Miller v. Bourgoin

613 A.2d 292, 28 Conn. App. 491, 1992 Conn. App. LEXIS 307
CourtConnecticut Appellate Court
DecidedAugust 4, 1992
Docket10005
StatusPublished
Cited by45 cases

This text of 613 A.2d 292 (Miller v. Bourgoin) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Bourgoin, 613 A.2d 292, 28 Conn. App. 491, 1992 Conn. App. LEXIS 307 (Colo. Ct. App. 1992).

Opinion

O’Connell, J.

The defendants appeal from the trial court’s decision rendering summary judgment in the [492]*492plaintiffs’ favor on both the complaint and the defendants’ counterclaim. The appeal arises from an alleged breach of a written contract for the construction and sale of a house.

The defendants’ first four claims are subsumed under the claim that the trial court improperly granted the plaintiffs’ motion for summary judgment on the complaint because there were material factual issues to be determined.1 The defendants’ fifth claim is that the trial court improperly granted summary judgment on the counterclaim because it was not before the court and because there were material factual issues to be determined. We reverse the judgment on the complaint and the counterclaim.

The following facts are relevant to the appeal. The plaintiffs were prospective buyers of a building lot and house to be constructed by the defendants. The parties’ original written contract specified a closing date of September 12, 1989. The plaintiffs paid a $16,000 deposit toward the purchase price of $190,000 with the balance to be paid at the closing.

In July, 1989, in connection with the installation of the septic leaching fields, the defendants had the property resurveyed and discovered that the foundation extended several feet over the approved building line. [493]*493The defendants attempted to remedy the problem by applying for a zoning variance. The application was denied in early September and the defendants were forced to reposition the foundation, thereby incurring a delay.

Recognizing that the house would not be completed by September 12, the parties agreed to postpone the closing date to October 31, 1989. Thereafter, the defendants requested, and the plaintiffs granted, five further extensions of time for the defendants to perform the contract. Three of those extensions were granted after the plaintiffs had unilaterally notified the defendants that time was of the essence.

The final agreed upon closing date was January 2, 1990, subject to the issuance of a certificate of occupancy and a final inspection by the plaintiffs’ mortgage lender, which was to take place on December 29,1989. On the morning of December 29, the mortgage lender inspected the premises and notified the plaintiffs that the house was not sufficiently complete to allow a January 2,1990 closing. Later that day, the plaintiffs communicated to the defendants, both orally and in writing, that they were terminating the contract on the ground that the defendants had breached the contract by failing to complete the house in a timely manner. The plaintiffs further demanded the return of their $16,000 deposit. On January 4,1990, five days after the notification of termination and two days following the scheduled closing date, the town building inspector issued a certificate of occupancy for the house. The defendants ultimately sold the house to a third party in June of 1990 for a figure substantially less than the contract price.

The plaintiffs brought this action, in two counts, to recover their deposit. The first count alleged that the defendants breached the contract by failing to have the [494]*494premises completed by December 29, 1989. The second count alleged that the actions of the defendants “constituted unfair, immoral, unethical, oppressive and unscrupulous business practices” in violation of General Statutes § 42-110b of the Connecticut Unfair Trade Practices Act (CUTPA).

The defendants’ answer raised special defenses concerning waiver and estoppel, substantial performance, fraudulent representation, setoff, and the nonapplicability of CUTPA. The defendants additionally filed a counterclaim in two counts to recover the difference between the contract price and the actual selling price. The plaintiffs’ answer to the counterclaim raised seven special defenses to each count.

After the pleadings were closed, the plaintiffs filed a motion for summary judgment on the complaint, supported by four affidavits, a deposition and answers to interrogatories. In opposition, the defendants offered three counter affidavits and two depositions.

The trial court granted the plaintiffs’ motion for summary judgment and, in response to the defendants’ motion for articulation, clarified that it had also granted summary judgment for the plaintiffs on the counterclaim. This appeal followed.

I

The defendants’ first four claims, taken together, contend that the trial court improperly granted the plaintiffs’ motion for summary judgment on the complaint because there were material factual issues to be determined.

Practice Book § 384 provides that summary judgment “shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of [495]*495law.” Further, “[tjhe party seeking summary judgment bears the burden of showing the nonexistence of any material fact, which is any fact that will make a difference in the result of a case.” Bassin v. Stamford, 26 Conn. App. 534, 537, 602 A.2d 1044 (1992).

