Attorney General v. Polyone Corp

CourtMichigan Court of Appeals
DecidedMay 31, 2018
Docket339754
StatusUnpublished

This text of Attorney General v. Polyone Corp (Attorney General v. Polyone Corp) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Attorney General v. Polyone Corp, (Mich. Ct. App. 2018).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

ATTORNEY GENERAL and DEPARTMENT OF UNPUBLISHED ENVIRONMENTAL QUALITY, May 31, 2018

Plaintiffs-Appellants,

v No. 339754 Ingham Circuit Court POLYONE CORPORATION, successor to M. A. LC No. 94-077813-CE HANNA COMPANY,

Defendant-Appellee.

Before: MURRAY, C.J., and SERVITTO and BOONSTRA, JJ.

PER CURIAM.

Plaintiffs, Attorney General and the Department of Environmental Quality (MDEQ), appeal as of right an opinion and order granting defendant summary disposition under MCR 2.116(C)(10) (no genuine issue of material fact). They also challenge an opinion and order granting defendant PolyOne Corporation’s request to be reimbursed for the costs of operating a disputed water treatment system. We affirm.

I. FACTS

This case concerns an upwelling of acidic water from the Dober Mine Complex in Iron County, which was the subject of a 1998 consent decree between plaintiffs and M. A. Hanna Company, to whom defendant is the successor in interest. Among other things, the consent decree required M. A. Hanna and its successors to renew an NPDES1 permit and operate an existing remedial water treatment system at the mine. The decree provided that, after defendant had completed the decree’s requirements and had been issued “a final NPDES Permit,” defendant would submit a notice of completion to the MDEQ, which would decide whether defendant had completed the decree’s requirements. If the MDEQ determined that defendant

1 NPDES stands for “National Pollutant Discharge Elimination System,” a type of permit issued through the MDEQ as part of a state-administered program under the Federal Water Pollution Control Act. Mich Farm Bureau v Dep’t of Environmental Quality, 292 Mich App 106, 108- 109; 807 NW2d 866 (2011).

-1- had done so, it would issue a Certificate of Completion. The Certificate of Completion would end defendant’s obligations under the consent decree.

On July 16, 2012, defendant sent the MDEQ a Notification of Completion and a draft final report. Ultimately, on December 6, 2012, the MDEQ issued defendant a Certificate of Completion. In its letter, the MDEQ stated that defendant would still be required to operate and maintain the NPDES permit and maintain the water treatment system at the Dober Mine Complex. This created a dispute between the parties regarding whether defendant had an obligation independent of the consent decree to do so.

On May 14, 2013, the MDEQ sent defendant a letter revoking the Certificate of Completion. Defendant responded by filing a petition for declaratory relief with the circuit court, asking the court to determine that defendant had no independent obligations to operate and maintain the water treatment system and that plaintiffs could not revoke the completion certificate. The circuit court ultimately agreed with defendant and ordered plaintiffs to pay defendant the costs of operating the system after December 2012, pursuant to stipulations between the parties.

II. CONTINUING OBLIGATIONS

Plaintiffs argue that the lower court erred by determining that the consent decree did not require defendant to continue operating the existing water remediation system after the MDEQ issued the Certificate of Completion. We conclude that plaintiffs’ position is without merit because the consent decree did not provide for ongoing maintenance obligations.

This Court reviews de novo the trial court’s decision on a motion for summary disposition. Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999). A party is entitled to summary disposition under MCR 2.116(C)(10) if “there is no genuine issue as to any material fact, and the moving party is entitled to judgment . . . as a matter of law.” A genuine issue of material fact exists if, when viewing the record in the light most favorable to the nonmoving party, reasonable minds could differ on the issue. Gorman v American Honda Motor Co, Inc, 302 Mich App 113, 116; 839 NW2d 223 (2013).

This Court interprets judgments entered by agreement of the parties in the same manner as contracts. Gramer v Gramer, 207 Mich App 123, 125; 523 NW2d 861 (1994). This Court reviews de novo the proper interpretation of an unambiguous contract. Klapp v United Ins Group Agency, Inc, 468 Mich 459, 463; 663 NW2d 447 (2003). This Court also reviews de novo the legal effects of contractual clauses. Quality Prods & Concepts Co v Nagel Precision, Inc, 469 Mich 362, 369; 666 NW2d 251 (2003).

