Jackson v. Fortunato, No. Cv 88-0096695 (Apr. 8, 1997)

1997 Conn. Super. Ct. 3925
CourtConnecticut Superior Court
DecidedApril 8, 1997
DocketNo. CV 88-0096695
StatusUnpublished

This text of 1997 Conn. Super. Ct. 3925 (Jackson v. Fortunato, No. Cv 88-0096695 (Apr. 8, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson v. Fortunato, No. Cv 88-0096695 (Apr. 8, 1997), 1997 Conn. Super. Ct. 3925 (Colo. Ct. App. 1997).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This is an action to foreclose mechanic's liens filed by the plaintiff, Charles Jackson, against property owned by the defendant, Robert A. Fortunato.1 The plaintiff alleges that he provided goods and services to the defendant commencing on July 27, 1986, in connection with the construction of a new home for the defendant at 30 Carrington Drive, Greenwich. The plaintiff further alleges in his complaint that he completed his work on September 1, 1987, and that he is owed approximately $22,500. The plaintiff filed two mechanic's liens, one in Greenwich on November 9, 1987, and the other in Stamford on November 16, 1987.2 CT Page 3926

In his revised answer dated June 13, 1996, the defendant denied owing any money to the plaintiff and left the plaintiff to his proof regarding the date on which he completed his work and services. The defendant did not file any special defenses, but did file an amended counterclaim dated August 28, 1996. The counterclaim consists of two counts. In the first count, the defendant alleges that he entered into a written contract with the plaintiff dated May 5, 1986, pursuant to which the plaintiff agreed to construct a single-family residence for the defendant "in a workmanlike manner" for approximately $254,000. The defendant further alleges that the plaintiff constructed the residence in a negligent and unworkmanlike manner, resulting in numerous defects in both the interior and exterior of the residence. The defendant seeks monetary damages because he has incurred or will incur costs to "correct and cure" the alleged defects.

In the second count of the counterclaim, the defendant alleges that the plaintiff also breached the contract by failing to "substantially complete" the project by March 15, 1987, as called for in the contract. The defendant claims that this delay caused him to pay additional interest on his construction loan.

In addition to denying the material allegations of the counterclaim, the plaintiff filed several special defenses, viz., that the defendant's counterclaim violates the statutes of limitations for both negligence actions as set forth in General Statutes § 52-584, and for breach of contract actions in General Statutes § 52-576; that the defendant failed to minimize his damages; that the defendant waived any defects because he accepted the plaintiff's work; and that the defendant is estopped from complaining about the work because he failed to raise timely objection thereto.

A bench trial was held over the course of several days during which the contract between the plaintiff and the defendants was introduced into evidence. This contract is labeled as an agreement between "Owner And Construction Manager" and provides that for a fixed fee the plaintiff will review the plans, develop a construction schedule, analyze bids, recommend the awarding of contracts, monitor costs, and generally coordinate the construction project, including the work of the various contractors, on behalf of the defendant. CT Page 3927

The first issue presented by the parties is the validity of the mechanic's liens that the plaintiff is seeking to foreclose. The evidence indicated that the defendant took occupancy of the subject premises in July, 1987, and that the town of Greenwich issued a certificate of occupancy on August 15, 1987. The plaintiff claims that he worked on the job until September 1, 1987, and that the filing of his liens complied with General Statutes § 49-34. This statute requires a lienor to file a certificate "within ninety days" after ceasing work. The defendant claims that the ninety days should run from the granting of the certificate of occupancy, which would mean that the lien filed in Stamford on November 16, 1987, was one or two days late, since the certificate of occupancy, as noted previously, was issued on August 15, 1987.

If a certificate of occupancy truly marked the commencement of the period for filing a lien, certainly some interesting issues would ensue in light of the fact that the building permit and certificate of occupancy were both issued by the town of Greenwich, the residence itself is in Greenwich, where the lien was timely filed, and the vast majority of the four acre plot is in that town, with only a small slice of land in Stamford. However, the certificate of occupancy issued in this case to the defendant provides only that the work complied with all state and local "laws and ordinances." The defendant has not cited any case that holds that such a certificate conclusively establishes the starting date for a timely filing under General Statutes § 49-34, which refers to "work" on the part of the lienor. Compliance with laws and ordinances, on the one hand, and "work," on the other, appears to involve different concepts. It has also been noted that while obtaining a certificate of occupancy "may be evidence of substantial performance, it is not dispositive of the question." Miller v. Bourgoin, 28 Conn. App. 491, 496,613 A.2d 292, cert. denied, 223 Conn. 927, 614 A.2d 825 (1992). By analogy, obtaining such a certificate does not dispose of the question as to when a lienor ceased work.

In that regard, the evidence disclosed that the plaintiff did perform certain work at the defendant's home after the issuance of the certificate of occupancy. This work, however, was characterized by the defendant as "trivial" in nature. He citedMartin Tire Rubber Co. v. Kelly Tire Rubber Co.,99 Conn. 396, 122 A. 102 (1923), for the proposition that trivial work or minor repairs do not constitute "work" within the meaning of the mechanic's lien statute. There were, according to the evidence, a CT Page 3928 number of "punchlist" items that the plaintiff completed after the certificate had been issued on August 15, 1987.3 The performance of some fifteen or so punchlist items at the specific request of the defendant does not appear to fall within the definition of "trivial" work as discussed in Martin Tire RubberCo., supra. The defendant's claim that the liens were not filed in a timely fashion is therefore rejected because work was performed after August 15, 1987, and within ninety days of filing the liens in Greenwich and in Stamford.

The evidence indicates that the defendant paid the plaintiff all that was billed and owed except for the final invoice of October 19, 1987, in the amount of $22,427. This sum included $8,000 for construction management and the balance for work personally performed by the plaintiff. In addition, section 10.6 of the contract provides that "if the scope of the project is changed materially, the amounts of compensation shall be equitably adjusted." The plaintiff claims that the scope of the project had increased by about $60,000 and that he was entitled to 10% or $6,000, which percentage is in line with the calculation of the management fee in the contract and does not appear to be inequitable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
Miller v. Bourgoin
613 A.2d 292 (Connecticut Appellate Court, 1992)
Lawson v. Whitey's Frame Shop
682 A.2d 1016 (Connecticut Appellate Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Conn. Super. Ct. 3925, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-v-fortunato-no-cv-88-0096695-apr-8-1997-connsuperct-1997.