Brewer Construction v. Fg Assoc., No. Cv92 050 78 85 (Jun. 21, 1993)

1993 Conn. Super. Ct. 6077
CourtConnecticut Superior Court
DecidedJune 21, 1993
DocketNo. CV92 050 78 85
StatusUnpublished

This text of 1993 Conn. Super. Ct. 6077 (Brewer Construction v. Fg Assoc., No. Cv92 050 78 85 (Jun. 21, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brewer Construction v. Fg Assoc., No. Cv92 050 78 85 (Jun. 21, 1993), 1993 Conn. Super. Ct. 6077 (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The plaintiff in this case, T.P. Brewer Construction Company, Inc., was at all times pertinent to this case a Connecticut corporation doing business in Connecticut. The President of this corporation was Terrence P. Brewer. Terrence P. Brewer and J. Scott Guilmartin, each owned 50% of the stock of said corporation. The named defendants in this case are FG Associates, a general partnership and Phillip Fine, individually, Morton Fine, individually and J. Scott Guilmartin, individually. The general partners of FG Associates were Phillip Fine and Morton Fine each owning 25% and the J. Scott Corporation owning 50%. The principal stockholders of J. Scott Corporation were J. Scott Guilmartin and Terrence Brewer each owning 50% of the stock in said corporation. Terrence Brewer was the President of J. Scott Corporation.

FG Associates were the owners of a certain piece or parcel of land located in East Granby, Connecticut on which it was to develop an office park financed by a mortgage from Connecticut Bank and Trust Co. The name of the office park was Creamery Brook Office Park.

On or about September 20, 1988, T.P. Brewer Construction Co., Inc., entered into an agreement with Phillip Fine, Morton Fine and J. Scott Guilmartin, i.e., two of the partners of FG Associates and a co-owner of the third partner who was active in the financial affairs of FG Associates, whereby T.P. Brewer Construction, Inc., agreed to perform site work for Creamery Brook Office Park in accordance with certain plans submitted by the parties and the defendants agreed to pay Brewer Construction CT Page 6078 Co. Inc., the sum of $420,957.00 for the performance of the contract. The plaintiff proceeded to perform its obligations under the contract completing a large portion of the work contracted for, but was forced to cease any further work in December of 1989 at which time it prepared the project for winter and suspended its operations. Plaintiff had determined that the bank was about to foreclose on the property and the defendants had run out of money with which to pay under the contract. All parties agreed that in addition to the work authorized in the original contract, the plaintiff, with the permission of the defendants, performed $29,874.58. worth of extra work. Much of this had to do with additional requirements with respect to pipes under Route 20, the highway adjoining the property.

Once a month the plaintiff would submit to the bank for its examination a computer printout showing the amount of work which had been completed up to date and the amount due on same. This would be examined also by the defendants and the bank would then furnish the defendants with a check in the appropriate amount which would then be paid to plaintiff. In this manner plaintiff received $300,997.00 out of the contracted amount of $420,957.00. The last of these requisitions was submitted in November of 1989 which showed approximately $2,500.00 worth of work done for which plaintiff had not been paid. This has never been paid.

The court finds that the amounts submitted on the requisitions were approximations and the figures were arrived at as an accommodation to the defendants in order to have the bank supply them with sufficient money to proceed with the building of the office park. The amounts shown on the requisitions were not accurate.

The court also finds that plaintiff did complete a certain amount of work for which it has not been paid.

After making demand on the defendants this action was brought against them in two counts. The first being in breach of contract and the second in quantum meruit.

In its requisitions the plaintiff showed $11,016.00 worth of work done with respect to certain light poles for which it was paid. The plaintiff agrees that this work was not performed land that the $11,016.00 worth of poles were returned and any CT Page 6079 amount due plaintiff is to be reduced by said amount.

