Unison Co., Ltd. v. Juhl Energy Development, Inc.

CourtDistrict Court, D. Minnesota
DecidedSeptember 17, 2018
Docket0:13-cv-03342
StatusUnknown

This text of Unison Co., Ltd. v. Juhl Energy Development, Inc. (Unison Co., Ltd. v. Juhl Energy Development, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unison Co., Ltd. v. Juhl Energy Development, Inc., (mnd 2018).

Opinion

EUNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA Unison Co., Ltd., Plaintiff, MEMORANDUM OPINION AND ORDER v. Civil No. 13-3342 ADM/BRT Juhl Energy Development, Inc., Juhl Energy, Inc., Winona Wind Holdings, LLC, Winona County Wind, LLC, Daniel Juhl, John Mitola, John Brand, Bartly J. Loethen, Audrey Loethen, and Jeff Bendel, Defendants. ______________________________________________________________________________ Boyoon Choi, Esq., Choi Capital Law PLLC, Seattle, WA, on behalf of Plaintiff. J. Matthew Berner, Esq., Droel PLLC, Bloomington, MN, on behalf of Defendants. ______________________________________________________________________________ I. INTRODUCTION This matter is before the undersigned United States District Judge for a ruling on Plaintiff Unison Co., Ltd.’s (“Unison”) Motion to Modify and Correct the Arbitration Award [Docket No. 181], Defendants Juhl Energy Development, Inc., Juhl Energy, Inc., Winona Wind Holdings, LLC, Winona County Wind, LLC, Daniel Juhl, John Mitola, John Brand, Bartly J. Loethen, Audrey Loethen, and Jeff Bendel’s (collectively, “Defendants”) Motion to Confirm Arbitration Award and Dismiss Plaintiff’s Amended Complaint with Prejudice [Docket No. 211], and Defendants’ Motion for Attorneys’ Fees and Costs [Docket No. 214]. For the reasons set forth below, Unison’s Motion is denied, Defendants’ Motion to Confirm Arbitration Award and Dismiss Plaintiff’s Amended Complaint with Prejudice is granted, and Defendants’ Motion for Attorneys’ Fees and Costs is denied. II. BACKGROUND Juhl Energy Development, Inc. (“JEDI”) and Unison are parties to contractual agreements related to the design, manufacture, and sale of Wind Turbine Generators (“WTG”) that were to be installed at a community wind farm project in Winona County, Minnesota. Am.

Compl. [Docket No. 14] ¶¶ 1, 18-22. In its December 17, 2013 Amended Complaint, Unison alleged 16 claims which largely arose from an April 14, 2010 Financing Agreement. Id. ¶¶ 31–132. On May 26, 2015, the Eighth Circuit ordered that Unison’s claims be arbitrated. Unison Co., Ltd. v. Juhl Energy Dev., Inc., 789 F.3d 816, 821 (8th Cir. 2015). This case was stayed pending the arbitration.1 Order [Docket No. 101]. Both Unison and JEDI submitted claims and defenses in arbitration. Unison claimed that JEDI fraudulently changed its ownership structure without Unison’s consent. Berner Aff.

[Docket No. 194] Ex. S (“Final Award”) at 5. JEDI claimed that it was defrauded because the WTGs Unison sold lacked an essential cold weather package for the production of wind power in Minnesota. Id. at 4. Arbitration hearings were held in July 2017 and January 2018. Id. On March 26, 2018, the arbitrators (the “Panel”) issued a Final Award. Id. The Panel concluded “that neither party had proven any of the claims that they asserted.” Id. at 6. The Panel further found that “both Unison and JEDI thought that the WTGs were suitable for use on the Winona Project, and neither party exercised sufficient and reasonable diligence to confirm such belief.” Id. Because the parties were “mutually mistaken . . . that the WTGs were suitable

