Willoughby Roofing & Supply Co. v. Kajima International, Inc.

598 F. Supp. 353, 1984 U.S. Dist. LEXIS 21430
CourtDistrict Court, N.D. Alabama
DecidedDecember 6, 1984
DocketCiv. A. CV82-L-5556-NE
StatusPublished
Cited by47 cases

This text of 598 F. Supp. 353 (Willoughby Roofing & Supply Co. v. Kajima International, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willoughby Roofing & Supply Co. v. Kajima International, Inc., 598 F. Supp. 353, 1984 U.S. Dist. LEXIS 21430 (N.D. Ala. 1984).

Opinion

MEMORANDUM OPINION *

LYNNE, Senior District Judge.

This matter comes before the Court on the plaintiff’s application for judgment. The plaintiff’s fraud, breach of contract, and related claims have been submitted to an arbitration panel at the insistence of the defendant. The arbitrators, having considered those claims and having found them meritorious, have awarded the plaintiffs $41,091.25 in compensatory damages. In addition, because they found the defendant guilty of willful misrepresentations of *355 material fact concerning the transaction at issue, the arbitrators have awarded the plaintiffs the further sum of $108,908.75 in punitive damages. However, the defendant, once the champion of the need for arbitration in this case, now expresses dissatisfaction with the results achieved by that process. Having once argued strenuously that the arbitration clause contained in the parties’ contract required arbitration of all of the plaintiff’s claims, 1 the defendant now seeks to qualify its previous position. Now, for the first time, the defendant argues that the arbitration panel lacked authority to consider the plaintiff’s claims for punitive damages. On this basis, the defendant has filed a motion to vacate the award of punitive damages. 2 Because the Court is satisfied that the arbitrators’ award was within the broad scope of their authority under the contract and under law, the defendant’s motion will be overruled and judgment entered in accordance with the arbitral award.

BACKGROUND

This action began when the plaintiff, Willoughby Roofing & Supply Company (“Willoughby Roofing”), filed suit in the Circuit Court of Madison County, Alabama. The complaint sought compensatory and punitive damages for breach of contract, fraud, misrepresentation, and breach of the duty of good faith and fair dealing by the defendant, Kajima International, Inc. (“Kajima”). These claims emanated from a contract between the parties whereby plaintiff, as subcontractor, was to construct and install a roof on a building for Kajima, the general contractor on a certain construction project in Huntsville, Alabama. Willoughby Roofing had allegedly prepared its bid on the roofing job in reliance on certain representations by Kajima as to the plans and specifications that would have to be followed in constructing the roof. Following acceptance of Willoughby Roofing’s bid, however, those plans and specifications were materially altered by Kajima, so much so that the cost to the plaintiff of completing the contract would have been substantially higher than anticipated. Therefore, Willoughby sought to renegotiate the contract price or to submit a new bid. Despite the fact that Willoughby had gone to considerable expense in preparing to fulfill the contract under the original specifications, Kajima chose instead to cancel the contract and engage another subcontractor to do the work.

It was at this point that the state court action was filed. Shortly thereafter, the case was removed to this Court by the defendant. Following removal, the defendant filed a motion for a stay of the proceedings pending arbitration. This motion was based upon the arbitration clause of the contract between the parties:

Section 6.07. Arbitration.
All claims, disputes, and other matters in question arising out of, or relating to, this Agreement or a Work Assignment or the breach thereof, except with respect to matters for which the Architect’s decision shall be final and binding as provided in this Agreement, shall be resolved by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

This arbitration clause is, of course, quite broad, and it evinces an intent of the parties to vest the arbitrators with authority to decide virtually any claim that could arise in relation to the contract and its *356 performance. Indeed, as the defendant itself aptly argued in support of its motion for a stay pending arbitration,

... the arbitration procedure applies to all disputes arising in connection with the subcontract. It would have been difficult, if not impossible, for the parties to have drafted a broader arbitration provision. This broad language, coupled with the national policy favoring a liberal construction of arbitration agreements, makes it clear that the disputes involved in this case are well within the scope of the arbitration agreement. 3

Convinced that the arbitration clause did indeed cover all of the plaintiffs claims, including the claims for compensatory and punitive damages for fraud, see generally Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395, 87 S.Ct. 1801, 18 L.Ed.2d 1270 (1967), the Court granted the stay. An arbitration panel was selected, and the plaintiff's claims were presented to that panel. Finding those claims to be meritorious, the panel awarded the plaintiff $150,000 in unspecified damages.

