Thornton v. Arlington Independent School District

332 S.W.2d 395, 1960 Tex. App. LEXIS 2002
CourtCourt of Appeals of Texas
DecidedJanuary 29, 1960
Docket16064
StatusPublished
Cited by2 cases

This text of 332 S.W.2d 395 (Thornton v. Arlington Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thornton v. Arlington Independent School District, 332 S.W.2d 395, 1960 Tex. App. LEXIS 2002 (Tex. Ct. App. 1960).

Opinion

BOYD, Justice.

George W. Thornton, doing business as L & M Electric Company, and the Aetna Casualty and Surety Company appeal from a joint and several judgment in favor of Arlington Independent School District.

The School District entered into a contract with Thornton for certain electrical work on its buildings, the total amount of the contract being $26,085.79, and Aetna was the surety on Thornton’s performance bond. The School District alleged that Thornton failed to supply properly skilled workmen and failed to properly prosecute the electrical work in such manner that the work of other contractors could be done without delay, and that upon the approval and certification of the architect the School District terminated Thornton's contract after due notice, and made arrangements with a third party to do the necessary interim work while advertisement for bids could be had and a new contract made for the electrical work; that the interim work amounted to $1,704.09 and the contract for the completion of the electrical work involved an expenditure of $29,546. The School District prayed for judgment in the amount of $5,474.15. The jury found that Thornton failed properly to prosecute the electrical work in such manner that the work of the other contractors could be accomplished without delay. Judgment was rendered for $5,422.50.

Appellants pleaded a general denial and further alleged that Thornton at all times was ready, willing and able to carry out the terms of the contract, and had skilled workmen on the job at all times until he was prevented, through no fault of his own, from performing the work by the refusal of the City of Arlington to grant a temporary permit to carry out the work under *396 the terms of the contract; that the City-Police of the City of Arlington, acting under the direction of the Mayor, the Corporation Court, and the Electrical Examiner of the City, preyented him from carrying out the terms of the contract; that the action of the Police rendered it impossible for Thornton to complete the contract. Appellants filed a cross-action asking for reimbursement for $2,819.33 for labor and materials expended on the job, $260 for premium on its performance bond, $10 for premium on a bond with the City of Arlington, and $3,000 for loss of profits.

Appellants filed a motion for instructed verdict, which was overruled, and that action is assigned as error. Appellants also contend that the evidence was insufficient to support the judgment.

Article 38 of the General Conditions of the Specifications of the Contract, provides as follows: “If the,Contractor should neglect to prosecute the work properly or fail to perform any provision of this Contract, the Owner, after three (3) days’ written notice to the Contractor may, without prejudice to any other remedy that he may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due to the Contractor; provided, however, that the Architect shall approve both such action and the amount charged to the Contractor.”

Article 39 thereof provides, in part, as follows: “If the Contractor * * * persistently or repeatedly refuse or fail to supply enough properly skilled workmen * * * or persistently disregard laws, ordinances * * * or otherwise be guilty of a substantial violation of any provision of the Contract, then the Owner, upon the certificate of the Architect that sufficient cause exists to justify such action, may, without prejudice to any other right of remedy and after giving the Contractor seven (7) days written notice, terminate the employment of the Contractor and take possession of .the premises and of all material, tools and-appliances thereon and finish the work. by whatever method he may deem expedient.”

Article 8 thereof is, in part, as follows: “The Contractor must, at his own cost, obtain all necessary permits * * * and comply with all State and Municipal building and sanitary laws, ordinances and regulations relating to building * *

Article 28 thereof provides that the Contractor shall obtain all licenses and to pay all fees and charges arising out of and in connection with the work.

Article 41 thereof provides that the School District might let other contracts in connection with the work; and that Thornton should properly connect and coordinate his work with the other contractors.

The contract was forwarded to Thornton on December 20, 1956, and was returned executed on January 10, 1957. On January 12, 1957, the architect sent Thornton a “letter of authority” to proceed with the work. Thornton did some work about the middle of January. The architect testified without contradiction that no other work was ever done by Thornton, and that soon after this work was done, he called Thornton by telephone, asking him to “get men on the job,” and on February 1, 1957, he wrote Thornton that electricians would be needed between then and the middle of February, and asked that Thornton advise him immediately what his intentions were concerning the furnishing of qualified electricians to do the work when needed. He got no reply to that letter. On February 8 the architect wrote Thornton that it was his understanding that Thornton had failed to secure permits from the City of Arlington for his men to do the work, and that since the work was urgently needed to be done to avoid delay, the School District would employ an electrician to do the immediate work, as authorized by Article 38 of the General Conditions of the Specifications. On February 12, an arrangement was made with Butcher Electrical Service to do that work. Thornton was not heard from, nor did he, *397 send any men to the job. The architect further testified that Thornton’s men were stopped by the City of Arlington because they were not licensed to do the work.

On February 12, 1957, the President of the School District Board wrote Thornton that the architect had “indicated to us in writing that sufficient cause exists to justify termination” of the contract because of Thornton’s failure to supply enough properly skilled workmen and his failure to prosecute his work in such manner that the other work could go on without delay, and that after repeated requests he had failed to supply any workmen whatsoever, which had delayed the work of the other contracts. On February 28, 1957, the School District entered into a contract with Metcalfe Electric Company to complete the electrical work.

Appellants say that there was no “certificate” by the architect that sufficient cause existed to justify termination of the contract, since the architect, in his letter to the School District Board, only recommended that the Board notify Thornton that his contract would be terminated under provisions of Article 39 of the General Conditions. To show that the architect’s letter did not amount to a “certification,” appellants cite Valente v. Weinberg, 80 Conn. 134, 67 A. 369, 13 L.R.A.,N.S., 448; Oden Const. Co. v. Helton, 218 Miss. 41, 65 So.2d 442; White v. Mitchell, 30 Ind.App. 342, 65 N.E. 1061; Wilson v. Borden, 68 N.J.L. 627, 54 A. 815; Benson v. Miller, 56 Minn. 410, 57 N.W. 943, and other cases.

In our disposition of the appeal we do not determine whether the architect’s letter was a “certification” that sufficient cause existed to terminate the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Security Sewage Equipment Co. v. McFerren
237 N.E.2d 898 (Ohio Supreme Court, 1968)
Security Sewage Equipment Co. v. McFerren
230 N.E.2d 130 (Ohio Court of Appeals, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
332 S.W.2d 395, 1960 Tex. App. LEXIS 2002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thornton-v-arlington-independent-school-district-texapp-1960.