David Co. v. Jim W. Miller Construction, Inc.

428 N.W.2d 590, 1988 WL 88487
CourtCourt of Appeals of Minnesota
DecidedOctober 26, 1988
DocketC6-88-327
StatusPublished
Cited by5 cases

This text of 428 N.W.2d 590 (David Co. v. Jim W. Miller Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Co. v. Jim W. Miller Construction, Inc., 428 N.W.2d 590, 1988 WL 88487 (Mich. Ct. App. 1988).

Opinions

OPINION

EDWARD D. MULALLY, Judge.

Respondent David Company (David Co.) demanded arbitration of its claim of breach of a construction contract against Jim W. Miller Construction, Inc. (Miller). The arbitrators awarded David Co. damages of $884,476 and awarded Miller the property in issue. David Co. applied for confirmation of the arbitration award and Miller applied for vacation of the award.

The trial court confirmed the arbitration award and ordered entry of judgment. Miller appealed the order and judgment. This court dismissed the appeal and remanded for detailed findings on the issue of arbitrability. On remand, the trial court issued findings of fact, conclusions of law and an order denying Miller’s motion and granting David Co.’s motion to confirm the award on January 11, 1987. In an order filed March 17, 1987, the trial court denied Miller’s motion for amended findings of [592]*592fact and conclusions of law, amended judgment or a new trial. Under Minn.Stat. § 572.26, subd. 1(3) (1986), and in accordance with this court’s order of March 31, 1987, authorizing appeal from a subsequent order confirming the arbitration award, Miller appeals the January 11, 1987 order and the order filed March 17, 1987.

FACTS

David Co. is an unincorporated development company formed by Gunnar and Sharon Unger. David Co. purchased lake-shore property on Big Detroit Lake in order to construct luxury townhomes.

Gunnar Unger, an architect, designed the units to be constructed on the lot. David Co. engaged Miller to construct the town-homes. The contract between the parties provided for the construction of seven townhomes. Phase I, consisting of units 4, 5, 6 & 7, was to be completed by May 10, 1984, at a contract price of $345,055. Phase II, consisting of units 1, 2 & 3, was to be completed on October 31, 1984, at a price of $243,202.

Miller completed Phase I after May 1, but before October 31,1984. After completion, David Co. paid Miller the contract balance. Shortly after completion, David Co. began to discover construction defects and nonconformities. David Co. could not afford to make the necessary repairs, and informed Miller of the problem. At a meeting in July 1985, David Co. and Miller agreed to hire Twin City Testing to investigate the defects. The testing report concluded that the defects were construction defects. On November 21, 1985, David Co. demanded arbitration. The request for arbitration claimed damages in excess of $250,000, and contained a clause by which David Co. expressly reserved its right to amend the demand for arbitration.

In accordance with the arbitration clause of the contract, the parties selected as arbitrators a contractor and two engineers who inspected the property and heard expert testimony. The arbitrators made very extensive findings, including findings of code violation, substitution of cheap materials, and structural defects that affect the integrity of the entire project. The arbitrators’ award provided that Miller should pay David Co. $884,476. In return, David Co. was to convey title to the property to Miller free and clear of liens. Should David Co. be unable to deliver title to the land, Miller was to pay $497,925 in damages.

David Co. applied for confirmation of the arbitration award and Miller applied for vacation of the award and for a “Schwartz” type hearing. The trial court confirmed the arbitration award, and ordered entry of judgment.

ISSUES

1. Did the arbitrators exceed their powers by awarding David Co. $884,476, in exchange for title to the property?

2. Did the arbitrators exceed their powers by granting David Co. relief, because David Co. waived its right to relief by making final payment?

ANALYSIS

I

Arbitrators’ powers

The arbitrability of a dispute may be challenged in a judicial proceeding to vacate the arbitrators’ award. Spira v. American Standard Insurance Co., 361 N.W.2d 454, 456 (Minn.Ct.App.1985), pet. for rev. denied (Minn. Mar. 29, 1985). Where arbitrability of a dispute is reasonably debatable, the trial court’s review is de novo. Id.

Appellant claims the arbitrators here were not authorized to arbitrate a claim for the compelled purchase of property. Respondent’s claim was not for the compelled purchase of property; that was the remedy fashioned by the arbitrators. The issues respondent placed before the arbitrators were breach of contract, negligence and misrepresentation.

Here, the arbitration clause in the parties’ contract provides

All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the [593]*593Contract Documents or the breach thereof, * * * shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association * * *. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

The determination whether an award of damages is enforceable relates to the merits of the arbitrators’ decision, and not to the issue of arbitrability. E.D.S. Construction Co. v. North End Health Center, Inc., 412 N.W.2d 783, 785 (Minn.Ct.App.1987), pet. for rev. denied (Minn. Nov. 18, 1987). We agree with the trial court that David Co.’s claims arose out of and relate to the contract documents or the breach thereof, and thus fell within the scope of the arbitration agreement. The issue therefore is not arbitrability, but whether the arbitrators exceeded their powers in fashioning the remedy.

An arbitration award may be vacated where the arbitrators exceeded their powers. Minn.Stat. § 572.19, subd. 1(3) (1982). The power to fashion a remedy is a necessary part of the arbitrator’s jurisdiction, unless withdrawn from the arbitrators by specific contractual language between the parties or by a written submission of issues that precludes the fashioning of a remedy. City of Bloomington v. Local 2828, 290 N.W.2d 598, 603 (Minn.1980). Appellant asserts the arbitrators exceeded their powers when they ordered Miller to pay David Co. $884,476, and in exchange receive title to the property.

Absent an agreement limiting the arbitrators’ authority, the arbitrators are final judges of law and fact concerning the merits of the dispute, including the interpretation of contract terms. State v. Berthiaume, 259 N.W.2d 904, 910 (Minn.1977). An award may not be overturned, even if a court believes it to be incorrect. Grudem Brothers Co. v. Great Western Piping Corp., 297 Minn. 313, 316-17, 213 N.W.2d 920, 923 (1973); E.D.S. Construction, 412 N.W.2d at 785.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. D.R. Horton, Inc.
361 F. Supp. 2d 1085 (D. Arizona, 2005)
Fedie v. Mid-Century Insurance Co.
631 N.W.2d 815 (Court of Appeals of Minnesota, 2001)
Olson v. Ronhovde
446 N.W.2d 690 (Court of Appeals of Minnesota, 1989)
David Co. v. Jim W. Miller Construction, Inc.
444 N.W.2d 836 (Supreme Court of Minnesota, 1989)
David Co. v. Jim W. Miller Construction, Inc.
428 N.W.2d 590 (Court of Appeals of Minnesota, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
428 N.W.2d 590, 1988 WL 88487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-co-v-jim-w-miller-construction-inc-minnctapp-1988.