At this point, the defendant first objected that the arbitrators had awarded punitive damages and that to do so was beyond their authority. In order to clarify the issue, the Court on April 26, 1984, ordered that the award be resubmitted to the same arbitration panel for an explicit breakdown of the claims for which damages were provided. Subsequently, on August 21, 1984, the panel issued the following award: 4

... [W]e the undersigned Arbitrators find the following facts:
1. That KAJIMA INTERNATIONAL, INC., did in fact breach its contract to WILLOUGHBY ROOFING & SUPPLY CO., INC., and that the compensatory damages suffered by WILLOUGHBY ROOFING & SUPPLY CO., INC., were $41,091.25.
2. We further find that KAJIMA INTERNATIONAL, INC., did make misrepresentations of material facts, that these facts were willfully made to deceive WILLOUGHBY ROOFING & SUPPLY CO., INC., that these misrepresentations were made by KAJIMA INTERNATIONAL, INC., to be relied upon by WILLOUGHBY ROOFING & SUPPLY CO., INC., and that in fact WILLOUGHBY ROOFING & SUPPLY CO., INC., did rely on these misrepresentations and that WILLOUGHBY ROOFING & SUPPLY CO., INC., suffered damages as a result of this reliance.
For these wrongful acts of KAJIMA INTERNATIONAL, INC., we find that KAJIMA INTERNATIONAL, INC., should pay punitive damages of $108,-908.15.

Therefore, Arbitrators, AWARD as follows:

A. Award compensatory damages in the amount of $41,091.25 to be paid by KAJIMA INTERNATIONAL, INC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ahmed v. Oak Management Corp.
Supreme Court of Connecticut, 2023
Kitchens v. TURQUOISE PROPERTIES GULF, INC.
70 So. 3d 377 (Court of Civil Appeals of Alabama, 2010)
Birmingham News Co. v. Horn
901 So. 2d 27 (Supreme Court of Alabama, 2004)
RP Industries, Inc. v. S & M EQUIP. CO.
896 So. 2d 460 (Supreme Court of Alabama, 2004)
Cavalier Mfg., Inc. v. Jackson
823 So. 2d 1237 (Supreme Court of Alabama, 2001)
Aguilera v. Palm Harbor Homes, Inc.
2001 NMCA 091 (New Mexico Court of Appeals, 2001)
McKee v. Hendrix
816 So. 2d 30 (Court of Civil Appeals of Alabama, 2001)
Polin v. Kellwood Co.
103 F. Supp. 2d 238 (S.D. New York, 2000)
Davis v. Prudential Securities, Inc.
59 F.3d 1186 (Eleventh Circuit, 1995)
J. Alexander Securities, Inc. v. Mendez
17 Cal. App. 4th 1083 (California Court of Appeal, 1993)
Pisciotta v. Shearson Lehman Bros., Inc.
629 A.2d 520 (District of Columbia Court of Appeals, 1993)
Matter of Prudential-Bache Securities and Depew
814 F. Supp. 1081 (M.D. Florida, 1993)
Maxus, Inc. v. Sciacca
598 So. 2d 1376 (Supreme Court of Alabama, 1992)
HL FULLER CONST. v. Indus. Dev. Bd.
590 So. 2d 218 (Supreme Court of Alabama, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
598 F. Supp. 353, 1984 U.S. Dist. LEXIS 21430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willoughby-roofing-supply-co-v-kajima-international-inc-alnd-1984.