Dove Brothers, Inc. v. Horn, No. 0052677 (May 14, 1992)

1992 Conn. Super. Ct. 4359
CourtConnecticut Superior Court
DecidedMay 14, 1992
DocketNo. 0052677
StatusUnpublished

This text of 1992 Conn. Super. Ct. 4359 (Dove Brothers, Inc. v. Horn, No. 0052677 (May 14, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dove Brothers, Inc. v. Horn, No. 0052677 (May 14, 1992), 1992 Conn. Super. Ct. 4359 (Colo. Ct. App. 1992).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This is an action for breach of contract brought by the plaintiff, Dove Brothers, Inc., against the defendants, Wayne and Dale Horn. The plaintiff has been involved in the business of CT Page 4360 erecting pre-engineered steel buildings in the Litchfield County area. The matter was originally brought to this court on a motion to dissolve a mechanic's lien, Horn v. Dove Brothers, Inc., DN CV 90-0052210S, whereupon the court ordered the pleadings to be expeditiously closed, and a hearing held on the merits. This instant contract action was returnable March 27, 1990, was assigned for trial on April 17, 1990, and said trial was completed on April 25, 1990. At said trial this court found the following.

On April 18, 1989, the plaintiff and the defendants entered into a contract ("the Contract") for the construction of a pre-engineered steel building ("the building") for an agreed upon price of $51,226.00. Plaintiff's Exhibit 1 (the Contract). A building permit was acquired on April 26, 1988, and the plaintiff claims that said permit would expire on April 25, 1989 if work on the building had not yet begun. Plaintiff's Exhibit 5 (Building permit). Therefore, the plaintiff claimed, the defendants requested that it proceed with the foundation even though it had not yet received the "anchor bolt" drawings from the manufacturer. The drawings were apparently required so that appropriate footings for steel beams would be properly located and distanced.

Subsequent to a delay allegedly at the defendants' request due to lack of funds, the plaintiff ordered the steel span building from the manufacturer, completed part of the metal structure, and was, thereafter, on October 2, 1989, terminated from the job. The plaintiff claims that its loss of profits after having been precluded by the defendants from completing the work and the value of work and materials provided prior to its termination, constitute damages pursuant to a claim for breach of contract. The plaintiff also seeks compensatory and punitive damages for the defendants' conversion of its tools for a period of time during which the defendants refused to return said tools and refused to permit the plaintiff onto the building's premises to recover the same.

The defendants claim that they first terminated the contract on or about May 30, 1989, due to dissatisfaction with the progress of the contract work, but reaffirmed that contract with the understanding that the building would be "substantially completed" by October 1, 1989. Plaintiff's Exhibit 10 (June 4, 1989, Letter from the defendants to the plaintiff). The defendants finally terminated the contract on October 2, 1989, and completed the contract work with another builder at an additional cost of $14,520.50. Defendant's Exhibit 11 (Copies of expenses incurred in completing the building). Subsequently, on December 27, 1989, the plaintiff filed a mechanic's lien in the amount of $15,000.00 for the value of the unpaid materials and services provided pursuant to the contract, as well as for the value of its tools. Consequently, the defendants were compelled to seek to discharge the same. CT Page 4361

During the course of the trial, both parties introduced testimony to support their respective claims. The defendants offered the testimony of Mr. Peter Bujnowski, who attempted to illustrate construction errors committed by the plaintiff. Indeed, Mr. Bujnowski testified that the plaintiff: improperly installed the northwestern corner of the building in a position where the building did not properly fit on the foundation; allowed the metal sheeting for the exterior of the building to lie on the ground for almost one month, thereby resulting in the formation of rust on said sheeting; improperly installed piers, resulting in plates overlapping said piers, necessitating additional work; and caused burn holes in the aforementioned plates. Mr. Bujnowski further testified that, because of the aforesaid errors, the value of the building, as constructed, was between $5,000.00 and $10,000.00 less than said building would have been had it been properly constructed. Testimony of Peter Bujnowski; Defendants' Exhibit 13 (Report of Peter Bujnowski).

