Walter Toebe & Co. v. Receiver of F Yeager Bridge & Culvert Co.

389 N.W.2d 99, 150 Mich. App. 386, 1986 Mich. App. LEXIS 2530
CourtMichigan Court of Appeals
DecidedApril 8, 1986
DocketDocket 82394
StatusPublished
Cited by18 cases

This text of 389 N.W.2d 99 (Walter Toebe & Co. v. Receiver of F Yeager Bridge & Culvert Co.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walter Toebe & Co. v. Receiver of F Yeager Bridge & Culvert Co., 389 N.W.2d 99, 150 Mich. App. 386, 1986 Mich. App. LEXIS 2530 (Mich. Ct. App. 1986).

Opinion

T. Roumell, J.

The receiver of the F. Yeager Bridge and Culvert Company appeals as of right from the December 17, 1984, order of the St. Clair County Circuit Court in claims by Walter Toebe & Company against the assets of the insolvent corporation. Four issues are raised, three of which are without merit. We affirm the trial court’s award of damages for Projects #1 and #2. We reduce the trial court’s award of damages for Project #8, and vacate the award for Projects #3, #4 & 5, #6, and #9. The receiver did not challenge the award for Project #7, thus we do not review it.

On July 17, 1974, F. Yeager Bridge and Culvert Company, a supplier of fabricated structural steel, filed a complaint in the circuit court for voluntary dissolution because of insolvency. Yeager asserted that the federal government’s removal of price controls on steel in 1974 caused a substantial price increase which Yeager was unable to pay, thus resulting in insolvency. On September 9, 1974, the circuit court ordered dissolution and appointed James Goerlich as receiver. Before the dissolution proceedings were initiated, Yeager had entered into contracts with Toebe and five other construction companies to supply fabricated structural *392 steel. Each of these companies had contracted to construct various bridges and highways for the Michigan State Highway Commission. Each of the companies filed a claim against the Yeager assets. We note that proceedings on the claims of the remaining five claimants, each of which is similarly situated with respect to the material issues of this appeal, have been adjourned pending resolution of this appeal.

On September 13, 1974, the six claimants filed suit in Ingham County Circuit Court against the State of Michigan and the Michigan Department of State Highways and Transportation. The complaint alleged that Yeager was a subcontractor of the claimants and had been prequalified by the state. It further alleged that Yeager’s inability to perform as a result of its insolvency caused their own performance to become impossible for practical reasons in light of the then current economic conditions. On October 22, 1974, the Ingham County Circuit Court ordered that the claimants’ prime contracts with the state and their subcontracts with other prime contractors be reformed by deleting all language concerning the furnishing of fabricated structural steel. The state undertook responsibility for providing the structural steel.

In December, 1974, the six claimants filed claims with the receiver, totaling approximately $1,554,138, for damages due to delay and lost profits caused by Yeager’s breach of contract. The receiver counterclaimed against four of the claimants for approximately $431,396. The proof of claim filed by Toebe was in the amount of $857,255.07 and represented Toebe’s estimated damages for the period between January 1, 1974, and December 31, 1975. The receiver filed an objection dated July 10, 1975, alleging that Toebe sustained no damages. The receiver filed a counter *393 claim dated July 12, 1976, seeking $20,199.75 for work completed by Yeager under three contracts with Toebe.

In 1977, Toebe filed suit against the state in the court of claims for damages based on the same facts as those presented in this case. That lawsuit was still pending when trial on the merits of this case was held.

On February 10, 1977, the receiver filed against each of the six claimants the following affirmative defenses: (1) that the damage claims were barred by the prior Ingham County Circuit Court judgment; (2) that the claims were barred by the doctrine of equitable estoppel; and (3) that the claims were barred by the doctrine of election of remedies. The receiver moved for summary judgment under GCR 1963, 117.3, and the motion was granted. Toebe appealed. This Court peremptorily reversed the order of summary judgment. Docket No. 77-02321, order of December 22, 1977.

On December 8, 1980, the circuit court ordered that the receiver’s affirmative defenses be stricken because they had not been included in the receiver’s responsive pleadings as required by GCR 1963, 111.3. The circuit court further gave the receiver 30 days in which to file for leave to amend the pleadings. On April 20, 1982, the receiver’s motion for leave to amend was granted. The receiver subsequently moved for summary judgment against the six claimants, but that motion was denied.

