Carmel Homes v. Bednar, No. Cv 99-0079393 S (Oct. 1, 2001)

2001 Conn. Super. Ct. 13475
CourtConnecticut Superior Court
DecidedOctober 1, 2001
DocketNo. CV 99-0079393 S
StatusUnpublished

This text of 2001 Conn. Super. Ct. 13475 (Carmel Homes v. Bednar, No. Cv 99-0079393 S (Oct. 1, 2001)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carmel Homes v. Bednar, No. Cv 99-0079393 S (Oct. 1, 2001), 2001 Conn. Super. Ct. 13475 (Colo. Ct. App. 2001).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
This is an action to foreclose a mechanic's lien in connection with the sale, delivery and installation of a modular home on real property owned by the defendants. The defendants filed a cross-complaint alleging breach of contract and violations of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq., and the manufacturer's modular home warranty statute, General Statutes § 21-86. After trial, submission of briefs and closing argument, the court issued a memorandum of decision, which reserved various issues for a supplemental hearing. The defendants then moved to reargue certain of the court's findings and conclusions. The court opened its decision to allow evidence on whether the parties had intended their contract to apportioned into separate pairs of part performances1 and granted re-argument on whether (a) the plaintiff substantially completed the work it contracted to perform and (b) the court's decision finding substantial performance considered any improper factors. Additional evidence, argument, and briefing followed. This memorandum now addresses all outstanding issues.

I — MOTION FOR REARGUMENT
A — Issues Presented
In contracting for purchase, delivery and installation of the modular home, the parties here signed three different documents that specified the work being contracted for: the purchase agreement and two signed "proposals" for other site work and a heating system. (Plaintiff's CT Page 13476 exhibits two, eight and ten.) In its memorandum of decision, the court found that these documents constituted one contractual agreement. The court also found that the duties each party agreed to perform under that contract could, under the criteria set forth in 2 Restatement (Second), Contracts § 240, p. 229 (1981), Venture Partners, Ltd v. SynapseTechnologies, Inc., 42 Conn. App. 109, 118, 679 A.2d 372 (1996); andKunian v. Development Corporation of America, 165 Conn. 300, 334 A.2d 427 (1973) "be apportioned into corresponding pairs of part performances;" 2 Restatement (Second), supra, § 240, comment (d); or were, in more traditional contract law terminology, divisible or severable into separate sets of duties. The court also found that the plaintiff's substantial performance of its duties under certain pairs of those part performances obliged the defendants "to render performance of the agreed equivalent" by paying the plaintiff for the work done, less credits and offsets allowed by law. The court granted the defendants' request to submit further evidence and argument on these questions.

The defendants claim that the burden of proving that the parties agreed to divisibility of the agreements fell on the plaintiff. (Def.s' Mem. of Law dated July 9, 2001 at 1.) They assert that they would have not agreed to partial performance of the contract as an agreed equivalent. (Id. at 3.) They argue that the evidence establishes that they agreed only to the whole transaction and would not have agreed to a divisible contract. (Id. at 3-4.) They also argue that the plaintiff did not intend the contract to be divisible. (Id. at 5.)

B — Defendants' Argument re Apportioning the Contract into Separate Pairs of Part Performances as Agreed Equivalents
The defendants argue that "the intent of the parties was not to form a divisible contract." (Id. at 1.) The court finds that no credible evidence was offered, either at trial or the supplemental hearing, that when entering into these agreements, either party:

(a) contemplated the question of whether the overall contractual agreement, consisting of the three signed documents, was divisible, severable, or (in the parlance of the Restatement) apportionable into separate pairs of part performances as agreed equivalents; or

(b) specifically intended not to form a divisible (or apportionable) contract.

Heather Bednar testified at the supplemental evidentiary hearing that building a house quickly was important to the defendants; that she CT Page 13477 believed she was signing one agreement instead of separate contracts;2 and that she focused on the total cost instead of the price of individual components of the agreement. Even if the court found this testimony credible, however, it would not defeat application of the rule of apportionment of part performances as agreed equivalents under any of the agreements.

