Fullerton v. McGowan

507 A.2d 473, 6 Conn. App. 624, 1986 Conn. App. LEXIS 903
CourtConnecticut Appellate Court
DecidedApril 1, 1986
Docket3040
StatusPublished
Cited by12 cases

This text of 507 A.2d 473 (Fullerton v. McGowan) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fullerton v. McGowan, 507 A.2d 473, 6 Conn. App. 624, 1986 Conn. App. LEXIS 903 (Colo. Ct. App. 1986).

Opinion

Bieluch, J.

The defendant has appealed from a judgment for the plaintiffs in an action on a contract for [625]*625the purchase and sale of land with a house then under construction thereon in Newtown. The pro se defendant, who was the owner and builder of the house, has raised four claims of error with regard to the court’s findings and award of damages.1 We find no error.

The facts are not in dispute. The plaintiffs contracted on August 23,1978, to purchase the property in question from the defendant for $108,000. This purchase price reflected an agreement between the parties pursuant to which the plaintiffs undertook to perform some of the work on the house themselves. During the negotiations prior to the written agreement, the defendant orally indicated that the house would be ready for occupancy on or about October 15, 1978, but this was extended to October 30, 1978, or “such other date ... as the parties may mutually agree upon” in the written contract.

Prior to October 30, 1978, the plaintiff Robert G. Fullerton visited the property often, on some of these occasions doing some of the construction work which he had agreed to do in reduction of the purchase price. On that date, Fullerton visited the property again and observed that the interior walls, the septic system, the driveway and the front steps had not been completed, and that the plumbing and kitchen fixtures, the heating unit and the oil tank had not been installed. Also, the electricity had not been connected. For these reasons, the defendant could not provide the plaintiffs with a certificate of occupancy, and the closing was therefore delayed. The defendant then informed the plaintiffs that he would complete the house before Thanksgiving. Fullerton, who had previously been in the real estate business, did not object to the delay, nor to a [626]*626later extension of time to “before Christmas.” The plaintiffs did, however, inform the defendant that they had sold their existing home with an agreed closing date of December 20,1978, by which time they were to surrender possession without delay.

The sale of the plaintiffs’ former home took place as scheduled and, on December 20, 1978, they rented a bungalow for their interim occupancy at a rental of $50 per week. Three days later, a physical altercation occurred between Fullerton and the defendant as a result of their differences. After this flare-up, Fullerton was denied access to the premises to complete any of the work required of the buyers. He did, however, visit the premises several times to conduct settlement negotiations. A closing date of January 20, 1979, was requested by the plaintiffs. Fullerton informed the defendant that, otherwise, a suit for specific performance would be instituted. The defendant, in reply, imposed three conditions for closing on that day: (1) that the plaintiffs relinquish all claims occasioned by the delay in the completion of the house; (2) that the plaintiffs execute a waiver running to the town of Newtown with respect to a fifteen degree grade on portions of the driveway of the residence; and (3) that Fullerton execute a release in favor of the defendant with respect to the assault which had occurred on December 23, 1978. The plaintiffs refused these demands and brought this action for specific performance and damages. Ancillary to their suit, a lis pendens was filed on the land records on February 28,1979. The defendant obtained a conditional certificate of occupancy on March 2, 1979, but the parties were unable to reach an agreement on the closing and a stalemate followed. The defendant filed a counterclaim for damages allegedly caused by the plaintiffs’ failure to close within a reasonable time after March 2, 1979.

[627]*627On December 20, 1979, the Citizens National Bank of Fairfield, a second mortgagee of the defendant, started foreclosure proceedings against the property. The plaintiffs were named defendants in that action because of their lis pendens against the property and a mechanic’s lien filed by Fullerton for materials and labor furnished in the amount of $4724.05. This foreclosure action went to a judgment of strict foreclosure. The plaintiffs exercised their right of redemption on June 10, 1980. Title in fee simple was obtained by payment of $103,524.86 to the prior encumbrancers, including the first mortgagee. To obtain this financing, the plaintiffs borrowed $75,000 from Fullerton’s parents at 10 percent interest.

