Coastal Plumbing-Heating v. Habetz, No. Cv90-030922 (Aug. 28, 1991)

1991 Conn. Super. Ct. 7116, 6 Conn. Super. Ct. 861
CourtConnecticut Superior Court
DecidedAugust 28, 1991
DocketNo. CV90-030922
StatusUnpublished

This text of 1991 Conn. Super. Ct. 7116 (Coastal Plumbing-Heating v. Habetz, No. Cv90-030922 (Aug. 28, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastal Plumbing-Heating v. Habetz, No. Cv90-030922 (Aug. 28, 1991), 1991 Conn. Super. Ct. 7116, 6 Conn. Super. Ct. 861 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This is an action to foreclose a mechanic's lien on property owned by the defendants Peter Habetz Jr. and Joyce Mihalko. The plaintiff Coastal Plumbing-Heating, Inc. (Coastal) was hired by the defendant Ken Condon, d/b/a Ken Condon Contracting (Condon) in April 1989 as a subcontractor for plumbing and heating work and improvements required to complete an addition on a house at 634 Arrowhead Drive in Orange, which was the property owned by the defendants Habetz and Mihalko. There was a written contract between Coastal and Condon dated April 27, 1989 for $8,551. covering the work to be performed by Coastal on the subject property. The contract price was $8,551, with $4,174 to be paid when the rough plumbing was installed, $3,517 when the heating was installed and the balance of $860 after the plumbing fixtures were delivered and installed. Only the first payment was made, and Coastal was owed $4,377 under the original contract. Coastal also performed additional plumbing work on June 9, 1989 which was billed at $42.20. While the construction of the addition was in progress, Condon requested Coastal to perform additional heating and plumbing work which was needed to complete the addition, and which was finished on August 7, 1989 and billed at $860.32. On August 30, 1989 Coastal returned to the job site to repair some bent heating lines at a cost of $74.66. All of this work was requested by Condon, and all of the charges for labor and materials are fair and reasonable for the services rendered by Coastal. Habetz requested Coastal to fix the boiler in August. Coastal replaced the extrol tank and relief valve on the boiler on August 30, 1989, and billed Habetz directly for that amount. The total amount of unpaid charges for services requested by Condon is $5,354.18. The total amount owed to Coastal, which includes the work requested directly by Habetz is $5552.65, and Coastal claims a mechanic's lien in that amount. CT Page 7117

The right to file a mechanic's lien is controlled by statute, and although a statutory lien is in derogation of the common law, its remedial purpose is to furnish security for a contractor's labor and materials, so the statutes are liberally construed. Seaman v. Climate Control Corporation, 181 Conn. 592, 597. "Those who provide services or materials in connection with the construction of a building are entitled to claim a lien on the land they have improved if they fall into one of two categories. Lienors are protected if they have a claim either (1) by virtue of an agreement with or the consent of the owner, or (2) by the consent of some person having authority from or rightfully acting for such owner in procuring labor or materials." Hall v. Peacock Fixture Electric Co., 193 Conn. 290, 293; Newtown Associates v. Northeast Structures, Inc., 15 Conn. App. 633, 637; 49-33 (a) C.G.S. Condon had a contract with Habetz to build the addition, and while the job was in progress they agreed to additional work to be performed by Condon. The heating and plumbing services of Coastal were furnished with the consent of Condon as general contractor and under the contractual authorization by Habetz to construct the addition. The contract between Condon and Habetz was for $103,000 not including extras. Habetz paid $93,000 on the contract but has not paid for the extras, and has made a claim against Condon for defective labor and materials, although the plumbing and heating work performed by Coastal is not part of that claim. Since Habetz has not paid Condon the agreed contract price of $103,000, or for the extras, Coastal's claim cannot be defeated on that basis. See 49-33 (f) C.G.S.

The mechanic's lien was recorded in the Town Clerk's Office on November 22, 1989, and Notice of Intent to claim a lien and the mechanic's lien was served on the defendants Habetz and Mihalko as the property owners on November 27, 1989. Those defendants claim that the lien was not filed within 90 days after Coastal finished the work on the subject property as required by 49-34 of the General Statutes. The form and content of the lien and the other procedures required by 49-34 have not been questioned by the defendants and are not involved in this appeal. The Court disregards a claim based on paragraph 5 of the complaint, that the last work performed by Coastal on the property was April 30, 1989. That paragraph has not been admitted by the defendants and is clearly a typographical error, as both paragraph 4 of the complaint and testimony at the trial by Coastal and Habetz show that the last date Coastal furnished materials and services was on August 30, 1989 when it repaired the broken heating line for Condon and made the boiler repairs requested by Habetz. Condon does not contest the lien. Habetz and Mihalko make two related claims: (1) the work was completed and billed on August 2, 1989, so that the lien is invalid because it was not served on the defendants November 27, 1989, which was more than 90 days after Coastal completed work on the subject property; (2) the additional work performed on August 30, 1989 was independent work done for Habetz and was insubstantial and CT Page 7118 cannot be considered in deciding whether the lien was filed within the 90 day time limit in 49-34 of the General Statutes.

The work performed by Coastal under the original contract concluded on August 2, 1989, and most of the additional services requested by Condon and billed as extras were completed by August 7, 1989. If Coastal's claim were based solely on those services the lien would be invalid since it was filed more than 90 days after August 7, 1989. Booth v. Von Beren, 82 Conn. 298, 306; Flint v. Raymond, 41 Conn. 510, 514. However, on August 30, 1989 Coastal was called back to the property by the same general contractor, Condon, to repair broken heating lines. On the same day, at the request of Habetz, Coastal made the minor repairs on the boiler. The lien was filed within 90 days from August 30, 1989, and is valid if the additional work on August 30, 1989 extended the time limit for filing it.

The general rule on this subject is stated in Martin Tire Rubber Co. v. Kelly Tire Rubber Co., 99 Conn. 396, 399-401, which summarizes earlier Connecticut cases on the subject. The period for filing the lien is ordinarily computed from the date of the last item of material furnished or services rendered. If, after the work is substantially done, the claimant for the material furnished or services rendered unreasonably delays the completion of the work, the date of beginning of the time limit is the date when the work is substantially done. "No trivial or inconsequential service or work done after the substantial completion of the building will extend the time for claiming the lien, or revive an expired lien when an unreasonable period has elapsed since the substantial completion. If the article furnished or the service rendered be trivial, but be required by the contract of building, this fact will be taken into consideration in determining whether the elapsed period be unreasonable or not.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bertozzi v. McCarthy
323 A.2d 553 (Supreme Court of Connecticut, 1973)
The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
Booth v. Vonberen
73 A. 775 (Supreme Court of Connecticut, 1909)
Peck v. Brush
98 A. 561 (Supreme Court of Connecticut, 1916)
Flint v. Raymond
41 Conn. 510 (Supreme Court of Connecticut, 1874)
Sanford v. Frost
41 Conn. 617 (Supreme Court of Connecticut, 1874)
Nichols v. Culver
51 Conn. 177 (Supreme Court of Connecticut, 1883)
Cooley v. Holcomb
35 A. 765 (Supreme Court of Connecticut, 1896)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Hall v. Peacock Fixture & Electric Co.
475 A.2d 1100 (Supreme Court of Connecticut, 1984)
Newtown Associates v. Northeast Structures, Inc.
546 A.2d 310 (Connecticut Appellate Court, 1988)
Backros, Inc. v. Davies
199 A.2d 349 (Connecticut Appellate Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 7116, 6 Conn. Super. Ct. 861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastal-plumbing-heating-v-habetz-no-cv90-030922-aug-28-1991-connsuperct-1991.