Mr. Bujnowski testified that an additional expenditure of $523.80 was required to jack up piers for a lean-to, resulting in the defendant paying a total of $50,028.80 to complete the building. Said cost is $1,198.00 less than the contract price of $51,226.00. However, in light of Mr. Bujnowski's testimony that the building is worth between $5,000.00 and $10,000.00 less than it would have been had it been properly constructed, the defendants contend that the building is, at a minimum, worth $46,226.00, resulting in a loss to the defendants of $3,802.80. Defendants' Exhibit 13.

More compelling to this court was the testimony of Mr. Edward Vanderhoef, a professional engineer who testified as the plaintiff's expert. Mr. Vanderhoef testified that the overall construction quality of the building is probably slightly better than average and, indeed, "was in pretty good shape." Testimony of Edward Vanderhoef; Plaintiff's Exhibit 29 (Report of Edward Vanderhoef). Mr. Vanderhoef testified that the building had a construction value of approximately $114,500.00 and, although he could not break down that value, said value was representative of the final project. Mr. Vanderhoef testified that he did not examine the building during the construction. Testimony of Edward Vanderhoef.

Mr. Vanderhoef also stated that most of the field conditions described by Mr. Bujnowski were either aesthetic in nature and, therefore, easily remedied, or not a field condition at all. Plaintiff's Exhibit 29. Mr. Vanderhoef's report coincides with the testimony of Mr. Bujnowski in that both agree that the wall does not line up with the steel wall framing. However, such condition appears to have been remedied by moving the framing inward approximately 3.25 inches via the use of existing bolts holes in CT Page 4362 affected framing. Plaintiff's Exhibit 29.

There was testimony to the effect that lean-to piers were intentionally constructed so that columns did not rest on the center of the piers. The plaintiff elicited testimony from Mr. Vanderhoef that such positioning would make it easier to enclose the lean-to, if the defendants so desired. Contrary to the defendants' expert, Mr. Vanderhoef's report indicates that this is a common practice. Plaintiff's Exhibit 29.

Mr. Vanderhoef stated, inter alia, that, contrary to the defendants' contention, there were only two small areas of fine surface rust. Plaintiff's Exhibit 29. Mr. Vanderhoef stated in his report that "[t]he dust was easily removed with a vigorous rubbing of the surface. The paint and the underlying galvanized surface does not appear to have been penetrated by the rust and is probably not the cause of the rust . . . Scrubbing the walls with a stiff brush would probably permanently remove the rust." Plaintiff's Exhibit 29.

The testimony proffered by experts for both the plaintiff and the defendants lead this court to conclude that the construction of the building, while not perfect, was, in the words of Mr. Vanderhoef, slightly better than average.

Pursuant to evidence provided at trial, it appears to this court that the plaintiff and the defendants entered into the Contract whereby the plaintiff would construct the building for a price of $51,226.00 "A.S.A.P." Contract, Article 2, 2.1. Time "[was] of the essence of the Contract." Contract, Article 14, 14.1. The Contract also provided, inter alia, that the defendants could withhold payments "on account of . . . (6) reasonable evidence that the work will not be completed within the Contract Time." Contract, Article 15, 15.1(6).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H & S TORRINGTON ASSOCIATES v. Lutz Engineering Co.
441 A.2d 171 (Supreme Court of Connecticut, 1981)
Henry F. Raab Connecticut, Inc. v. J. W. Fisher Co.
438 A.2d 834 (Supreme Court of Connecticut, 1981)
Guilford Yacht Club Ass'n v. Northeast Dredging, Inc.
468 A.2d 1235 (Supreme Court of Connecticut, 1984)
J. C. Penney Properties, Inc. v. Peter M. Santella Co.
555 A.2d 990 (Supreme Court of Connecticut, 1989)
Fullerton v. McGowan
507 A.2d 473 (Connecticut Appellate Court, 1986)
Newtown Associates v. Northeast Structures, Inc.
546 A.2d 310 (Connecticut Appellate Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 4359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dove-brothers-inc-v-horn-no-0052677-may-14-1992-connsuperct-1992.