Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates

717 A.2d 294, 50 Conn. App. 289, 1998 Conn. App. LEXIS 381
CourtConnecticut Appellate Court
DecidedSeptember 8, 1998
DocketAC 17379
StatusPublished
Cited by14 cases

This text of 717 A.2d 294 (Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates, 717 A.2d 294, 50 Conn. App. 289, 1998 Conn. App. LEXIS 381 (Colo. Ct. App. 1998).

Opinion

[290]*290 Opinion

SCHALLER, J.

The plaintiff, Anthony Julian Railroad Construction Company, Inc., appeals from the trial court’s refusal to issue a property execution, pursuant to General Statutes § 52-356a,1 for the claimed unsatisfied portion of a mechanic’s lien foreclosure judgment. On appeal, the plaintiff claims that the trial court abused its discretion by failing to issue the property execution for which the plaintiff properly applied. We affirm the judgment of the trial court.

The following relevant facts are recited in our decision in Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates, 39 Conn. App. 544, 664 A.2d 1177, cert. denied, 235 Conn. 930, 667 A.2d 800 (1995). “On December 28,1987, the plaintiff, a construction company, entered into contracts with [Patrick R.] Pacelli and three others who were principals in Mary Ellen Drive Associates and T.K.P. Associates, two general partnerships. The contract was for site development of a residential subdivision known as Nicole Estates in Milford. The plaintiff contracted to build the roadways for the subdivision. On March 23, 1988, the plaintiff and the defendants signed a waiver of mechanic’s lien related to the subdivision. On April 1,1988, the plaintiff commenced work. The plaintiff stopped work [291]*291on March 2, 1989, due to nonpayment.2 At this time, there remained an estimated $150,000 of work left to complete the job. On April 26, 1989, the plaintiff filed a mechanic’s lien in the amount of $400,164.3 The plaintiff subsequently returned to the site to perform additional work and services.

“On September 13, 1989, the plaintiff commenced this action against several defendants4 seeking to foreclose the mechanic’s lien in the original principal amount of $400,164. The complaint, and each of the amended complaints as filed,5 alleged work performed after the date of the filing of the lien.6 The prayer for relief claimed money damages.7 The case was tried [292]*292before a state trial referee on December 2 and 3, 1992. The first issue presented to the court was whether the plaintiff, by executing the March 23, 1988 lien waiver, had waived its right to file and foreclose the mechanic’s lien. The court held that there was no waiver of the hen by the plaintiff. The court then analyzed whether the plaintiffs hen had priority over competing claims by the defendant UST Bank/Connecticut [UST Bank], a bank that held a mortgage on the property. The court held that the plaintiffs hen did have priority over the mortgage of [UST Bank]. The court found for the plaintiff in the amount of $315,1648 for work done prior to the filing of the hen and $87,441.42 for work performed after the filing of the hen. On January 3, 1994, the trial court rendered a judgment of strict foreclosure in favor of the plaintiff.” Id., 545-46.

The trial court found the fair market value of the property to be $825,000 and set the first law day at January 25, 1994. Prior to the running of this law day, the defendants UST Bank and Robert D. Scinto filed an appeal challenging the trial court’s determination regarding the priority of the mechanic’s hen. This appeal was docketed as AC 13212. In addition, Pacehi filed an appeal challenging the trial court’s award of damages for work performed after the filing of the mechanic’s hen. This appeal was docketed as AC 13244.

During the pendency of those appeals, the plaintiff negotiated settlements with UST Bank and Scinto that called for the payment of $325,000 to the plaintiff in [293]*293exchange for the release of the mechanic’s lien. The parties to that settlement complied with its terms, and on December 28, 1994, the plaintiff filed a notice of partial satisfaction of judgment with the trial court. Accordingly, the appeal in AC 13212 was withdrawn by UST Bank and Scinto.

We decided the issue that was raised in Pacelli’s appeal (AC 13244) as reported in Anthony Julian Railroad Construction Co. v. Mary Ellen Drive Associates, supra, 39 Conn. App. 544. In that case, we held that the trial court’s award of damages for work performed after the filing of the mechanic’s lien was proper under the mechanic’s lien statute, General Statutes § 49-33. In reaching that conclusion, we relied on the fact that the pleadings properly presented the issue of the recover-ability for work performed after the filing of the lien. Because the pleadings presented only the statutory remedy of a mechanic’s lien, we concluded that the trial court’s award was proper.

