LeChase Construction Services LLC v. United Structures of America, Inc.

CourtDistrict Court, W.D. New York
DecidedFebruary 12, 2024
Docket6:20-cv-06915
StatusUnknown

This text of LeChase Construction Services LLC v. United Structures of America, Inc. (LeChase Construction Services LLC v. United Structures of America, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeChase Construction Services LLC v. United Structures of America, Inc., (W.D.N.Y. 2024).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NEW YORK _____________________________________

LeCHASE CONSTRUCTION SERVICES, LLC,

Plaintiff, DECISION AND ORDER

v. 6:20-CV-06915 EAW

ARGONAUT INSURANCE COMPANY,

Defendant. _____________________________________

I. INTRODUCTION Pending before the Court is a motion for summary judgment filed by defendant Argonaut Insurance Company (“Defendant”). (Dkt. 25). Because material issues of fact prevent resolution of this case as a matter of law at this pre-answer stage of the proceedings, the motion is denied. II. BACKGROUND This matter arises from a construction project in Dover, New York, known as the Cricket Valley Energy Administration and MCE Building Project (“the Project”). (See Dkt. 1-1 at 9, ¶ 4; Dkt. 25-12 at ¶ 1). Plaintiff LeChase Construction Services, LLC (“Plaintiff”) performed work on the Project. (Dkt. 25-12 at ¶ 1; Dkt. 26-19 at ¶ 1). On June 8, 2017, Plaintiff entered into a subcontract with United Structures of America, Inc. (“USA”) to provide structural steel design and fabrication for the Project. (Dkt. 25-12 at ¶ 2; Dkt. 26-19 at ¶ 2). USA’s original contract amount with Plaintiff was $3,874,383. (Dkt. 25-12 at ¶ 3; Dkt. 26-19 at ¶ 3). USA as principal executed a Supply Bond (“the Bond”) with Defendant as surety in the amount of $3,874,383. (Dkt. 25-12 at ¶ 4; Dkt. 26-19 at ¶ 4; see Dkt. 25-9). The Bond was issued to and accepted by Plaintiff, as obligee. (Dkt. 25-12 at ¶ 5; Dkt. 26-19 at ¶ 5). The Bond states, in relevant part, as

follows: [A]ny suit by [Plaintiff] under this bond must be instituted before . . . the earlier of: (a) the expiration of one year from the date [USA] was obligated under the Material Contract to deliver the materials to [Plaintiff], or (b) the expiration of one year from the date any other default by [USA] under the Material Contract.

(Dkt. 25-9 at 1 (emphasis added)). Plaintiff filed its complaint on July 20, 2020, in New York State Supreme Court, Monroe County. (Dkt. 1-1 at 11). The crux of the dispute on the pending motion is whether USA defaulted prior to July 20, 2019, because if so and if no exception applies, the claim would be untimely. On September 18, 2019, Plaintiff issued Purchase Change Order No. 18 (“Change Order 18”) that reduced USA’s contract balance by $144,000, which according to Plaintiff accounted for the removal of site supervision from USA’s scope of work and still resulted in a positive value on USA’s subcontract. (Dkt. 25-12 at ¶ 8; Dkt. 26-19 at ¶ 8). The description on Change Order 18 stated: “Additional LCS Costs due to USA Breach of Contract. Costs Include Added LeChase General Conditions to manage USA abandonment of the work, additional fabrication issues that have been discovered.” (Dkt. 25-10 at 1 (emphasis added)). A spreadsheet attached to Change Order 18 details additional costs incurred by Plaintiff commencing on July 2, 2018. (Id. at 2; see also id. at 9). Defendant contends that Plaintiff submitted a formal claim on the Bond on November 1, 2019 (Dkt. 25-12 at ¶ 13), but Plaintiff denies that this correspondence was a formal claim—instead arguing that it submitted costs to Defendant on that date in the amount of $431,421.68 relating to costs it had incurred as a result of USA’s default, and that it first notified Defendant of issues relating to USA’s performance on the Project on

September 5, 2019 (Dkt. 26-19 at ¶ 13). Plaintiff contends that its claim on the Bond is “limited to USA’s default for failing to indemnify and make [Plaintiff] whole for the costs outlined in the letter dated October 28, 2019.” (Id. at ¶ 14). By letter dated February 12, 2020, Plaintiff wrote to Defendant outlining that its total claim against the Bond was $2,232,212.68, plus interest and attorneys’ fees. (Dkt.

