Thermo Electron Corp. v. Waste Management Holdings, Inc.

15 Mass. L. Rptr. 712
CourtMassachusetts Superior Court
DecidedFebruary 12, 2003
DocketNo. 013064
StatusPublished

This text of 15 Mass. L. Rptr. 712 (Thermo Electron Corp. v. Waste Management Holdings, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thermo Electron Corp. v. Waste Management Holdings, Inc., 15 Mass. L. Rptr. 712 (Mass. Ct. App. 2003).

Opinion

Brassard, J.

Plaintiff Thermo Electron Corporation (“Thermo”) brought this action to enforce a guarantee (the “Guarantee”) executed by the defendant Waste Management Holdings, Inc. (“WMH”). This matter is before the Court on the parties’ cross motions for summary judgment. For the reasons set forth below, Thermo’s motion for summary judgment is ALLOWED.

I. BACKGROUND

Pursuant to the summary judgment record, the undisputed material facts are as follows.

On December 22, 1994, Thermo and Rust International Corporation (“Rust”) entered into an Engineering, Procurement and Construction Agreement (“EPC Agreement”) concerning the construction of a de-inking pulp facility in Menominee, Michigan (the “Project”).1 At the time the EPC Agreement was entered into, Rust was a majority-owned subsidiary of WMH.2 The EPC Agreement was essentially a subcontract under which Thermo, as the general contractor on the Project, subcontracted to Rust the vast majority of the engineering, procurement and construction responsibilities relating to the Project. Pursuant to Article 10.3 of the EPC Agreement, Rust warranted to Thermo that “the design and engineering of the Project shall be performed in accordance with the standard of care, skill, and diligence as would be provided by an engineering firm experienced in supplying similar services nationally to pulp and paper producing entities.”

As a condition of its entering into the EPC Agreement with Rust, Thermo insisted that WMH execute a guarantee, the terms of which provide, in relevant part:

The Guarantor [WMH] for valuable consideration, the receipt and adequacy of which are hereby acknowledged, hereby unconditionally and irrevocably guarantees to Thermo the full, faithful and punctual payment, and not merely collection, when due, whether by acceleration or otherwise, of all sums (including all interest) which hereafter become due from Rust to Thermo under and pursuant to the [EPC] Agreement.

Guarantee at par. 3(a). The only defenses available to WMH under the Guarantee were those defenses “available to Rust and [which] have not been limited by the express provisions of the [EPC] Agreement and which have not been waived pursuant to Section 6 or 8 below.” Guarantee at par. 4. One such defense waived by WMH pursuant to Paragraph 6 of the Guarantee is [713]*713the defense of “notice of any default or termination given by Thermo to Rust under the [EPC] Agreement.” Guarantee at par. 6(vii). The Guarantee also provides that “[t]he Guarantor’s liability hereunder shall be unaffected by . . . any change in the corporate existence, structure or ownership of Rust.” Guarantee at par. 9(v).

Under Article 24 of the EPC Agreement, Rust was required to make certain payments to WMH in consideration for WMH providing the Guarantee. Thermo was to “reimburse” Rust for these payments in the amount of $250,000 for each year that the Guarantee remained in effect. EPC Agreement at Article 24. Attorney Robert Craig of WMH testified in his deposition that he could not find any evidence to suggest that Rust had made payments to WMH, as required by Article 24 of the EPC Agreement. Thermo has not made any reimbursement payments to Rust. Rust has never sent Thermo a bill, invoice or other request for reimbursement pursuant to Article 24, nor has Rust ever sent a written notice to Thermo notifying it of its failure to pay any amount required under Article 24.

On May 20, 1996, pursuant to an Asset Purchase Agreement (“APA”), Rust sold certain of its assets and assigned certain of its contracts, including the EPC Agreement, to Raytheon Engineers & Constructors, Inc. (“Raytheon”). The APA provides, in relevant part:

The Buyer [Raytheon] agrees to use commercially reasonable efforts . . . including] the provision of substitute security of like character, quality and amount, to obtain the release of the Sellers, Rust, WMX and their Affiliates from those Support Agreements indicated as ‘To Be Released” on Schedule 8.7. [Raytheon] will consult with Rust from time to time concerning the progress made with respect to any such releases, and will permit Rust reasonable participation in such process.