Following a bench trial in July, 1983, the circuit court rendered an opinion on August 3, 1984, awarding $90,292.75 to Toebe and $20,199.72 to the receiver. The award to Toebe was later modified in a judgment of December 17, 1984, resulting in a sum of $87,888.40.

On appeal the receiver argues that Toebe is *394 equitably estopped from seeking damages against Yeager for breach of contract. He claims that Toebe’s obligation under the prime contracts to furnish fabricated steel was excused by the reformation of the contracts between Toebe and the state as a result of the litigation in the Ingham County Circuit Court in 1974. In the 1974 lawsuit, Toebe argued that its obligation to supply fabricated structural steel to the state was excused due to commercial impossibility (i.e., its inability to perform resulted from Yeager’s insolvency). In the instant litigation, Toebe characterizes the 1974 litigation as an effort to mitigate damages. The receiver argues that Toebe’s claim in the instant litigation necessarily assumed that Toebe’s obligation to the state was valid. According to the receiver, the inconsistent positions advocated by Toebe in these lawsuits give rise to the application of the doctrine of equitable estoppel. He claims it was not necessary that Yeager show reliance upon Toebe’s position in the earlier litigation in order to invoke equitable estoppel, because estoppel rests upon broad principles of justice. Here justice demands that Toebe be estopped from asserting its claim against Yeager.

Equitable estoppel rests upon broad principles of justice. Mertz v Mertz, 311 Mich 46; 18 NW2d 271 (1945). The doctrine of equitable estoppel has been refined to include the following elements:

" '(1) a party by representation, admissions, or silence, intentionally or negligently induces another party to believe facts; (2) the other party justifiably relies and acts on this belief; and (3) the other party will be prejudiced if the first party is permitted to deny the existence of the facts.’ Cook v Grand River Hydroelectric Power Co, Inc, 131 Mich App 821, 828; 346 NW2d 881 (1984).” Yahrling v Belle Lake Ass’n, Inc, 145 Mich App 620, 627; 378 NW2d 772 (1985).

*395 Equitable estoppel has been invoked to preclude a party who has successfully maintained one position in a lawsuit from taking an inconsistent position in a subsequent lawsuit on the same factual issues. Burgess v Holder, 362 Mich 53; 106 NW2d 379 (1960); Mertz v Mertz, supra. The assertion of inconsistent positions on factual issues in successive lawsuits may come within this doctrine, although in some circumstances collateral estoppel may be a more appropriate defense. See Stolaruk v Dep’t of Transportation,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alan Custom Homes, Inc v. Krol
667 N.W.2d 379 (Michigan Court of Appeals, 2003)
Thermo Electron Corp. v. Waste Management Holdings, Inc.
15 Mass. L. Rptr. 712 (Massachusetts Superior Court, 2003)
Backus v. Kauffman
605 N.W.2d 690 (Michigan Court of Appeals, 1999)
Brb Printing, Inc. v. Vernon G. Buchanan
106 F.3d 400 (Sixth Circuit, 1997)
BRB Printing, Inc. v. Buchanan
878 F. Supp. 1049 (E.D. Michigan, 1995)
Jim-Bob, Inc v. Mehling
443 N.W.2d 451 (Michigan Court of Appeals, 1989)
City of Holland v. Manish Enterprises
436 N.W.2d 398 (Michigan Court of Appeals, 1988)
Ombrello v. Montgomery Ward Long Term Disability Trust
415 N.W.2d 658 (Michigan Court of Appeals, 1987)
Antal v. Porretta
418 N.W.2d 395 (Michigan Court of Appeals, 1987)
Helmer v. Peoples Community Hospital Authority
411 N.W.2d 823 (Michigan Court of Appeals, 1987)
M & a Associates, Inc. v. Vcx, Inc.
657 F. Supp. 454 (E.D. Michigan, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
389 N.W.2d 99, 150 Mich. App. 386, 1986 Mich. App. LEXIS 2530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walter-toebe-co-v-receiver-of-f-yeager-bridge-culvert-co-michctapp-1986.