Walter Toebe & Co. v. Department of State Highways

373 N.W.2d 233, 144 Mich. App. 21
CourtMichigan Court of Appeals
DecidedJuly 1, 1985
DocketDocket 76780
StatusPublished
Cited by14 cases

This text of 373 N.W.2d 233 (Walter Toebe & Co. v. Department of State Highways) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walter Toebe & Co. v. Department of State Highways, 373 N.W.2d 233, 144 Mich. App. 21 (Mich. Ct. App. 1985).

Opinion

Danhof, C.J.

Plaintiff, Walter Toebe & Company, appeals as of right from a Court of Claims judgment awarding it damages in the amount of $42,304.19, plus costs and interest, for breach of contract. The contract at issue here arose from the following circumstances.

In December, 1973, the state advertised the letting of bids for the construction of a segment approximately one mile in length on 1-275 in western Wayne County. The project involved both excavation work, which included the preparation of bridge sites and the laying of a 24-inch prestressed concrete watermain line, and the construction of five bridges. The bridge job involved the construction of one bridge over Palmer Road (S06), two bridges over Cherry Hill Road (B99 and S07), and two bridges over Fellows Creek (B04 and B06). The bridge work and the excavation work had to be coordinated since bridge construction was dependent upon the progress of the excavation work.

*25 In order to assist them in preparing bids, defendant, Department of State Highways, provided responding contractors with project plans and specifications, a form proposal, and a Critical Path Network known as CPN 370A. 1 The final contracts for the two jobs were to be work-day contracts, as opposed to calendar-day contracts, since project work was allocated in terms of the actual number of days "it is possible for the contractor to effectively carry out work”, as determined by the state and as reflected on CPN 370A.

Prospective bidders were also provided with a computer printout entitled "CP Method”. This printout was based on CPN 370A and was a "translation of the work involved in [the CPN] expressed in calendar dates”. The printout contained a detailed breakdown of the entire project with the earliest and latest start and completion dates for each project phase. The earliest projected completion date was August 18, 1975 (as noted on CPN 370A), and the latest projected completion date was April 27, 1976.

With these documents, plaintiff prepared a bid on the bridge construction job which was submitted to the state on January 6, 1974. Based upon the 213 work days allotted the winning bridge construction contractor, and working from the estimated completion date noted on CPN 370A, plaintiff derived calendar dates for scheduling its equipment and crews and then relied on those *26 calendar dates in projecting costs of labor, machinery and materials based upon when and under what circumstances the bridge sites would be accessible and the work would be performed.

Plaintiff was the low bidder on the bridge job, and Holloway Construction Co. was low bidder on the excavation job. On January 31, 1974, representatives of the plaintiff, the defendant and Holloway attended a preconstruction meeting at which various project details were settled upon before the final award of contracts. Plaintiff submitted CPN 370A as its progress schedule and it was approved by defendant as the project schedule for the final contract.

Plaintiff was awarded the bridge project contract on February 13, 1974, and was allowed to commence activity ten days later. Unknown to plaintiff, however, and sometime after the preconstruction meeting but before plaintiff was awarded the bridge contract, defendant discovered an error in the excavation job specifications it had sent to bidders on the excavation project in an amount estimated at approximately $965,000. As a result of the error, defendant was faced with the option of either reletting the excavation job or delaying the award and entering into negotiations with Holloway over the item. Defendant elected to negotiate with Holloway for a lump-sum settlement, since reletting would take several months. On February 28, 1974, Holloway entered into a $196,-000 lump-sum settlement with defendant. This meant that the usual procedure of awarding related project contracts nearly simultaneously was not followed in the instant case. The excavation contract was finally awarded to Holloway on April 26, 1974, with a job start date of May 6, approximately 21 calendar days after the anticipated project start date of April 15.

*27 The latest start date listed on the CP Method for the Fellows Creek bridges (B04 and B06) was September 19, 1974, and Toebe actually commenced work about August 29, 1974. Thus, Toebe was behind according to its own anticipated schedule, but was on schedule under the CPN, despite the delayed award of the excavation contract. Toebe was given access to the Palmer Road bridge site (S06) on June 6, 1974, while it projected April 30, 1974, as the starting date. Despite the delay in awarding the excavation contract, bridge S06 was completed in July, 1975, as originally estimated by Toebe. According to one of Toebe’s engineers, the late award "did not affect that project at all”. The lower court rejected plaintiff’s claim for damages with respect to these projects.

It had been anticipated that work on the Cherry Hill bridges (S07 and B99) would begin on October 30, 1974. Bridge S07 was not begun until July, 1975, and B99 not until September, 1975. These delays were caused by the fact that installation of the 24-inch watermain, a condition precedent to work on Cherry Hill bridge B99, depended upon the special ordering and fabrication of prestressed concrete pipes. Holloway ordered this pipe on or about February 20, 1974, but it did not arrive on site until January, 1975. Nothing in CPN 370A mentioned the ordering and delivery of the special-order pipe. In the opinion of plaintiff’s construction planning expert, Michael Hill, the ordering and delivery of the Cherry Hill watermain pipe was a major event which should have appeared on CPN 370A due to its long lead-time and its essential relation to the overall progress of the project. The lower court awarded plaintiff damages sustained as a result of this omission.

Work on the project was completed on April 12, 1976, eight months after the earliest projected *28 completion date and two weeks before the latest projected completion date. Toebe completed its contract in 168 of the 213 work days allotted it under the contract. According to Toebe, the initial delay caused by defendant’s failure to simultaneously award the contracts for the bridge and excavation jobs prevented Toebe from utilizing its equipment in the sequence represented on the CPN in the most efficient and economical manner, as Toebe had planned, in order to timely complete the project. Plaintiff appeals from the lower court’s calculation of damages on the latter projects and its refusal to award such on the former.

Plaintiff maintains that the trial court erred as a matter of law in finding that defendant was not liable for its delay in awarding the excavation contract to Holloway. Plaintiffs position is based upon three theories of recovery. First, plaintiff argues that the trial court found that defendant misrepresented that the bridge contract and the excavation contract would be let nearly simultaneously, but nevertheless ruled that defendant’s delay in awarding the excavation contract was not unreasonable. Plaintiff contests not only the finding of reasonableness but also the conclusion that defendant’s initial delay by itself had to be found unreasonable in order to be actionable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ana Jose v. Sebastian Malarz
Michigan Court of Appeals, 2019
Attorney General v. Polyone Corp
Michigan Court of Appeals, 2018
MacOmb Mechanical Inc v. Lasalle Group Inc
Michigan Court of Appeals, 2015
Muci v. State Farm Mutual Automobile Insurance
705 N.W.2d 151 (Michigan Court of Appeals, 2005)
Dollar Rent-A-Car Systems v. Nodel Construction
432 N.W.2d 423 (Michigan Court of Appeals, 1988)
Ritchie v. Michigan Consolidated Gas Co.
413 N.W.2d 796 (Michigan Court of Appeals, 1987)
Skyline Steel Corp. v. A.J. Dupuis Co.
648 F. Supp. 360 (E.D. Michigan, 1986)
Walter Toebe & Co. v. Receiver of F Yeager Bridge & Culvert Co.
389 N.W.2d 99 (Michigan Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
373 N.W.2d 233, 144 Mich. App. 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walter-toebe-co-v-department-of-state-highways-michctapp-1985.