Elm Haven Construction Ltd. Partnership v. Neri Construction, LLC

281 F. Supp. 2d 406, 2003 U.S. Dist. LEXIS 15956, 2003 WL 22118953
CourtDistrict Court, D. Connecticut
DecidedSeptember 11, 2003
Docket3:01CV1307 (GLG)
StatusPublished
Cited by14 cases

This text of 281 F. Supp. 2d 406 (Elm Haven Construction Ltd. Partnership v. Neri Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elm Haven Construction Ltd. Partnership v. Neri Construction, LLC, 281 F. Supp. 2d 406, 2003 U.S. Dist. LEXIS 15956, 2003 WL 22118953 (D. Conn. 2003).

Opinion

MEMORANDUM DECISION

GOETTEL, District Judge.

The plaintiff, Elm Haven Construction Limited Partnership, (EHC), brings this *408 action against the defendants, Neri Construction, LLC (Neri) and Unites States Fidelity & Guaranty Company (USF & G). This motion concerns the plaintiffs claims against USF & G only. Specifically, the plaintiff claims that USF & G breached its obligations pursuant to a performance bond and a payment bond that it issued on behalf of Neri, and that USF & G breached an implied covenant of good faith and fair dealing. USF & G has filed a motion for summary judgment claiming that the plaintiff (1) is not entitled to any funds pursuant to the performance bond because it failed to declare a default and give sufficient notice of the alleged default, as required by the bond and underlying subcontract; and, (2) cannot sue on the payment bond because it is not a “claimant” as that term is defined in the bond. We agree with USF & G that no genuine issue of fact exists as to any of the plaintiffs claims against it and, for the reasons set forth more fully below, GRANT USF & G’s motion for summary judgment.

Standard

“Summary judgment is appropriately granted when the evidentiary record shows that there are no genuine issues of material fact and that the moving party is entitled to judgment as a matter of law.” Balfour Beatty Constr., Inc. v. Colonial Ornamental Iron Works, Inc., 986 F.Supp. 82, 84 (D.Conn.1997); see Fed.R.Civ.P. 56. The court must view all inferences and ambiguities in a light most favorable to the non-moving party. See Bryant v. Maffucci, 923 F.2d 979, 982 (2d Cir.1991), cert. denied, 502 U.S. 849, 112 S.Ct. 152, 116 L.Ed.2d 117 (1991). “A plaintiff raises a genuine issue of material fact if the jury could reasonably find for the plaintiff.” Balfour, 986 F.Supp. at 84 (citation and internal quotation marks omitted).

Because we must evaluate the terms of a contract, i.e., the performance and payment bonds, summary judgment is appropriate only when the terms of the agreement are wholly unambiguous. Heyman v. Commerce & Indus. Ins. Co., 524 F.2d 1317, 1320 (2d Cir.1975). Contractual language is unambiguous if it has “ ‘a definite and precise meaning, unattended by danger of misconception in the purport of the [contract] itself, and concerning which there is no reasonable basis for a difference of opinion.’ ” Hunt Ltd. v. Lifschultz Fast Freight, Inc., 889 F.2d 1274, 1277 (2d Cir.1989).

Language does not become ambiguous solely because the parties offer conflicting interpretations during the course of litigation. See Wards Co. v. Stamford Ridgeway Assocs., 761 F.2d 117, 120 (2d Cir.1985); see also Schering Corp. v. Home Ins. Co., 712 F.2d 4, 9 (2d Cir.1983). Instead, the moving party must prove that the contractual language is not susceptible to at least two fairly reasonable meanings. Schering, 712 F.2d at 9; see also Cable Science Corp. v. Rochdale Village, Inc., 920 F.2d 147, 151 (2d Cir.1990). If the moving party cannot establish unambiguous contract language, a material issue exists concerning the parties’ intent, which is a question of fact, thereby rendering summary judgment inappropriate. Thompson v. Gjivoje, 896 F.2d 716, 721 (2d Cir.1990).

Facts

In January of 1999, EHC entered into a contract, as general contractor, for a construction project in New Haven, Connecticut. In May of that same year, EHC entered into a contract with Neri, making Neri a subcontractor on the project. In consideration of roughly $3,642,000, Neri agreed to furnish labor, materials, and equipment for the project. The subcontract required also that Neri post a bond guaranteeing the performance of the subcontract and a payment bond for labor and materials for the benefit of Neri’s subcon *409 tractors and suppliers on the project. USF & G issued the two separate bonds on Neri’s behalf. Shortly thereafter, Neri began its work on the project.

Problems arouse between Neri and EHC roughly two months into the project. EHC, as it claims, found that Neri was failing to comply with site plans and specifications. Additionally, EHC alleges that Neri was not using the proper materials, was failing to coordinate its work and was not complying with certain erosion requirements. Around February, 2001, EHC began sending correspondence to Neri and USF & G regarding its displeasure with Neri’s performance of its obligations under the contract.

These letters are the focus of our inquiry regarding the performance bond because USF & G claims that EHC failed to declare properly Neri’s default under the relevant contract provisions. EHC contests this argument claiming that “USF & G had actual and reasonable notice that [it] had declared Neri in default under the subcontract, and that [it] was making demands upon the performance bond.” (Ford Aff. ¶ 25.) We will set forth the relevant contract provisions and letters regarding the performance bond and address the parties’ arguments in that regard, followed by our discussion of the payment bond

Discussion

Performance Bond and Letters

In relevant part, the performance bond requires specifically that,

Whenever Principal shall be, and be declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee’s obligations thereunder: (1) Surety may promptly remedy the default subject to the provisions of paragraph 3 herein, or; (2) Obligee after reasonable notice to Surety may, or Surety upon demand of Obligee, may arrange for the performance of Principal’s obligation under the subcontract subject to the provisions of paragraph 3 herein; (3) The balance of the subcontract price, as defined below, shall be credited against the reasonable cost of completing performance of the subcontract.

(See Schoenhaar Aff., Ex. A (emphasis added.))

The performance bond also incorporated the subcontract between EHC and Neri.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
281 F. Supp. 2d 406, 2003 U.S. Dist. LEXIS 15956, 2003 WL 22118953, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elm-haven-construction-ltd-partnership-v-neri-construction-llc-ctd-2003.