Southwest v. Sbbi, Inc.

CourtCourt of Appeals of Arizona
DecidedMay 22, 2018
Docket1 CA-CV 17-0294
StatusUnpublished

This text of Southwest v. Sbbi, Inc. (Southwest v. Sbbi, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwest v. Sbbi, Inc., (Ark. Ct. App. 2018).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

SOUTHWEST CONCRETE PAVING CO., Plaintiff/Appellee/Cross-Appellant,

v.

SBBI, INC., et al., Defendants/Appellants/Cross-Appellees.

No. 1 CA-CV 17-0294 FILED 5-22-2018

Appeal from the Superior Court in Maricopa County No. CV2014-005443 The Honorable Kerstin G. LeMaire, Judge

AFFIRMED IN PART; REVERSED AND REMANDED IN PART

COUNSEL

Cheifetz Iannitelli Marcolini, PC, Phoenix By Claudio Eduardo Iannitelli, Cynthia R. Estrella, Jason Kelly Thomas Counsel for Plaintiff/Appellee/Cross-Appellant

Thompson Krone PLC, Tucson By Evan L. Thompson, Russell E. Krone Counsel for Defendants/Appellants/Cross-Appellees SOUTHWEST v. SBBI, INC., et al. Decision of the Court

MEMORANDUM DECISION

Presiding Judge Maria Elena Cruz delivered the decision of the Court, in which Judge Jennifer B. Campbell and Judge James P. Beene joined.

C R U Z, Presiding Judge:

¶1 We are asked to review several disputes between a general contractor, SBBI, Inc. (“SBBI”), and concrete paving subcontractor Southwest Concrete Paving Co. (“Southwest”). We affirm the trial court’s delay damages, extra work, and attorneys’ fee award to Southwest. We reverse and remand for further proceedings to address whether SBBI properly deducted the cost of dowel basket installation from Southwest’s contract price.

FACTUAL AND PROCEDURAL HISTORY

¶2 Southwest performed concrete paving work at the UAS Maintenance Hangar at Holloman Air Force Base in New Mexico (the “Project”). Hensel Phelps Construction Co. (“Hensel Phelps”) was the general contractor for the Project. SBBI contracted with Hensel Phelps to perform certain site work and paving work on or about February 22, 2012 (the “SBBI Contract”). SBBI then contracted with Southwest on March 12, 2012, to complete paving work (the “Southwest Contract”).

¶3 The SBBI Contract obligated SBBI to “[f]urnish and install reinforcing, dowels, and dowel baskets for the apron paving.”1 Both the Southwest Contract and Southwest’s “Final Proposal” included “drilling and installing of dowel bars” but neither mentioned dowel baskets. That same language appeared in SBBI’s Bid Proposal to Hensel Phelps.

¶4 SBBI asked Southwest to price the removal of dowel baskets from the Project plans and specifications. Southwest told SBBI that it did not include dowel baskets in its Final Proposal because it did not believe the owner would approve their use. Nonetheless, Southwest prepared a

1 Dowel baskets are a method of installing dowel bars used in certain concrete applications. Dowel baskets are placed on grade and new concrete is poured over the basket assembly. Dowel bars are installed by drilling into the vertical edge of existing concrete. The parties do not dispute that dowel baskets and dowel bars are not the same.

2 SOUTHWEST v. SBBI, INC., et al. Decision of the Court

report showing dowel basket installation would cost $106,278.00. Hensel Phelps later removed dowel baskets from the final plans and specifications and issued a change order reducing SBBI’s contract price by $106,278.00. SBBI then issued a deductive unilateral change order reducing Southwest’s contract price by the same amount.

¶5 The paving portion of the Project suffered numerous delays. The parties disputed who caused the delays; Southwest contended that SBBI failed to properly coordinate other subcontractors’ work and that one subcontractor, Bray Construction, caused significant delays through surveying and aggregate base layer errors. SBBI, on the other hand, contended Southwest was responsible for some of the delays alongside Bray. Southwest sued SBBI and its surety seeking $172,852.40 in damages based on twenty-five days of delay. Southwest also sought $21,575.64 for power washing, $11,706.56 for repairs to freshly poured concrete, and $6,875.40 to remove and replace a concrete panel, all of which it contended constituted extra work beyond the scope of the Southwest Contract.

¶6 SBBI moved for partial summary judgment, contending the unilateral deductive change order was appropriate because both the SBBI Contract and the plans and specifications included dowel baskets when the parties entered into the Southwest Contract. SBBI also contended that the Southwest Contract precluded Southwest’s delay damages claim:

Should the Subcontractor, without fault or neglect on its own part, be delayed in the commencement or completion of the Work by the fault or neglect of the Contractor or another subcontractor on the project, Subcontractor shall be entitled to a reasonable extension of time only. . . . In no event shall the Subcontractor be entitled to receive compensation or damages for any aforementioned delays except to the extent that the Contractor shall receive such compensation or damages from the Agency/Owner or another third party.