“Although the party seeking summary judgment has the burden of showing the nonexistence of any material fact ... a party opposing summary judgment must substantiate its adverse claim by showing that there is a genuine issue of material fact together with the evidence disclosing the existence of such an issue.” (Citations omitted; internal quotation marks omitted.) Connell v. Colwell, 214 Conn. 242, 246, 571 A.2d 116 (1990). It is axiomatic that “[i]n order to oppose successfully a motion for summary judgment, the opposing party must recite facts . . . which contradict those offered by the moving party.” (Internal quotation marks omitted.) Citizens National Bank v. Hubney, 182 Conn. 310, 312, 438 A.2d 430 (1980). “In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the non-moving party.” Connell v. Colwell, supra, 246-47. Moreover, “[i]n ruling on a motion for summary judgment, the court’s function is not to decide issues of material fact, but rather to determine whether any such issues exist.” Lomangino v. LaChance Farms, Inc., 17 Conn. App. 436, 438, 553 A.2d 197 (1989).

Among the issues claimed to require a factual determination is the question of whether the contract had been substantially performed on December 29, 1989, the date on which the plaintiffs terminated the contract.

The parties generally agree on the status of the house on the morning of December 29,1989. When the mortgage lender’s inspector arrived that morning, there were no contractors on the site. The house still lacked several items including a sewage-waste permit, a rail[496]*496ing on the front porch, a completed garage floor, floor coverings, and bathroom fixtures. The defendants claim, however, that the inspection was conducted before the agreed upon time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Cleaning & Restoration, LLC v. Koskerides
234 Conn. App. 401 (Connecticut Appellate Court, 2025)
Nationstar Mortgage, LLC v. Mollo
185 A.3d 643 (Connecticut Appellate Court, 2018)
Bomberov. Bombero
Connecticut Appellate Court, 2015
Dubaldo Electric, LLC v. Montagno Construction, Inc.
988 A.2d 351 (Connecticut Appellate Court, 2010)
Petitte v. DSL. Net, Inc.
925 A.2d 457 (Connecticut Appellate Court, 2007)
Pettit v. HAMPTON AND BEECH, INC.
922 A.2d 300 (Connecticut Appellate Court, 2007)
Bank of New York v. Conway
916 A.2d 130 (Connecticut Superior Court, 2006)
Santone v. Liberty Mutual Ins. Co., No. Cv 98 0354105 (Mar. 18, 2003)
2003 Conn. Super. Ct. 3783 (Connecticut Superior Court, 2003)
Town of Columbia v. J.S. Nasin Company, No. Cv-01-0074739-S (Mar. 26, 2002)
2002 Conn. Super. Ct. 3758 (Connecticut Superior Court, 2002)
Pisani Construction, Inc. v. Krueger
791 A.2d 634 (Connecticut Appellate Court, 2002)
Nesbitt v. Satti, No. 547261 (Sep. 27, 2001)
2001 Conn. Super. Ct. 13468-ep (Connecticut Superior Court, 2001)
All-Star Storage-Derby v. James Contract, No. Cv 01 0084961s (Sep. 18, 2001)
2001 Conn. Super. Ct. 13468-cr (Connecticut Superior Court, 2001)
Jaser v. Fischer
783 A.2d 28 (Connecticut Appellate Court, 2001)
Krevis v. City of Bridgeport
779 A.2d 838 (Connecticut Appellate Court, 2001)
Carmel Homes, Inc. v. Bednar, No. Cv 99-0079393 S (Mar. 26, 2001)
2001 Conn. Super. Ct. 4317 (Connecticut Superior Court, 2001)
Federal Natl. Mortgage Assn. v. Jessup, No. Cv98 0169417 S (Dec. 8, 2000)
2000 Conn. Super. Ct. 15343 (Connecticut Superior Court, 2000)
Riverbend Exec. Ctr. v. Modern Telecomm., No. Cv97 0157888 S (Jun. 1, 2000)
2000 Conn. Super. Ct. 6707 (Connecticut Superior Court, 2000)
Difronzo v. Krane, No. Cv98-0489078s (May 18, 2000)
2000 Conn. Super. Ct. 6572 (Connecticut Superior Court, 2000)
Langner v. the Stop Shop Supermarket, No. Cv. 95 0377385 (Jan. 27, 2000)
2000 Conn. Super. Ct. 1276 (Connecticut Superior Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
613 A.2d 292, 28 Conn. App. 491, 1992 Conn. App. LEXIS 307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-bourgoin-connappct-1992.