Regional School Dist. v. Wayne Const., No. Cv99 033 78 80 S (May 18, 2000)

2000 Conn. Super. Ct. 5775
CourtConnecticut Superior Court
DecidedMay 18, 2000
DocketNo. CV99 033 78 80 S, No. CV99 033 78 13 S
StatusUnpublished

This text of 2000 Conn. Super. Ct. 5775 (Regional School Dist. v. Wayne Const., No. Cv99 033 78 80 S (May 18, 2000)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regional School Dist. v. Wayne Const., No. Cv99 033 78 80 S (May 18, 2000), 2000 Conn. Super. Ct. 5775 (Colo. Ct. App. 2000).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
Wayne Construction Corp. ("Wayne"), a New York corporation with a principal place of business in Scarsdale, New York, filed the present application to confirm an arbitral award in its favor, pursuant to §52-417 of the General Statutes.1 Regional School District No. 9 (the "District"), a public school district with authority and control over the operation of public schools within Region District No. 9 of Redding/Easton, Connecticut, filed the present cross-application to CT Page 5776 vacate the award, pursuant to § 52-418 (a)(4).2

The arbitration panel could reasonably have found the following facts. On September 24, 1993, the District and Wayne entered into a contract for renovation and building code update work (project) at the Joel Barlow High School in Redding, which was owned and operated by the District. The parties, termed as "Owner" and "Contractor," respectively, in the contract, adopted verbatim the standard boilerplate contract entitled, "General Conditions of the Contract for Construction" (standard agreement), prepared and printed by the American Institute of Architects (AIA Document A201, 1987 Ed.), as their main contract, supplemented by a "Standard Form of Agreement Between Owner and Contractor" (AIA Document A101, 1987 Ed.), which filled out information specific to the parties and their contract, and a typewritten "Supplementary General Conditions" (supplementary agreement), dated April 1, 1993. The three documents "represent the entire and integrated agreement between the parties." (AIA Document A101, arts. 1 9.) The District retained Kaestle Boos Associates, Inc. (hereinafter the "architect"), which acted as its representative, inspector and liaison with Wayne during construction. The architect also had the authority to determine whether the project performed by Wayne was satisfactory under the terms of the contract and whether the project met the terms of "substantial completion" and "final completion" as defined in the contract. Under the contract, the project was to be "substantially complete" within 365 days from September 23, 1993, with an additional thirty days for the "final completion."

The standard agreement contains a broad arbitration clause. Subparagraph 4.5.1 provides, in pertinent part:

Any controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator or arbitrators may be entered in any court having jurisdiction thereof. . . . Such controversies or Claims upon which the Architect has given notice and rendered a decision as provided in Subparagraph 4.4.4 shall be subject to arbitration upon written demand of either party. Arbitration may be commenced when 45 days have passed after a Claim has been referred to the Architect as provided in Paragraph 4.3 and no decision has been rendered.

CT Page 5777

The work was overseen on behalf of District by a school building committee ("committee"), chaired by Michael S. Cardillo. Wayne alleged that from the outset, the committee, especially Cardillo, continually disrupted its work, egregiously interfered with its rights under the contract, and usurped the authority of the architect to administer the contract. The District's architect informed Wayne, via certified mail, dated October 14, 1994, in response to Wayne's revised application for payment number 10, that Wayne had failed to meet "substantial completion" in accordance with all contract requirements. Wayne claimed that the District unilaterally adjusted and reduced the balance due under the revised application for payment number 10. On November 23, 1994, the parties terminated the contract and the District declared a contractor default. The District subsequently made demands on Wayne's surety Hartford Fire Insurance Company ("Hartford"), to complete a "punch list" of the project under the performance bond, that is, what needed to be done in order to achieve the "final completion" of the project.

