Phoenix Contractors, Inc. v. General Motors Corp.

355 N.W.2d 673, 135 Mich. App. 787
CourtMichigan Court of Appeals
DecidedJune 28, 1984
DocketDocket 70844
StatusPublished
Cited by7 cases

This text of 355 N.W.2d 673 (Phoenix Contractors, Inc. v. General Motors Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phoenix Contractors, Inc. v. General Motors Corp., 355 N.W.2d 673, 135 Mich. App. 787 (Mich. Ct. App. 1984).

Opinion

Per Curiam.

Following a jury trial, plaintiff Phoenix Contractors, Inc., was awarded damages in the amount of $199,084. At trial, plaintiff claimed damages for delay caused by defendant’s interference with a construction project. The alleged interference was defendant’s instruction to one of its subcontractors, Darin & Armstrong, Inc., not to allow other subcontractors to keep Darin & Armstrong from completing its contract on time. Plaintiff contended that Darin & Armstrong kept plaintiff from orderly construction and increased its costs of completion.

The construction project was undertaken by plaintiff pursuant to a written contract for the mechanical trades work in the press building of defendant’s plant. This contract was one of sixteen *790 involved in the expansion of defendant’s Fisher Body Production Plant in Wyoming, Michigan, to facilitate production of defendant’s X-car line.

The contract was awarded in the usual manner. There was a series of bid documents, including a request for quotations, bid forms, drawings and specifications. Defendant’s standard general conditions for all construction contracts, including conditions and addenda for the specific contract, were incorporated by reference in the written contract between the parties. Also included in the contract was a "no damage for delay” clause.

Defendant appeals as of right, and plaintiffs cross-appeal.

Issues

I. Did the "no damage for delay” clause in the contract, as a matter of law, defeat plaintiff’s claim for damages?

We find that the plaintiff was entitled to a jury determination of damages.

II. Did plaintiff waive its cause of action?

We find that a jury question existed as to the waiver claim.

III. Did the trial court commit reversible error in charging the jury with regard to the "no damage for delay” clause?

We do not find reversible error in the charge.

The Exculpatory Clause

Plaintiff’s responsibility under the contract involved installing piping for compressed air, heating and water. Plaintiff was also responsible for installing six heating units on the building roof.

Defendant contracted directly with Darin & *791 Armstrong, Inc., for installation and assembly of presses, and with the floor steel contractor, American Bridge. Defendant also acted as its own job representative and general contractor for the press installation project. This was not a typical arrangement since the general contractor did not have all subcontractors under its control.

Plaintiff got behind on its contract obligation because of delays. Additional man hours attributable to project changes were approved and paid for by defendant. Plaintiff got further behind, however, because it could not work while Darin & Armstrong was installing presses.

It was clear, and everyone in the project recognized, that no change in the completion date of the contract could be made. Plaintiff did complete the job on time, but at substantial additional cost which plaintiff attributes to interference and delay caused by defendant and its subcontractors, particularly Darin & Armstrong.

Defendant contends that the exculpatory "no damage for delay” clause relieves it of responsibility for plaintiff’s claim as a matter of law. At the conclusion of plaintiff’s proofs defendant moved for a directed verdict. Defendant contends that it was error for the trial court to deny a directed verdict.

In deciding whether to grant defendant’s motion for directed verdict, the trial court must view the evidence, and all legitimate inferences that may be drawn therefrom, in a light most favorable to plaintiff. If the evidence, as examined in this manner, establishes a prima facie case the motion should be denied. Vandendries v General Motors Corp, 130 Mich App 195, 198; 343 NW2d 4 (1983). •When a party appeals from a denial of a motion for directed verdict, this Court is limited on review to the question of whether the party opposing the *792 motion offered evidence about which reasonable minds could differ. Perry v Hazel Park Harness Raceway, 123 Mich App 542, 549; 332 NW2d 601 (1983).

Article 7(c) of the contract, the "no damage for delay” clause relied upon by defendant, reads as follows:

"(c) If the contractor is delayed in the completion of the several portions or the whole of the work comprehended in the contract due to acts of the owner, acts of the other contractors in performing a contract with the owner, fire, floods, strikes, or other casualties beyond the control and without the fault or negligence of the contractor, the time for completion shall be extended for a period determined by the owner to be equivalent to the time of such delay. The contractor will not be entitled to recover the actual damages he sustains by reason of such delays. (Contingency items in the contractor’s bid are assumed to provide for continuing costs while the job is delayed.)”

We find this exculpatory clause to be valid. See Owen Construction Co, Inc v Iowa State Dep’t of Transportation, 274 NW2d 304, 306 (Iowa, 1979), and Anno: Validity and Construction of ”No Damage” Clause with Respect to Delay in Building or Construction Contract, 74 ALR3d 187, § 3, pp 203-206.

There are exceptions to the enforceability of such clauses. These exceptions infclude situations where the delay (1) was of a kind not contemplated by the parties; (2) amounted to an abandonment of the contract; (3) was caused by bad faith on the part of the contracting authority; or (4) was caused by the active interference of the other contracting party. See Owen, supra, p 307, and cases cited therein, and 74 ALR3d supra, at II, pp 203-231.

In this case, plaintiff contends that the "no *793 damage for delay” clause does not apply because there was no delay. The record shows that plaintiff completed the contract on time. We reject this contention, finding that the clause was applicable under the facts of this case. We do find, however, that a jury issue existed as to plaintiffs claim that the "delay” was of a kind not contemplated by the parties and/or that the delay was caused by the active interference of defendant.

Although plaintiff completed its contract on time, it sustained substantial additional costs. It was not permitted to work while another contractor, Darin & Armstrong, was setting presses. This interfering contractor was directed by defendant to give its work priority. The record shows that the interfering contractor was also insulated from the typical method for resolving on-the-job disputes. Darin & Armstrong answered directly to defendant, as opposed to the contractor in charge of the project. Construction projects of the kind involved in this dispute are normally handled by a tiered structure of authority. This structure is made up of the owner, a general contractor, and subconstractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwest v. Sbbi, Inc.
Court of Appeals of Arizona, 2018
MacOmb Mechanical Inc v. Lasalle Group Inc
Michigan Court of Appeals, 2015
Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)
Tricon Kent Co. v. Lafarge North America, Inc.
186 P.3d 155 (Colorado Court of Appeals, 2008)
Walter Toebe & Co. v. Department of State Highways
373 N.W.2d 233 (Michigan Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
355 N.W.2d 673, 135 Mich. App. 787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phoenix-contractors-inc-v-general-motors-corp-michctapp-1984.