed a contract with G Co. for the construction of a new house on land owned by the plaintiff. That contract permitted the plaintiff to contract for necessary site work with a separate contractor. Thereafter, the plaintiff and the defendant entered into a separate contract providing that the defendant would perform certain site work in connection with the construction of the new house, including the digging of a hole for the foundation, the installa- tion of a septic tank and footing drains, and the construction of two retaining walls and two driveways. G Co. completed its construction of the house, and the plaintiff received a certificate of occupancy. At that Page 4 CONNECTICUT LAW JOURNAL June 28, 2022

774 JUNE, 2022 343 Conn. 773 Winakor v. Savalle time, however, the defendant had not completed the site work he was obligated to perform under the parties’ contract. The planning and zoning commission of the town in which the plaintiff’s property was located informed the plaintiff that the house would be approved for zoning compliance if certain site work was completed. The parties then entered into a second contract requiring the defendant to complete the work that was agreed on in the first contract by a certain date and at an additional cost. The plaintiff ultimately became dissatisfied with the quality and timing of the defendant’s work, terminated their relationship, and hired another contractor to complete the site work and to remedy any flaws in the defendant’s previous work. The trial court ruled in part for the plaintiff, concluding that the defendant had breached the contracts with the plaintiff by failing to complete the site work on schedule and by causing the plaintiff to incur additional expenses to repair and finish the work that the defendant was contractually required to perform. The court also concluded that the defendant had violated the Home Improvement Act by failing to comply with certain statutory requirements regarding the form of the contracts and that the defendant’s violation of the Home Improvement Act constituted a per se violation of the Connecticut Unfair Trade Practices Act (CUTPA) (§ 42-110a et seq.). The defendant appealed to the Appellate Court, which affirmed the trial court’s judgment with respect to the plaintiff’s breach of contract claim but reversed with respect to the plaintiff’s claims under the Home Improvement Act and CUTPA. The Appellate Court concluded that the Home Improvement Act did not apply to the defendant’s work, as that work fell within the new home exception set forth in § 20-419 (4) (A), and, consequently, the plaintiff failed to state a claim under both the Home Improvement Act and CUTPA. The plaintiff, on the granting of certification, appealed to this court. Held that the Appellate Court cor- rectly concluded that the Home Improvement Act did not apply to the defendant’s work because that work fell within the new home exception set forth in § 20-419 (4) (A), and, accordingly, this court affirmed the Appellate Court’s judgment: although the contracts between the plaintiff and the defendant were separate from the contract between the plaintiff and G Co. to construct the new house, the work the defendant agreed to perform was within the scope of the work contemplated by the contract between the plaintiff and G Co., as many of the projects the defendant was obligated to complete were expressly included in the contract between the plaintiff and G Co., and, thus, the work the defen- dant agreed to perform would have been completed by G Co. if the plaintiff had not elected to contract out the site work to the defendant; moreover, G Co.’s construction work could not have proceeded without the defendant’s work, as G Co.’s work depended physically and tempo- rally on the defendant’s foundation work, the defendant was required to communicate with G Co. throughout the defendant’s performance of the site work, and the first contract between the plaintiff and the defen- June 28, 2022 CONNECTICUT LAW JOURNAL Page 5

343 Conn. 773 JUNE, 2022 775 Winakor v. Savalle dant specified that the defendant was to complete his work within a certain time for the purpose of facilitating G Co.’s construction of the house, and, thus, both the close timing and the extensive communication required between the defendant and G Co. led to the conclusion that the defendant’s work was sufficiently interrelated with the construction of the house; furthermore, much of the work the defendant performed contributed directly to the habitability of the house, and that work was necessary in order for the house to comply with the town zoning requirements. Argued December 20, 2021—officially released June 28, 2022

Procedural History

Action to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of New London and tried to the court, Frechette, J.; judgment for the plaintiff, from which the defendant appealed to the Appellate Court; thereafter, the court, Frechette, J., granted the plaintiff’s motion for attorney’s fees, and the defendant filed an amended appeal; subsequently, the Appellate Court, Prescott, Moll and Harper, Js., reversed in part the trial court’s judgment, and the plaintiff, on the grant- ing of certification, appealed to this court. Affirmed. Paul M. Geraghty, with whom was Jonathan E. Friedler, for the appellant (plaintiff). Patrick J. Markey, with whom, were James H. Lee and, on the brief, Mary H. Patryn, for the appellee (defendant). Opinion

KAHN, J. This appeal requires us to consider whether certain services provided by a contractor fall under the purview of the Home Improvement Act, General Statutes § 20-418 et seq. In this appeal, the plaintiff, Lee Winakor, claims that the Appellate Court incorrectly concluded that the Home Improvement Act did not apply to work performed on his property by the defen- dant, Vincent Savalle. The defendant claims that the Page 6 CONNECTICUT LAW JOURNAL June 28, 2022

776 JUNE, 2022 343 Conn. 773 Winakor v. Savalle

work falls under the new home exception of the Home Improvement Act and, therefore, that the Appellate Court’s conclusion was correct. We agree with the defendant and, accordingly, affirm the judgment of the Appellate Court. The following undisputed facts and procedural his- tory are relevant to the present appeal. In 2005, the plaintiff purchased real property located at 217 Legend Wood Road in North Stonington. In 2012, the plaintiff executed a contract with Golden Hammer Builders, LLC (Golden Hammer), through its principal, Brian Mawd- sley, in order to construct a single-family home on the property. The contract contemplated the construction of the home and all related site work for a price of $425,300. It also contained a provision permitting the plaintiff to subtract $55,000 from the total cost of the construction by independently contracting for the nec- essary site work with a separate contractor. After meeting with the plaintiff, the defendant submit- ted a bid to complete that site work for under $50,000. The plaintiff accepted the defendant’s bid and drafted a contract to memorialize their agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drummer v. State
233 Conn. App. 383 (Connecticut Appellate Court, 2025)
Cerame v. Lamont
Supreme Court of Connecticut, 2023
State v. White
215 Conn. App. 273 (Connecticut Appellate Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
343 Conn. 773, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winakor-v-savalle-conn-2022.