The trial court granted partial summary judgment as to the unilateral change order, finding Southwest’s Final Proposal “included dowel baskets in its bid price[.]” The court denied summary judgment on Southwest’s delay damages claim, however, finding genuine issues of material fact remained as to who had caused the delays.

¶7 Following a bench trial, the court denied Southwest’s concrete repair claim but awarded its full power washing and concrete panel replacement claims, finding both constituted extra work under the

3 SOUTHWEST v. SBBI, INC., et al. Decision of the Court

Southwest Contract. The court also awarded $40,094.20 in delay damages, finding the clause quoted above did not apply because “SBBI willfully and knowingly delayed Southwest’s ability to timely perform” by “fail[ing] to appropriately supervise Bray.”

¶8 The court also invited Southwest to submit an attorneys’ fee application and statement of costs. Southwest did so, seeking $78,124.50 in attorneys’ fees. SBBI opposed the application and filed its own attorneys’ fee application requesting a similar amount of fees. The court determined that Southwest was the successful party and awarded it $20,000 in attorneys’ fees.

¶9 SBBI timely appealed the final judgment as well as the ruling denying summary judgment on Southwest’s delay damages claim. Southwest timely cross-appealed the court’s ruling granting summary judgment to SBBI on the unilateral deductive change order. We have jurisdiction over both the appeal and cross-appeal pursuant to Arizona Revised Statutes (“A.R.S.”) section 12-2101(A)(1).

DISCUSSION

I. The Court’s Denial of Summary Judgment on Southwest’s Delay Damages Claim Is Not Appealable.

¶10 SBBI first challenges the trial court’s order denying summary judgment on Southwest’s delay damages claim. An order denying summary judgment typically is not appealable even after entry of a final judgment. Cal X-Tra v. W.V.S.V. Holdings, L.L.C., 229 Ariz. 377, 408 n.50, ¶ 105 (App. 2012). This is because such orders do not necessarily affect the final judgment; they only indicate the trial court’s belief that the issues raised should proceed to trial. Navajo Freight Lines, Inc. v. Liberty Mut. Ins. Co., 12 Ariz. App. 424, 428 (1970). We may review the order, however, if the denial is based on a purely legal issue or if the proponent reasserts the issue in a motion for judgment as a matter of law pursuant to Arizona Rule of Civil Procedure 50 or other post-trial motion. Desert Palm Surgical Grp., P.L.C. v. Petta, 236 Ariz. 568, 577, ¶ 22 (App. 2015). We review de novo whether a pure question of law precluded the denial of summary judgment. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Earnhardt's Gilbert Dodge, Inc.
132 P.3d 825 (Arizona Supreme Court, 2006)
Brand v. Elledge
419 P.2d 531 (Arizona Supreme Court, 1966)
Sanborn v. Brooker & Wake Property Management, Inc.
874 P.2d 982 (Court of Appeals of Arizona, 1994)
Navajo Freight Lines, Inc. v. Liberty Mutual Insurance
471 P.2d 309 (Court of Appeals of Arizona, 1970)
McAlister v. Citibank
829 P.2d 1253 (Court of Appeals of Arizona, 1992)
Taylor v. State Farm Mutual Automobile Insurance
854 P.2d 1134 (Arizona Supreme Court, 1993)
Phoenix Contractors, Inc. v. General Motors Corp.
355 N.W.2d 673 (Michigan Court of Appeals, 1984)
Triple R Paving, Inc. v. Broward County
774 So. 2d 50 (District Court of Appeal of Florida, 2000)
Berry v. 352 E. Virginia, L.L.C.
261 P.3d 784 (Court of Appeals of Arizona, 2011)
Pellerin Construction, Inc. v. Witco Corp.
169 F. Supp. 2d 568 (E.D. Louisiana, 2001)
Cal X-Tra v. W.V.S v. Holdings, L.L.C.
276 P.3d 11 (Court of Appeals of Arizona, 2012)
United Dairymen of Arizona v. Schugg
128 P.3d 756 (Court of Appeals of Arizona, 2006)
Fulton Homes Corp. v. BBP CONCRETE
155 P.3d 1090 (Court of Appeals of Arizona, 2007)
John C. Lincoln Hospital v. Maricopa County
96 P.3d 530 (Court of Appeals of Arizona, 2004)
National Bank of Arizona v. Thruston
180 P.3d 977 (Court of Appeals of Arizona, 2008)
Bennett v. Baxter Group, Inc.
224 P.3d 230 (Court of Appeals of Arizona, 2010)
Desert Palm Surgical Group, P.L.C. v. Petta
343 P.3d 438 (Court of Appeals of Arizona, 2015)
Lee v. ING Investment Management, LLC
377 P.3d 355 (Court of Appeals of Arizona, 2016)
Dobson Bay Club II DD, LLC v. La Sonrisa De Siena, LLC
393 P.3d 449 (Arizona Supreme Court, 2017)
American Power Products, Inc. v. CSK Auto, Inc.
396 P.3d 600 (Arizona Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Southwest v. Sbbi, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwest-v-sbbi-inc-arizctapp-2018.