§ 39O — Contracts for construction and materials; suspension, delay or interruption due to order of awarding authority; adjustment in contract price; written claim

Massachusetts § 39O
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title IIILAWS RELATING TO STATE OFFICERS
Ch. 30GENERAL PROVISIONS RELATIVE TO STATE DEPARTMENTS, COMMISSIONS, OFFICERS AND EMPLOYEES

This text of Massachusetts § 39O (Contracts for construction and materials; suspension, delay or interruption due to order of awarding authority; adjustment in contract price; written claim) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 30, § 39O (2026).

Text

Section 39O. Every contract subject to the provisions of section thirty-nine M of this chapter or subject to section forty-four A of chapter one hundred forty-nine shall contain the following provisions (a) and (b) in their entirety and, in the event a suspension, delay, interruption or failure to act of the awarding authority increases the cost of performance to any subcontractor, that subcontractor shall have the same rights against the general contractor for payment for an increase in the cost of his performance as provisions (a) and (b) give the general contractor against the awarding authority, but nothing in provisions (a) and (b) shall in any way change, modify or alter any other rights which the general contractor or the subcontractor may have against each other.

(a)The awarding au

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 39O, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/39O.