The goal of contractual interpretation is to honor the parties’ intent and to enforce the contract’s plain terms. Davis v LaFontaine Motors, Inc, 271 Mich App 68, 73; 719 NW2d 890 (2006). This Court discerns the parties’ intent from the contract’s language. Id. If no reasonable person could dispute the meaning of the contract’s plain language, this Court must enforce that language as written. Rory v Continental Ins Co, 473 Mich 457, 468; 703 NW2d 23 (2005). We construe contractual terms in context, according to their commonly used meanings. Henderson v State Farm Fire & Cas Co, 460 Mich 348, 354; 596 NW2d 190 (1999). We must interpret a

-2- contract in a way that gives every word, phrase, and clause meaning, and must avoid interpretations that render parts of the contract surplusage. Klapp, 468 Mich at 468.

In this case, § XXVI of the consent decree states: “Upon issuance of the Certificate of Completion of Response Activities Performed Pursuant to this Decree, the Defendant’s obligations as set forth in this Decree shall terminate, except as otherwise provided herein.” Accordingly, unless an ongoing obligation is provided in the decree, defendant’s obligations end when a Certificate of Completion is issued.

Plaintiffs rely on ¶ 4.4 (defining “Existing Remedial System”) and ¶ 4.8 (defining “Operation and Maintenance Activities” or “O & M Activities”) of the decree to argue that the consent decree provided an ongoing obligation to operate and maintain the existing remedial system. Plaintiffs’ argument is not persuasive because these paragraphs are in the “definitions” section of the consent decree. Because these paragraphs are only definitions, not terms and conditions of the consent decree, they cannot constitute other obligations. Similarly, while § 3 of the consent decree states that a general goal of the consent decree is “to operate and maintain the Existing Remedial System,” this general statement of goals is not in the area of the decree that defines the parties’ obligations.

Regarding operation and maintenance, the decree provided that defendant had an obligation to “implement[] . . . the O&M Activities and sampling required by the current NPDES Permit.” (Emphasis added.) However, the then-current permit ended at some point before PolyOne renewed the permit on October 1, 2005.2 Because this provision was specifically limited to the “current” permit, it would not require defendant to engage in operation and maintenance activities past the expiration of that permit. Nowhere else does the decree mention any obligations for ongoing operation and maintenance.

Also contrary to plaintiffs’ position, the consent decree contemplates that plaintiffs may bring future actions against defendant regarding “response activities related to the facility” after issuing a Certificate of Completion. The decree provides:

Plaintiffs’ Post-Certification of Completion Reservations: Notwithstanding any other provision of this Decree except as provided in Paragraph 21.1(e), the Plaintiffs reserve, and this Decree is without prejudice to, the right to institute proceedings in this action or in a new action, or to issue an administrative order seeking to compel Defendant (1) to perform further response activities relating to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walters v. Nadell
751 N.W.2d 431 (Michigan Supreme Court, 2008)
Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Fultz v. Union-Commerce Associates
683 N.W.2d 587 (Michigan Supreme Court, 2004)
Quality Products and Concepts Co. v. Nagel Precision, Inc.
666 N.W.2d 251 (Michigan Supreme Court, 2003)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
Gramer v. Gramer
523 N.W.2d 861 (Michigan Court of Appeals, 1994)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Koenig v. City of South Haven
597 N.W.2d 99 (Michigan Supreme Court, 1999)
DAVIS v. LaFONTAINE MOTORS, INC
719 N.W.2d 890 (Michigan Court of Appeals, 2006)
Grant v. AAA Michigan/Wisconsin, Inc.
724 N.W.2d 498 (Michigan Court of Appeals, 2006)
Henderson v. State Farm Fire & Casualty Co.
596 N.W.2d 190 (Michigan Supreme Court, 1999)
Walter Toebe & Co. v. Department of State Highways
373 N.W.2d 233 (Michigan Court of Appeals, 1985)
Michigan Farm Bureau v. Department of Environmental Quality
807 N.W.2d 866 (Michigan Court of Appeals, 2011)
Moraccini v. City of Sterling Heights
822 N.W.2d 799 (Michigan Court of Appeals, 2012)
Gorman v. American Honda Motor Co.
839 N.W.2d 223 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Attorney General v. Polyone Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/attorney-general-v-polyone-corp-michctapp-2018.