25-11). In that letter, Plaintiff states, among other things, that its costs underlying the Bond are tied, in part, to Change Order 18, which “contains certain additional labor costs attributable to the significant increase in the amount of time required by [Plaintiff’s] field management staff to manage fabrication errors, incomplete or inaccurate deliveries, and other problems with orders, materials, and related safety issues caused by USA.” (Id. at

1). Plaintiff further states that these issues and its costs “were exacerbated by USA’s refusal to come to the jobsite and manage these issues itself.” (Id.). This necessitated, according to Plaintiff, its assignment of an additional superintendent to the Project (whose spreadsheet of time is attached to Change Order 18, reflecting the time commencing on July 2, 2018). (Id. at 1-2).

Defendant contends that it denied Plaintiff’s claim on the Bond, in part, on the basis that the claim was untimely because the action was not filed within one year of USA’s default. (See Dkt. 25-13 at 7). After commencement of this action, the case was removed to this Court on October 30, 2020, on the basis for diversity jurisdiction. (Dkt. 1).1 After removal, the Court granted Plaintiff’s motion to remand and denied Defendant’s summary judgment motion as moot. (Dkt. 15). The Second Circuit Court of Appeals vacated the

Court’s remand order and sent the case back for further proceedings. (Dkt. 19). After conferring with the parties, a briefing schedule was set for the filing of Defendant’s renewed motion for summary judgment. (Dkt. 22; Dkt. 24). Defendant filed its summary judgment motion on June 30, 2023. (Dkt. 25). Plaintiff responded in opposition on July 28, 2023. (Dkt. 26). Defendant filed a reply memorandum in further

support of its motion on August 18, 2023. (Dkt. 27). Oral argument was held before the undersigned on November 28, 2023, at which time the Court reserved decision. (Dkt. 31). After oral argument, Plaintiff submitted without leave further papers in opposition to the motion for summary judgment. (Dkt. 32). Defendant filed a letter objecting to the untimely filing (Dkt. 34), and Plaintiff submitted a response (Dkt. 35). Because Plaintiff

failed to request leave before making its additional submissions, and even now only seeks leave as an afterthought in a letter filed in response to Defendant’s objections, see W.D.N.Y. Loc. R. Civ. P. 6(a)(6) (“Absent permission of the Judge hearing the motion, sur-reply papers are not permitted.”), the Court will not consider the post-argument submissions.

1 Although it took repeated efforts by Plaintiff to comply with the Court’s directions that it file further information concerning the citizenship of its members (see Dkt. 31; Dkt. 33; Dkt. 36; Dkt. 37; Dkt. 38; Dkt. 39), it finally complied with the Court’s requests and the Court agrees that the parties’ citizenship is diverse. III. DISCUSSION Rule 56 of the Federal Rules of Civil Procedure provides that summary judgment should be granted if the moving party establishes “that there is no genuine dispute as to

any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). The Court should grant summary judgment if, after considering the evidence in the light most favorable to the nonmoving party, the court finds that no rational jury could find in favor of that party. Scott v. Harris, 550 U.S. 372, 380 (2007) (citing Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87 (1986)). Once the moving

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Caldarola v. Calabrese
298 F.3d 156 (Second Circuit, 2002)
International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
Varlotta Construction Corp. v. Sette-Juliano Construction Corp.
234 A.D.2d 183 (Appellate Division of the Supreme Court of New York, 1996)
Shawnlee Construction, LLC v. J.K. Scanlan Co.
42 F. Supp. 3d 561 (S.D. New York, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
LeChase Construction Services LLC v. United Structures of America, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lechase-construction-services-llc-v-united-structures-of-america-inc-nywd-2024.