Elm Haven Construction Ltd. Partnership v. Neri Construction LLC

376 F.3d 96
CourtCourt of Appeals for the Second Circuit
DecidedJuly 23, 2004
DocketDocket No. 03-7967
StatusPublished
Cited by2 cases

This text of 376 F.3d 96 (Elm Haven Construction Ltd. Partnership v. Neri Construction LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elm Haven Construction Ltd. Partnership v. Neri Construction LLC, 376 F.3d 96 (2d Cir. 2004).

Opinion

WINTER, Circuit Judge.

Elm Haven Construction L.P. (“Elm Haven”) appeals from Judge Goettel’s grant of summary judgment to United States Fidelity and Guaranty Company (“USF &, G”) on Elm Haven’s claims against Performance and Payment Bonds issued by USF & G. The district court held that USF & G was not liable on the Performance Bond because Elm Haven failed, as required by the bond, to declare a default and to allow USF & G to cure that default before Elm Haven hired a replacement subcontractor. The court further held that USF & G was not liable to Elm Haven on the Payment Bond because Elm Haven was not a “claimant” entitled to sue on the bond and had not been assigned the rights of any claimant. We affirm.

BACKGROUND

On January 26, 1999, Elm Haven and Neri Construction LLC (“Neri”) entered into a subcontract agreement with Neri as subcontractor and Elm Haven as general contractor. Pursuant to the subcontract agreement, Neri purchased a Performance Bond and a Payment Bond from USF & G on March 16, 1999. Connecticut law governs the subcontract agreement and the bonds.

The Performance Bond, which was in the amount of $3,642,600, imposed certain obligations and conferred certain rights on USF & G (“Surety”) if Elm Haven (“Obli-gee”) declared Neri (“Principal”) to be “in default,” as follows:

Whenever Principal shall be, and be declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee’s obligations thereunder:
(1)Surety may promptly remedy the default subject to the provisions of paragraph 3 herein, or;
(2) Obligee after reasonable notice to Surety may, or Surety upon demand of Obligee, may arrange for the performance of Principal’s obligation under the subcontract subject to the provisions of paragraph 3 herein;
(3) The balance of the subcontract price, as defined below, shall be credited against the reasonable cost of completing performance of the subcontract.

The subcontract agreement between Neri and Elm Haven was made a part of the Performance Bond by reference. The subcontract agreement outlined procedures to be followed in the event of a default by Neri. Elm Haven was required to give Neri 72 hours written notice to cure a default, and if Neri did not cure, Elm Haven could perform the work itself, withhold payment from Neri, and/or terminate its subcontract agreement with Neri and hire another subcontractor. Thus, a partial default under the subcontract agreement did not require a termination of that agreement.

The Payment Bond was for $3,642,600 “for the use and benefit of claimants.” The bond defined a “claimant” as “one having a direct contract with the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract.” Under the bond, only claimants who were not paid within 90 days of performance could sue USF & G for the amount due. The subcontract agreement was incorporated into the Payment Bond by reference. That agreement gave Elm Haven several rights with respect to Neri’s subcontractors — the potential claimants under the Payment Bond— including the right to ask sub-subcontractors if they were being paid, to refuse progress payments to Neri if such payments were necessary to satisfy liens filed by third parties, and to issue joint progress payment checks to Neri and its sub[99]*99contractors if Elm Haven believed that the sub-subcontractors were not being paid. The subcontract agreement also included the following sentence, handwritten and initialed by both Neri and USF & G, in three places: “No payments will be made to subcontractors sub-subcontractors or suppliers without prior approval of this subcontractor [Neri] and its bonding company [USF & G]

About two months after work began on the project, Neri and Elm Haven began complaining about each other’s performance. Elm Haven sent several letters to Neri, copied to USF & G, detailing its complaints about Neri’s performance and failure to respond to inquiries from Elm Haven. It also sent letters to USF & G requesting its “assistance in this matter.” Beginning in April, several letters informed USF & G and Neri that certain portions of the work for which Neri was responsible would be performed by others because Neri had either failed to perform, or claimed that it was not contractually required to perform, that work. For example, the April 30 letter stated that, because Neri had failed to perform certain parts of its work, Elm Haven “hereby provides notice to [Neri] that this work will be performed by others in accordance with” the default provisions of the subcontract agreement. On May 17, 2001, Elm Haven contracted with another subcontractor — Sweeney Excavation — to replace Neri. Moreover, two of Neri’s sub-subcontractors or suppliers made payment claims against Elm Haven, and one of them filed a mechanic’s lien against Elm Haven. Elm Haven paid the lienholder claimant directly, without seeking approval from Neri or USF & G.

Finally, on June 26, 2001, Elm Haven wrote directly to USF & G, noting that it had been “forced to supplement NERI forces in completing the balance of contract work,” that Neri had “virtually abandoned” the project as of April 30, and that Elm Haven had incurred an estimated loss of $942,102. USF & G responded by stating that it was not liable to Elm Haven under the Performance Bond.

The Performance Bond issued by USF & G in connection with this matter clearly sets forth the requirements for notice of default necessary to trigger any obligation on the part of the surety. The language of the Performance Bond clearly requires that, in order to trigger the. surety’s obligations, the principal shall be in default and that the obligee shall affirmatively declare the principal in default. Review of the file reveals that there has been no declaration of default which would trigger the surety’s obligations. Elm Haven’s unilateral actions . have precluded USF & G from performing an investigation and exercising its, options under the bond.

Elm Haven replied that it had declared Neri in default at least by April 30, 2001, and that USF & G therefore was liable on the Performance Bond.

Elm Haven also sought payment from USF & G under the Payment Bond, which was denied. Elm Haven then brought the instant suit against USF & G and Neri on July 11, 2001, alleging in pertinent part that USF & G breached its obligations under both bonds and under the implied covenant of good faith and fair dealing.

DISCUSSION

The district court granted USF & G’s motion for summary judgment on August 22, 2003. Relying primarily on L & A Contracting v. Southern Concrete Services, Inc., 17 F.3d 106 (5th Cir.1994), the court held that the “declaration of default term” of the Performance Bond was unambiguous and was satisfied only by a “sufficiently clear, direct, and unequivocal or precise [100]*100declaration of default.” Elm Haven Constr. L.P. v. Neri Constr., LLC, 281 F.Supp.2d 406, 413 (D.Conn.2003). In the court’s view, no such declaration occurred prior to Elm Haven’s June 26, 2001 letter, by which time Elm Haven had hired Sweeney Excavation, thus “preclud[ing] USF & G from exercising its options” under the bond and rendering the bond void. Id. at 414.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
376 F.3d 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elm-haven-construction-ltd-partnership-v-neri-construction-llc-ca2-2004.