In their purchase contract, the plaintiffs had agreed to apply for a mortgage loan at the Newtown Savings Bank, the defendant’s first mortgagee. This bank gave the plaintiffs a commitment for a mortgage loan of $75,000 for thirty years at 9% percent interest. The commitment was extended to January 3,1979, but can-celled on that date. Upon the plaintiffs’ redemption of the property seventeen months later, the bank had increased its rate to 14 percent, four percentage points higher than the interest rate charged by the parents. After taking possession of the premises, the plaintiffs incurred further expenditures to correct defects and to complete the work of the defendant on the house. Thereafter, on March 12,1981, the plaintiffs amended their complaint in this action by adding a second count alleging damages consequential to their obtaining title to the premises by redemption in the foreclosure proceeding.

The trial court concluded that time was not of the essence under the contract between the parties. It found that the agreement neither expressed nor implied such an intention in its terms. When the closing did not take place on October 30,1978, as specified in the [628]*628agreement, the court held that the plaintiffs were under a duty to extend for a reasonable period the defendant’s time for completion of the house. The defendant knew that the plaintiffs had sold their former home with possession and occupancy to be delivered by them on December 20, 1978. The court found, therefore, that a closing on that date would have given the defendant a reasonable further time of almost two months for performance of the agreement. Consequently, it measured the plaintiffs’ damages from that date and awarded them judgment in the amount of $22,740.30. Damages were computed as follows:

Cost of property redemption $103,524.86
Counsel fees for property redemption 2,174.36
Correction and completion of defendant’s work 9,069.48
Deposit paid to defendant 11,000.00
Total cost of property $125,768.70
Contract price 108,000.00
Increased cost to plaintiffs $17,768.70
Additional mortgage interest of Vi percent for thirty years discounted 4,971.60
Total damages $22,740.30

Judgment was also rendered for the plaintiffs on the defendant’s counterclaim.

The defendant’s first claim is that the court erred in finding that the defendant breached the contract. This court disagrees with that claim. It is the contention of the defendant that since the closing date had passed, the plaintiffs waived their right to performance on October 30,1978, by working on the premises during November and December, 1978.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corman v. Russo, No. Cv99 0066474s (Jan. 11, 2002)
2002 Conn. Super. Ct. 502 (Connecticut Superior Court, 2002)
Bethlehem Christian Fellowship, Inc. v. Planning & Zoning Commission
755 A.2d 249 (Connecticut Appellate Court, 2000)
Citino v. Hartford Redevelopment Agency, No. Cv 95 0545209s (Jan. 30, 1997)
1997 Conn. Super. Ct. 306 (Connecticut Superior Court, 1997)
Atlantic Pipe Corp. v. Quadrangle Ltd., No. Cv 87-0336982 (Oct. 28, 1993)
1993 Conn. Super. Ct. 9165 (Connecticut Superior Court, 1993)
Federal Deposit Ins. Corp. v. Blonder, No. Cv 90 44764 S (Apr. 30, 1993)
1993 Conn. Super. Ct. 4270 (Connecticut Superior Court, 1993)
Miller v. Bourgoin
613 A.2d 292 (Connecticut Appellate Court, 1992)
Dove Brothers, Inc. v. Horn, No. 0052677 (May 14, 1992)
1992 Conn. Super. Ct. 4359 (Connecticut Superior Court, 1992)
Dinehart v. Berube, No. 29 01 48 (Apr. 25, 1991)
1991 Conn. Super. Ct. 3404 (Connecticut Superior Court, 1991)
Epstein v. Carrier
533 A.2d 1221 (Connecticut Appellate Court, 1987)
Morning Star Holding Co. v. Kostopoulos
533 A.2d 569 (Connecticut Appellate Court, 1987)
Maretz-Franford, Inc. v. Kramer
508 A.2d 35 (Connecticut Appellate Court, 1986)
Bartsch v. Planning & Zoning Commission
506 A.2d 1093 (Connecticut Appellate Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
507 A.2d 473, 6 Conn. App. 624, 1986 Conn. App. LEXIS 903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fullerton-v-mcgowan-connappct-1986.