APA at par. 8.7. The Guarantee executed by WMH for Rust’s work on the Project is included among the “Support Agreements” referenced in Schedule 8.7 of the APA.

In November of 1996, a major component of the waste water treatment plant at the de-inkmg pulp facility failed. In early 1997, Thermo and Raytheon entered into a funding agreement to address the failure of the waste water treatment plant. The funding agreement provided that the parties would share the costs of investigation and repair, and that once the problem was addressed, Thermo and Raytheon would enter into binding arbitration to apportion liability.

On January 31, 2000, Thermo, Raytheon, and a third party commenced an arbitration proceeding to determine liability and to apportion damages for the failure of the waste water treatment plant.3 Several former Rust employees served as key witnesses over the course of the 34-day arbitration proceeding. In a written decision dated November 29, 2000, the panel of arbitrators determined that Rust had breached its design warranty to Thermo under the EPC Agreement. The panel found that mechanical completion of the Project had occurred on July 19, 1996, and that Rust’s breach of the design warranty had occurred prior to this time. Raytheon, as the successor to Rust, was ordered to pay damages to Thermo in the amount of $3,823,545. On February 15, 2001, Raytheon paid Thermo $2,567,757 of the arbitration award, leaving an outstanding balance of $1,255,788. On September 28, 2001, the United States District Court for the District of Massachusetts (Harrington, J.) issued an order confirming the arbitration award plus postjudgment interest, for a total unpaid balance of $1,364,370.18.

In May of 2001, Raytheon, which prior to that time had been acquired by Washington Group International, Inc. (“WGI”), became subject to a bankruptcy proceeding when WGI filed for bankruptcy protection in the Federal Bankruptcy Court for the District of Nevada. On June 8, 2001, Thermo made demand on WMH to pay the outstanding balance of the arbitration award, pursuant to the Guarantee executed by WMH. On July 18, 2001, Thermo filed the present action, seeking to enforce the Guarantee. On October 17, 2002, Rust and WMH entered into an “Assignment of Rights and Claims,” pursuant to which Rust assigned its right to collect any Guarantee payments due to Rust under Article 24 of the EPC Agreement. On November 26, 2002, WMH filed a motion to amend its answer to include a counterclaim for breach of contract against Thermo, due to Thermo’s alleged failure to make payments to Rust under Article 24 of the EPC Agreement.

II. DISCUSSION

A. Legal Standard for Summary Judgment

Summary judgment is appropriate where there are no issues of genuine material fact, and the moving party is entitled to judgment as a matter of law. Ng Bros. Constr., Inc. v. Cranney, 436 Mass. 638, 643-44 (2002), citing Kourouvacilis v. General Motors Corp., 410 Mass. 706, 711 (1991); see also Mass.R.Civ.P. 56(c). The moving party bears the burden of affirmatively demonstrating that there is no triable issue of material fact. Pederson v. Time, Inc., 404 Mass. 14, 17 (1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Way Construction Company
909 F.2d 259 (Seventh Circuit, 1990)
VALLEY NATIONAL BANK OF AZ. v. Kline
310 N.W.2d 301 (Michigan Court of Appeals, 1981)
Williams v. Logan
459 N.W.2d 62 (Michigan Court of Appeals, 1990)
MacKlin v. Brown
314 N.W.2d 538 (Michigan Court of Appeals, 1981)
Walter Toebe & Co. v. Receiver of F Yeager Bridge & Culvert Co.
389 N.W.2d 99 (Michigan Court of Appeals, 1986)
MacDonald v. Perry
70 N.W.2d 721 (Michigan Supreme Court, 1955)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Roels v. Drew Industries, Inc.
608 N.E.2d 411 (Appellate Court of Illinois, 1992)
T.C.T. Building Partnership v. Tandy Corp.
751 N.E.2d 135 (Appellate Court of Illinois, 2001)
Oakland County v. Allen
294 N.W. 98 (Michigan Supreme Court, 1940)
Beal v. Board of Selectmen
646 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1995)
Tuper v. North Adams Ambulance Service, Inc.
697 N.E.2d 983 (Massachusetts Supreme Judicial Court, 1998)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
TLT Construction Corp. v. A. Anthony Tappe & Associates, Inc.
716 N.E.2d 1044 (Massachusetts Appeals Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
15 Mass. L. Rptr. 712, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thermo-electron-corp-v-waste-management-holdings-inc-masssuperct-2003.