On March 8, 1995, the District and Hartford entered into a completion agreement of the "punch list." The completion agreement expressly provided that neither Wayne nor the District acknowledged liability for breach of contract damages and that the agreement was made solely for the purpose of mitigating damages. Hartford and Wayne signed a settlement agreement on September 15, 1997, which resolved the issues of Wayne's liability to Hartford, under the performance bond, for the expenses of completing the project and consequential damages from Wayne's inability, allegedly due to the District's failure to pay a balance due under the revised application for payment number 10, to satisfy claims by Wayne's subcontractors and labor and material suppliers. Pursuant to the settlement agreement, Hartford also irrevocably assigned, conveyed and transferred to Wayne all of its rights to seek reimbursement or indemnification from the District.

On November 3, 1997, Wayne filed a demand for arbitration of its claim arising out of the contract with the American Arbitration Association (AAA), seeking recovery of damages, among others, from the alleged unpaid balance due for the work performed, home office and project delay damages, extra costs for the additional work, costs and expenses charged by its surety Hartford, damages to its reputation and lost profits and damages for impairment of its bonding capacity. The District filed a "preliminary answering statement," dated November 17, 1997, denying Wayne's arbitration claims and asserting a counterclaim for "professional fees and expenses, and extra costs in dealing with [Wayne's] breach of contract and the subsequent effort to complete the building project." The District also asserted therein the special defense that the arbitration demand and claim for relief were untimely CT Page 5778 and barred under the terms of the contract. The District filed a "supplemental answering statement and counterclaim," dated December 1, 1997, substantiating its special defense of the untimeliness of Wayne's arbitration defense and its counterclaim. The District and Wayne mutually agreed upon a panel of three arbitrators, recognized as experts in their respective fields of construction law, contracting and engineering.

On March 27, 1998, the District filed a motion to dismiss Wayne's arbitration demand as untimely. In its motion, the District argued that the architect had exclusive and final authority to determine any of Wayne's claims pursuant to paragraph 4.3.2 of the supplementary agreement.3 In addition, the District argued that Wayne failed to file its arbitration demand in a timely manner under the terms of the contract. On April 17, 1998, the arbitrators denied the District's motion to dismiss.

On October 22, 1998, the District filed a request to bifurcate the hearing. It requested that the arbitrators structure the hearing in such a manner so that it could be allowed to put on evidence of its defense before Wayne had the opportunity to put on its case-in-chief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morici v. Jarvie
75 A.2d 47 (Supreme Court of Connecticut, 1950)
Gary Excavating, Inc. v. Town of North Haven
318 A.2d 84 (Supreme Court of Connecticut, 1972)
Beckman v. JALICH HOMES, INC.
460 A.2d 488 (Supreme Court of Connecticut, 1983)
Grenier v. Compratt Construction Co.
454 A.2d 1289 (Supreme Court of Connecticut, 1983)
Silliman Co. v. S. Ippolito & Sons, Inc.
467 A.2d 1249 (Connecticut Appellate Court, 1983)
Noroton Heights Fire Department v. Vuono-Lione, Inc.
362 A.2d 982 (Supreme Court of Connecticut, 1975)
West Haven Sound Development Corp. v. City of West Haven
514 A.2d 734 (Supreme Court of Connecticut, 1986)
Town of East Hartford v. East Hartford Municipal Employees Union, Inc.
539 A.2d 125 (Supreme Court of Connecticut, 1988)
White Oak Corp. v. Department of Transportation
585 A.2d 1199 (Supreme Court of Connecticut, 1991)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Garrity v. McCaskey
612 A.2d 742 (Supreme Court of Connecticut, 1992)
White v. Kampner
641 A.2d 1381 (Supreme Court of Connecticut, 1994)
Saturn Construction Co. v. Premier Roofing Co.
680 A.2d 1274 (Supreme Court of Connecticut, 1996)
United States Fidelity & Guaranty Co. v. Hutchinson
710 A.2d 1343 (Supreme Court of Connecticut, 1998)
Town of Stratford v. International Ass'n of Firefighters
728 A.2d 1063 (Supreme Court of Connecticut, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2000 Conn. Super. Ct. 5775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/regional-school-dist-v-wayne-const-no-cv99-033-78-80-s-may-18-2000-connsuperct-2000.