The plaintiff has offered evidence both under the theory of breach of contract and under the theory of quantum meruit. Both parties agree that the correct rule for damages under breach of contract is that outlined in Young vs. Shetucket Coal and Wood Co., 97 Conn. 92 (1921) although the parties differ as to the correct application of the rule. In that case a building contractor did not substantially complete the work for which he contracted and was prevented from doing so by the defendant owner. The court held that the plaintiff was entitled to cease work and sue for damages for breach of contract or for quantum meruit. If the plaintiff chose the breach of contract theory the measure of damages would be "for the work done, such a proportion of the entire price as the fair cost of the work bears to the fair cost of the whole work and in respect to the work not done such profit as he would have realized by doing it."

In the opinion of this court, insufficient evidence was introduced to substantiate recovery by the plaintiff under the theory of breach of contract. Among other things, there was no evidence of loss of profit on the work unfinished and no acknowledgement of this as happened in the case of Wilson vs. Kapetan, Inc., 25 Conn. App. 529, 534.

With respect to Count Two, in which the plaintiff relies upon quantum meruit, Connecticut Case Law holds that a contractor who was prevented by an owner from completing the contract, may treat same as recinded [rescinded]. Valente vs. Weinberg, 80 Conn. 134, (1907). Connelly vs. DeVoe, 37 Conn. 570 (1871), and the contractor may sue upon quantum meruit for the work performed. Young vs. Shetucket Wood and Coal Co., 97 Conn. 92,94 (1921). This is based upon equity not upon the original contract between the parties. Simonetti vs. Lovermi, 15 Conn. App. 722,725-26 (1988). Where the defendants themselves have prevented full performance of the contract "the plaintiff is permitted a recovery for the reasonable value of labor and materials already furnished, without regard to the extent of the benefit conferred upon the other party to the contract." Martin v. Kavanewsky, 157 Conn. 514, 519 (1969). Kearns v. Andree,107 Conn. 181, 186 (1928).

In the opinion of this court, the plaintiff's completion of the project was prevented by the defendants. At that time the CT Page 6080 value of the services rendered by the plaintiff and for which it was uncompensated was $57,707.15 less the sum of $11,016.00 (the value of the returned light poles) plus the sum of $29,874.00 being the value of the extras performed by the plaintiff or a net sum due the plaintiff for which he was uncompensated of $76,565.15. The sum of $57,707.15 is the value in excess of the sum received testified to by Terrence Brewer and appearing on Schedule D.

In the opinion of this court, J. Scott Guilmartin is correctly named as an individual defendant in this case. "[I]t is the duty of an agent to disclose not only the fact that he is acting in a representative capacity, but also the identity of his or her principal if the individual seeks to avoid personal liability in a business transaction." Diamond Match Co. v. Crute, 145 Conn. 277, 279 (1958).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Appleby
438 A.2d 811 (Supreme Court of Connecticut, 1981)
Diamond Match Co. v. Crute
141 A.2d 247 (Supreme Court of Connecticut, 1958)
Alaimo v. Royer
448 A.2d 207 (Supreme Court of Connecticut, 1982)
J. Frederick Scholes Agency v. Mitchell
464 A.2d 795 (Supreme Court of Connecticut, 1983)
Martin v. Kavanewsky
255 A.2d 619 (Supreme Court of Connecticut, 1969)
Kearns v. Andree
139 A. 695 (Supreme Court of Connecticut, 1928)
Young v. Shetucket Coal & Wood Co.
115 A. 672 (Supreme Court of Connecticut, 1921)
Valente v. Weinberg
67 A. 369 (Supreme Court of Connecticut, 1907)
Zolan, Bernstein, Dworken & Klein v. Milone
467 A.2d 938 (Connecticut Appellate Court, 1983)
Connelly v. Devoe
37 Conn. 570 (Supreme Court of Connecticut, 1871)
Sportsmen's Boating Corp. v. Hensley
474 A.2d 780 (Supreme Court of Connecticut, 1984)
Bound Brook Ass'n v. City of Norwalk
504 A.2d 1047 (Supreme Court of Connecticut, 1986)
Simonetti v. Lovermi
546 A.2d 331 (Connecticut Appellate Court, 1988)
Wilson v. Kapetan, Inc.
595 A.2d 369 (Connecticut Appellate Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 6077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brewer-construction-v-fg-assoc-no-cv92-050-78-85-jun-21-1993-connsuperct-1993.