Rowland Ironworks v. 1200 Post R. E Assoc., No. Cv 97 0156531 (Dec. 4, 1998)

1998 Conn. Super. Ct. 14266
CourtConnecticut Superior Court
DecidedDecember 4, 1998
DocketNo. CV 97 0156531
StatusUnpublished

This text of 1998 Conn. Super. Ct. 14266 (Rowland Ironworks v. 1200 Post R. E Assoc., No. Cv 97 0156531 (Dec. 4, 1998)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowland Ironworks v. 1200 Post R. E Assoc., No. Cv 97 0156531 (Dec. 4, 1998), 1998 Conn. Super. Ct. 14266 (Colo. Ct. App. 1998).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
This action seeks to foreclose a mechanic's lien which was recorded in connection with a dispute between the plaintiff, Rowland Ironworks, Inc., of Danbury, and two defendants, 1200 Post Road East Associates Limited Partnership (1200 Post Road), and National Recording Studios, Inc. d/b/a National Video Center (National Video), both of Westport.

The plaintiff filed a complaint alleging that the defendant 1200 Post Road owns a commercial building located at 1200 Post Road East in Westport, and that it had a written contract dated October 9, 1995, and amended December 27, 1995, with National Video, which occupied a portion of the subject premises, and is described in the lien as "contractors or agents" for 1200 Post Road, to render services and furnish materials for a construction project at the subject premises. The plaintiff further alleges that it rendered services and furnished materials to the defendants between November, 1995 and April, 1996; that the contract price was approximately $29,000; that the defendant National Video had paid the plaintiff approximately $12,000, leaving a balance due of $16,776; and that the plaintiff had filed a mechanic's lien in that amount.

In their answer, 1200 Post Road and National Video, hereafter referred to as the defendants, denied the material allegations of the complaint and asserted a counterclaim with two counts. In the first count, the defendants allege that National Video was in possession of a certain portion of the building at 1200 Post Road East, Westport. which was the location where the plaintiff was to perform its construction services. The defendants contend that the plaintiff breached its contract by failing to perform in a workmanlike manner in accordance with the terms of the contract. The defendants also allege that the plaintiff failed to finish the project in a timely manner. In the second count of the counterclaim, the defendants allege that the plaintiff performed its work in a negligent manner and that the defendants incurred CT Page 14268 "substantial costs above the contract price."

The case was referred to Attorney Sherwood Spelke, an attorney trial referee, in accordance with General Statutes § 52-434(a) and Practice Book (1998 Rev.) § 19-2. The referee submitted a report finding the following facts: (1) the plaintiff's contract with National Video obligated it to fabricate and erect steel beams at the subject premises; (2) the contract price, as modified on December 27, 1995, was for $28,989; (3) the plaintiff performed the work in a timely fashion because the plaintiff was not obliged to commence until the shop drawings were approved by National Video's architect, which was not completed until mid-February of 1996, and also because time was not of the essence in the contract; (4) during the course of construction, the plaintiff sent a bill for approximately $16,000 seeking a progress payment which was not disputed by the defendant National Video; (5) the defendant National Video unilaterally breached the contract by terminating the plaintiff's services with a letter dated April 8, 1996, at a point when the plaintiff's work was "nearly complete;" (6) the plaintiff performed its work in a satisfactory manner, and the defendants did not prove their counterclaim to the contrary; and (7) the cost to National Video of completing the project was $1,970, which is a credit to be subtracted from the contract price.

The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) the plaintiff was entitled to a foreclosure of its mechanic's lien; (2) the debt as of the date of his report. June 21, 1998, was the contract price, less a deposit of $6,187.25, and less the cost of correction, for a total of $20,771 owed to the plaintiff; and (3) the plaintiff had substantially performed the contract when the defendants breached the contract by terminating the plaintiff's services without justification, and hence the referee recommended that judgment enter for the plaintiff with respect to the counterclaim.

Pursuant to Practice Book (1998 Rev.) § 19-12, the defendants moved to correct the referee's report1 in the following respects: (1) the plaintiff's delay in commencing and finishing the project could not be based on a delay in receiving the shop drawings because the plaintiff was in control of preparing such drawings; (2) the plaintiff breach the contract by not beginning the project until mid-March. 1996, and by not finishing it by the time the defendants terminated the plaintiff's involvement with the project; (3) the referee CT Page 14269 recommended a recovery in an amount greater than that claimed in the mechanic's lien; and (4) the defendants should prevail on their counterclaim as their expert witnesses' testimony was unchallenged.

The attorney trial referee declined to make any changes in his report or recommendations in response to the defendants' motion to correct except to reiterate that the contract did not contain a specific date for completion and, hence, the plaintiff had a reasonable time to do so.

The defendants did not, thereafter, file exceptions to the report as authorized by Practice Book (1998 Rev.) § 19-13.2 However, they did file objections to the report as authorized by Practice Book (1998 Rev.) § 19-14.3 The objections reiterate the claims asserted in the motion to correct and assert that: (1) the plaintiff is not excused from a tardy beginning and a failure to complete the project in a timely manner because of an alleged delay in receiving approval of the shop drawings, as the plaintiff was in control of such drawings; and (2) the defendants presented two experts who testified about the cost of completing the project, but who did not contradict each other as the referee indicated, because they were testifying as to different methods of such completion.

This court's scope of review of an attorney trial referee's report was reiterated by the Supreme Court in Elgar v. Elgar,238 Conn. 839, 848-49, 679 A.2d 937 (1996). There, the court held that "[a] reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court . . . or the Superior Court reviewing the findings of . . . attorney trial referees. See Practice Book § 443 . . . The factual findings of a [trial referee] on any issue are reversible only if they are clearly erroneous . . . [A reviewing court] cannot retry the facts or pass upon the credibility of the witnesses . . . A finding of fact is clearly erroneous when there is no evidence in the record to support it . . . or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed." (Citations omitted; internal quotation marks omitted.). See alsoTDS Painting and Restoration, Inc. v. Copper Beach Farm, Inc.,45 Conn. App. 743, 751, 669 A.2d 173, cert. denied, 243 Conn. 908,701 A.2d 338

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
Elgar v. Elgar
679 A.2d 937 (Supreme Court of Connecticut, 1996)
Wilcox Trucking, Inc. v. Mansour Builders, Inc.
567 A.2d 1250 (Connecticut Appellate Court, 1989)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)
Beizer v. Goepfert
613 A.2d 1336 (Connecticut Appellate Court, 1992)
Griffin v. Planning & Zoning Commission
621 A.2d 1359 (Connecticut Appellate Court, 1993)
Iroquois Gas Transmission System v. Mileski
682 A.2d 140 (Connecticut Appellate Court, 1996)
Tarka v. Filipovic
694 A.2d 824 (Connecticut Appellate Court, 1997)
TDS Painting & Restoration, Inc. v. Copper Beech Farm, Inc.
699 A.2d 173 (Connecticut Appellate Court, 1997)
Aunyx Corp. v. Canon U. S. A., Inc.
507 U.S. 973 (Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
1998 Conn. Super. Ct. 14266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowland-ironworks-v-1200-post-r-e-assoc-no-cv-97-0156531-dec-4-connsuperct-1998.