Superior Steel Spring Co. v. New Era Spring & Specialty Co.

184 N.W. 440, 215 Mich. 594, 1921 Mich. LEXIS 797
CourtMichigan Supreme Court
DecidedOctober 3, 1921
DocketDocket No. 11
StatusPublished
Cited by4 cases

This text of 184 N.W. 440 (Superior Steel Spring Co. v. New Era Spring & Specialty Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Steel Spring Co. v. New Era Spring & Specialty Co., 184 N.W. 440, 215 Mich. 594, 1921 Mich. LEXIS 797 (Mich. 1921).

Opinion

Fellows, J.

Plaintiff, located at Mt. Clemens, manufactures automobile springs. • Defendant, located at Grand Rapids, is a large dealer in them. In April, 1918, by a proposal and an acceptance of it they entered into a contract for 10,000 Ford springs. The price was $1.25 each. The parties appear to have had previous business relations. At the time the contract was made plaintiff had two carloads of steel on track at Mt. Clemens which it needed the money to pay' for and got in touch with defendant. Defendant paid the entire contract price for the 10,000 springs in advance by its notes which were discounted by plaintiff at Mt. Clemens and which were paid by defendant when due. By the contract 2,500 springs were to be delivered each week for the weeks ending [596]*596April 27th, May 4th, May 11th, and May 18th. The proposal which was accepted contained the following:

“We will thus pay in advance as per the terms on the order, for both the steel or material and profit on ten thousand springs. It is done with the distinct understanding that you are to produce the springs by the date specified and on any such orders you fail to have ready for shipment, you will pay us 25 cents per spring, as a portion of our lost profit, if we so elect.”

On May 18th, the final day agreed upon for the completion of the contract, less than 2,000 springs had been delivered, and the full amount was not delivered until June 29th. About this time arrangements were made for 1,500 more springs at the same price and soon thereafter for 400 more at $1.45 each. On these later arrangements 1,908 springs were delivered. To recover the amount due for them this action is brought. It was met by the defendant by insisting that there was due to it from the plaintiff under the clause of the contract above quoted more than the amount of its indebtedness to the plaintiff, and the case in the court below turned quite largely on the question of whether the provision was one for stipulated damages or for a penalty. Other questions were raised to which we shall presently refer. Plaintiff does not deny that it failed to deliver the springs in accordance with the terms of the contract, and the testimony of its secretary fairly disclosed that such failure was due to its filling other contracts. Nor is it denied that defendant had numerous orders which it had obtained for springs canceled by reason of such failure.

Counsel for both parties have been most diligent in their research and have called to our attention a large number of our own cases together with numerous authorities from other jurisdictions. As this court [597]*597has, we think, conclusively settled the question here involved we shall confine our attention to our own cases.

In the early case of Jaquith v. Hudson, 5 Mich. 123, Mr. Justice Christiancy, who wrote for the court, in a masterly and exhaustive opinion fully considered the question and laid down the rule for the consideration of contracts of this character which have been consistently adhered to by this court ever since. After pointing out the reasons and principles which justify the courts in holding that penalties as distinguished from stipulated damages may not be enforced, he says:

“But the court will apply this principle, and disregard the express stipulation of parties, only in those cases where it is obvious from the contract before them, and the whole subject-matter, that the principle of compensation has been disregarded, and that to carry out the express stipulation of the parties, would violate this principle, which alone the court recognizes as the law of the contract.”

And in considering the classes of cases he said:

“But, secondly, there are great numbers of cases, where, from the nature of the contract and the subject-matter of the stipulation, for the breach of which the sum is provided, it is apparent to the court that the actual damages for a breach are uncertain in their nature, difficult to be ascertained, or impossible to be estimated with certainty, by reference to any pecuniary standard, and where the parties themselves are more intimately acquainted with all the peculiar circumstances, and therefore better able to compute the actual or probable damages, than courts or juries, from any evidence which can be brought before them. In all such cases, the law permits the parties to ascertain for themselves, and to provide in the contract itself, the amount of the damages which shall be paid for the breach. In permitting this, the law does not lose sight of the principle of compensation, which is the law of the contract, but merely adopts the computation or estimate of the damages made by the parties, as being the best and most' certain mode [598]*598of ascertaining the actual damage, or what sum will amount to a just compensation. The reason, therefore, for allowing the parties to ascertain for themselves the damages in this class of cases, is the same which denies the right in the former class of cases: viz., the courts adopt the best and most practicable mode of ascertaining the sum which will produce just compensation.”

After fully considering the question and taking up the case then before the' court, he said:

“The damages to arise from the breach of this covenant, from the nature of the case, must be not only uncertain in their nature, but impossible to be exhibited in proof, with any reasonable degree of accuracy, by any evidence which could possibly be adduced. It is easy to see that while the damages might be very heavy, it would be very difficult clearly to prove any. Their nature and amount could be better estimated by the parties themselves, than by witnesses, courts, or juries. ^ It is, then, precisely one of that class of cases in which it has always been recognized as peculiarly appropriate for the parties to fix and agree upon the damages for themselves.”

In Calbeck v. Ford, 140 Mich. 48, Mr. Justice Blair, speaking for the court, quoted fully from the Jaquith Case, and said:

“This case has been frequently referred to with approval, and is- a clear and authoritative statement of the rule as expounded by this court. Applying the principles above stated to the facts of this case, it appears to us that the case falls within the classes referred to in the second class, where, from the nature of the contract and the subject-matter of the stipulation, it is apparent that the actual damages for a breach are uncertain in their nature, difficult to be ascertained, or impossible to be estimated with certainty by reference to any pecuniary standard. The weight of authority is distinctly in favor of the proposition that cases like the one under consideration come within this classification.”

[599]*599And in Ross v. Loescher, 152 Mich. 386, Mr. Justice Grant said:

“In cases where it is difficult to accurately determine the damages which one party may suffer by the failure of the other to perform his contract, the parties themselves may agree upon such sum as in their judg-ment will be ample compensation for the breach.”

The following cases among others will be found to have consistently followed the rules announced in the Jaquith Case: Western Gas Construction Co. v. Dowagiac Gas & Fuel Co., 146 Mich. 119 (10 Ann. Cas. 224); City of Detroit v. Telephone Co., 135 Mich. 696; Germain

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bielski v. Wolverine Insurance
140 N.W.2d 772 (Michigan Court of Appeals, 1966)
Psaty & Fuhrman, Inc. v. Housing Authority
68 A.2d 32 (Supreme Court of Rhode Island, 1949)
Malone v. Levine
215 N.W. 356 (Michigan Supreme Court, 1927)
Ann Arbor Asphalt Construction Co. v. City of Howell
198 N.W. 195 (Michigan Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
184 N.W. 440, 215 Mich. 594, 1921 Mich. LEXIS 797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-steel-spring-co-v-new-era-spring-specialty-co-mich-1921.