1 Although only Unison and JEDI were parties to the contracts with the arbitration clause, the parties conceded that claims against all named defendants should be submitted to arbitration so all of the claims could be heard in a single forum. See Unison, 789 F.3d at 817 n.1. 2 for use on the Winona Project, the Panel has concluded that the most appropriate and equitable remedy for both parties is the rescission of all of the contracts between the parties.” Id. Unison was responsible for dismantling the WTGs. Id. at 6–7. If Unison declined to remove the WTGs, it was ordered to pay JEDI $350,000 to cover JEDI’s cost of

decommissioning. Id. Further, “[i]n order to more nearly place the parties in the position they were in prior to the rescinded contracts,” Unison was ordered to pay JEDI $285,000 for construction and related costs, plus $76,000 for additional freight costs resulting from packaging problems caused by Unison. Id. at 7. Those costs were subject to 5% interest from December 5, 2013 to May 15, 2018, for a total amount of $442,720. Id. Thus, if Unison elected to dismantle the WTGs, it was ordered to pay JEDI $442,720. If Unison declined to dismantle the WTGs, it was ordered to pay JEDI $792,720. On March 27, 2018, Defendants moved to Confirm the Arbitration Award and Dismiss Plaintiffs’ Amended Complaint [Docket No. 130], and on May 7, 2018, Defendants moved for

Attorneys’ Fees and Costs [Docket No. 148]. The Motions were denied as premature since Unison had declared its intention to challenge the arbitration award under § 12 of the Federal Arbitration Act (“FAA”), which provides that any party may move to vacate, modify, or correct an arbitration award within 90 days of the initial arbitration award. See Order [Docket No. 178]. On June 22, 2018, Unison filed its Motion to Modify and Correct the Arbitration Award [Docket No. 181]. Unison raises two arguments in support of its Motion. First, Unison contends that the Final Award should be modified because it disproportionally places the financial burden on Unison, which is contrary to the Panel’s equitable decision in rescinding the contracts.

Second, Unison asserts that the Final Award should be vacated because the Panel exceeded its 3 power by granting an award outside the scope of the parties’ contractual agreements. On June 28, 2018, Defendants filed its Response [Docket No. 192] to Unison’s Motion. Defendants argue that Unison’s Motion should be denied because it failed to first seek the same relief from the Panel. Defendants also argue that Unison arguments in support of modifying or

vacating the Final Award lack merit. On July 2, 2018, Defendants renewed their Motions to Confirm the Arbitration Award and for Attorneys’ Fees and Costs. III. DISCUSSION A. Motion to Modify and Correct the Arbitration Award Unison argues that the Final Award should either be vacated under § 10 or modified under § 11 of the FAA. Defendants respond that a party seeking to vacate, modify, or correct an arbitration award must first seek such relief from the arbitrators before filing a motion in district

court. Since Unison failed to do so, Defendants contend that Unison’s arguments challenging the Final Award have been waived. Defendants also challenge Unison’s arguments on the merits, asserting that none of Unison’s contentions constitute cognizable grounds for vacating or modifying the Final Award. The FAA provides for judicial review to confirm, vacate, or modify arbitration awards. Hall Street Assocs., L.L.C. v. Mattel, Inc., 552 U.S. 576, 582 (2008). Vacateur of an arbitration award is governed by § 10 of the FAA, which “authorizes a district court to vacate an arbitration award” under the following circumstances: (1) where the award was procured by corruption, fraud, or undue means; (2) where there was evident partiality or corruption in the arbitrators, 4 or either of them; (3) where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced; or (4) where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made. Med. Shoppe Int’l, Inc. v. Turner Invs., 614 F.3d 485, 488 (8th Cir. 2010) (quoting 9 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Sheila Ann Mead v. Brent Mead
974 F.2d 990 (Eighth Circuit, 1992)
Christopher C. McGrann v. First Albany Corporation
424 F.3d 743 (First Circuit, 2005)
Borchert v. Maloney
581 N.W.2d 838 (Supreme Court of Minnesota, 1998)
Johnny's, Inc. v. Njaka
450 N.W.2d 166 (Court of Appeals of Minnesota, 1990)
Beck v. Spindler
99 N.W.2d 684 (Supreme Court of Minnesota, 1959)
David Co. v. Jim W. Miller Construction, Inc.
444 N.W.2d 836 (Supreme Court of Minnesota, 1989)
Unison Co., Ltd. v. Juhl Energy Development, Inc.
789 F.3d 816 (Eighth Circuit, 2015)
Inter-City Gas Corp. v. Boise Cascade Corp.
845 F.2d 184 (Eighth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Unison Co., Ltd. v. Juhl Energy Development, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/unison-co-ltd-v-juhl-energy-development-inc-mnd-2018.