Following our decision in that case, no further action was taken in the foreclosure proceeding. The plaintiff did not file a motion for the trial court to open the foreclosure judgment to set new law days and, as a result, the foreclosure action remained dormant. On March 19, 1997, however, the plaintiff applied for a property execution. The trial court denied the application and this appeal followed.

I

The plaintiff first claims that the trial court improperly conducted a hearing on its application for a property execution because under § 52-356a, issuance of such an execution is purely a ministerial act by the court clerk once the clerk is presented with a properly executed application with respect to a valid judgment that remains unsatisfied. We are not persuaded.

[294]*294As a preliminary matter, we note that the plaintiff, in its brief, has essentially abandoned this claim. The plaintiff states that “[i]t must be conceded that the trial court does have supervisory control over the process of an execution.” We are in complete agreement with the plaintiffs statement of the law. See generally Gainty v. Russell, 40 Conn. 450, 450-51 (1873); Gager v. Watson, 11 Conn. 168, 171 (1836).

Moreover, we analogize the trial court’s action in holding a hearing on the propriety of the issuance of an execution in this case to the common law writ of audita querela. “The ancient writ of audita querela has been defined as a writ issued to afford a remedy to a defendant against whom judgment had been rendered, but who had new matter in defense (e.g., a release) arising, or at least raisable for the first time, after judgment. . . . Because the writ impairs the finality of judgments, the common law precluded its use in cases in which the judgment debtor sought to rely on a defense such as payment or a release that he had the opportunity to raise before the entry of judgment against him. . . . No authority has been cited to suggest that the writ of audita querela was ever available to present issues which were presented before the entry of the judgment attacked by the writ. . . . The writ of audita querela provides relief from a judgment at law because of events occurring subsequently which should cause discharge of a judgment debtor.” (Citations omitted; internal quotation marks omitted.) Ames v. Sears, Roebuck & Co., 206 Conn. 16, 20-21, 536 A.2d 563 (1988).

This case provides an appropriate context for the application of this common law writ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Alegrand
23 A.3d 1250 (Connecticut Appellate Court, 2011)
Dreambuilders Construction, Inc. v. Diamond
997 A.2d 553 (Connecticut Appellate Court, 2010)
Airtech of Stamford v. 50 Washington Str., No. Cv 98 0166513 (Nov. 4, 2002)
2002 Conn. Super. Ct. 14139 (Connecticut Superior Court, 2002)
Waldo v. Ohno, No. Cv 01-0451985 S (Sep. 6, 2002)
2002 Conn. Super. Ct. 11297 (Connecticut Superior Court, 2002)
Homeside Lending, Inc. v. Negron, No. Cv 99 0169795 S (Jan. 3, 2002)
2002 Conn. Super. Ct. 151 (Connecticut Superior Court, 2002)
Boris Corporation v. Plane Broker, Inc., No. Cv00-0162236s (Feb. 27, 2001)
2001 Conn. Super. Ct. 3045 (Connecticut Superior Court, 2001)
Connecticut Concrete v. Arc Icesports, No. X01 Cv 00-0160662s (Feb. 8, 2001)
2001 Conn. Super. Ct. 2187 (Connecticut Superior Court, 2001)
Cadle Co. v. Glen Developers, Inc., No. Cv 92 0341912 S (Nov. 22, 2000)
2000 Conn. Super. Ct. 14416 (Connecticut Superior Court, 2000)
Citizens Savings Bank v. Rohlman, No. Cv00-0434257 (Jul. 24, 2000)
2000 Conn. Super. Ct. 8981 (Connecticut Superior Court, 2000)
Steeltech Building Products v. Viola, No. Cv 98 0580266 S (May 15, 2000)
2000 Conn. Super. Ct. 5953 (Connecticut Superior Court, 2000)
Washington Mutual Bank v. Turner, No. Cv98 0263975 (Jul. 19, 1999)
1999 Conn. Super. Ct. 9424 (Connecticut Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
717 A.2d 294, 50 Conn. App. 289, 1998 Conn. App. LEXIS 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-julian-railroad-construction-co-v-mary-ellen-drive-associates-connappct-1998.