The parties' lack of intent or agreement as to whether the overall contractual agreement could be apportioned into separate pairs of partial performances as agreed equivalents (or would be divisible) does not preclude it being such, if it meets the applicable criteria. Nor would the fact that the defendants may have focused their attention only on the bottom-line total price, as opposed to the costs of the separate components of the various agreements. The Restatement establishes two criteria for a divisible contract: (1) "apportionment" — that the parties' performances can be apportioned into corresponding pairs of part performances; and (2) "agreed equivalents" — that the parts of each pair of performances are agreed equivalents:

If the performances to be exchanged under an exchange of promises can be apportioned into corresponding pairs of part performances so that the parts of each pair are properly regarded as agreed equivalents, a party's performance of his part of such a pair has the same effect on the other's duties to render performance of the agreed equivalent as it would have if only that pair of performances had been promised.

2 Restatement (Second), supra § 240, p. 229 (1981).

This court has previously noted that no language in the agreements specifies an intent to make them severable. As Professor Corbin notes, however, "in most of the cases where the matter is in litigation, the parties had no "intention [regarding divisibility of their agreement] and none can be found by an honest process of interpretation of their expressions." 3A A. Corbin (1960), Contracts § 694, p. 283; see also 2 Restatement (Second), Contracts § 240, comment (e) (1981) ("[t]he parties may, by express provision, determine either that it is or is not proper so to regard them. But they do not often do this, and, because separate pairs of corresponding parts are not the subjects of separate bargains . . ., the parties usually cannot even be said to have had any actual intention on the point."). Thus, the CT Page 13478 absence of contractual language specifying that the agreements were intended to be divisible is neither unusual nor a bar to their being such.

. . .

As the Restatement points out, however, the rules on divisibility of a contract arise only when the parties intended a single contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masda Realty Corporation v. Name Realty Corporation
195 A.2d 559 (Supreme Court of Connecticut, 1963)
Kunian v. Development Corporation of America
334 A.2d 427 (Supreme Court of Connecticut, 1973)
Edens v. Kole Construction Co.
450 A.2d 1161 (Supreme Court of Connecticut, 1982)
Ivey, Barnum & O'Mara v. Indian Harbor Properties, Inc.
461 A.2d 1369 (Supreme Court of Connecticut, 1983)
The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Hinchliffe v. American Motors Corp.
440 A.2d 810 (Supreme Court of Connecticut, 1981)
Hall v. Peacock Fixture & Electric Co.
475 A.2d 1100 (Supreme Court of Connecticut, 1984)
Hartford Federal Savings & Loan Ass'n v. Tucker
491 A.2d 1084 (Supreme Court of Connecticut, 1985)
Gargano v. Heyman
525 A.2d 1343 (Supreme Court of Connecticut, 1987)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
Simonetti v. Lovermi
546 A.2d 331 (Connecticut Appellate Court, 1988)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)
Staehle v. Michael's Garage, Inc.
646 A.2d 888 (Connecticut Appellate Court, 1994)
Steiger v. J. S. Builders, Inc.
663 A.2d 432 (Connecticut Appellate Court, 1995)
Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates
664 A.2d 1177 (Connecticut Appellate Court, 1995)
Venture Partners, Ltd. v. Synapse Technologies, Inc.
679 A.2d 372 (Connecticut Appellate Court, 1996)
Perkins v. Colonial Cemeteries, Inc.
734 A.2d 1010 (Connecticut Appellate Court, 1999)
Jacques All Trades Corp. v. Brown
752 A.2d 1098 (Connecticut Appellate Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2001 Conn. Super. Ct. 13475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carmel-homes-v-bednar-no-cv-99-0079393-s-oct-1-2001-connsuperct-2001.